Updated Proposed Timeline below:
Lease (F) 12/31/2021
Zoning Submit (F) 7/7/2021
Zoning Approved (F) 12/30/2021
BP Submit (F) 1/21/2022
BP Approved (F) 3/31/2022
CX Start (F) 4/4/2022
CX Complete (F) 5/31/2022
As an alternative, we are also talking to the same property owner about ground space only for
collocating antennas on a wood PSE utility pole– this is our back up..
As an aside, there is extensive work being done to this building, and they have redesigned their remodel
which required the additional permits – which we have heard are approved now.
The need for the cell-on-wheels is directly tied to the ability of CITC to finish their project.
The cell-on-wheels is only necessary due to the fact that CITC has not started their project, and that the
reason they have not started their project is due to circumstances outside of their control (and not due to
waiting on permit issuance).
Please let me know if you need any additional information.
Kim Allen
Senior Vice President, Land Use Entitlements and Strategic Planning
Wireless Policy Group LLC
Office: 425-628-2666
Kim.allen@wirelesspolicy.com
From: Alex Morganroth <AMorganroth@Rentonwa.gov>
Date: Wednesday, May 19, 2021 at 1:16 PM
CAUTION: This email originated from outside the City of Renton. Do not click links, reply or open
attachments unless you know the content is safe.