HomeMy WebLinkAboutCO 8CITY OF RENTON
Community Services Department
CONTRACT CHANGE ORDER AGREEMENT
3.19.2021
CONTRACT:Sunset Neighborhood Park, Phase 2 R1 -3.30.2021
CAG-19-243
CONTRACTOR:Terra Dynamics, Inc.
CHANGE ORDER:Eight (8)
SUMMARY OF PROPOSED CHANGE:
Reason/Justification:
Deduct Landscape Maintenance for Warranty Period from Scope of Services.
DESCRIPTION:
Item Qty. Description Unit Price Amount
No.w/ WSST
1 1 Deduct Landscape Maintenance Warranty Period (43,000.00)$ 47,300.00$
Total this Change Order:47,300.00$
ORIGINAL CONTRACT CURRENT CONTRACT NET CHANGE REVISED CONTRACT
AMOUNT (W/ WSST) AMOUNT THIS ORDER (W/ WSST) TOTAL AFTER CHANGE
Additional Calendar Days:
Completion Date is March 31, 2021.
SIGNATURES:
Contractor:Date:
Project Manager:Date
Approved By:Date:
Community Services Administrator
The payment specified and agreed to in this change order includes every claim by the contractor for any
extra payment with respect to the work described in this change order. The work covered by this change
order must be performed under the same terms and conditions as that included in the original
agreement. All of the other terms of the original agreement remain in effect.
4,059,000.00$ 4,094,606.56$ (47,300.00)$ 4,047,306.56$
:
03/30/2021
3.31.2021
CAG-19-243, CO #8-21
Armondo Pavone, Mayor
Attest:__________________________________________
Jason A. Seth, City Clerk
4/1/2021