Department of Natural Resources and Parks ● Wastewater Treatment Division
Environmental Services ● 201 S Jackson Street, MS KSC-NR-5500
Seattle, WA 98104-3855
DETERMINATION OF NONSIGNIFICANCE
TITLE OF PROPOSAL: Loop® Compost Pilot Project at South Treatment Plant
DESCRIPTION OF PROPOSAL: The King County Wastewater Treatment Division proposes to construct a temporary pilot composting
system at King County’s South Treatment Plant (STP) which will further process Class B Loop® biosolids – a product of the wastewater
treatment process – into a Class A Loop compost. The regulatory designation of Class A biosolids allows for unrestricted use as a soil
amendment. The composting system will be built and operated within the boundaries of the County’s South Treatment Plant in Renton,
WA The project will operate for three to five years, after which it will be decommissioned.
LOCATION OF PROPOSAL, INCLUDING STREET ADDRESS, IF ANY:. The proposed project will be located in Renton WA, at
1200 Monster Road SW, within the existing STP site.
SEPA Responsible Official: Mark Isaacson
Position/Title: Director, King County Wastewater Treatment Division
Address: 201 S Jackson Street, MS KSC-NR-5500
Seattle, WA 98104-3855
Date: Signature:
Proponent and Lead Agency: King County Department of Natural Resources and Parks
Wastewater Treatment Division
Contact Person: Jacob Sheppard, Environmental Planner
King County Wastewater Treatment Division
201 S Jackson Street, MS KSC-NR-5500
Seattle, WA 98104
phone: (206) 477-5395; e-mail: jacob.sheppard@kingcounty.gov
Issue Date: January 15, 2021
The State Environmental Policy Act (SEPA) lead agency for this proposal has determined that it does not have a probable significant
adverse impact on the environment. An environmental impact statement is not required under RCW 43.21C.030(2)(c). This decisio n was
made after review of a completed environmental checklist, the environmental reports listed in Section A.8 of the environmental checklist,
and other information on file with the lead agency. This information is available to the public on request.
This Determination of Nonsignificance (DNS) is issued under WAC 197-11-340 (2); the lead agency will not act on this proposal for
18 days from the issue date. Comments must be submitted by February 1, 2021. Submit comments to Katherine Fischer, Supervisor,
Environmental Services, King County Wastewater Treatment Division, 201 S Jackson Street, MS KSC -NR-5500, Seattle, WA 98104-
3855. Contact Jacob Sheppard, Environmental Planner, at (206) 477-5395 or jacob.sheppard@kingcounty.gov for questions or information
on how to submit comments electronically.
The King County Wastewater Treatment Division recently submitted a permit application for this project to the Puget Sound Clean Air
Agency, which provides the opportunity for appeal. Therefore, there is no administrative appeal of this DNS pursuant to RCW 43.21C.075,
WAC 197-11-680, KCC 20.44.120, and King County Public Rule 7-4-1. The public rule may be viewed at
http://www.kingcounty.gov/about/policies/rules/utilities/put741pr.aspx or contact Jacob Sheppard, Environmental Planner, at (206) 477-
5395 or jacob.sheppard@kingcounty.gov to obtain a copy of the rule.
[Statutory authority: RCW 43.21C.110. 84 -05-020 (Order DE 83-39), §197-11-970, filed 2/10/84, effective 4/4/84.]
DocuSign Envelope ID: 4192BB43-050B-4A75-BDB4-E07E1D659CA3
1/12/2021
EXHIBIT 5
RECEIVED
Clark Close 04/19/2021
PLANNING DIVISION
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
Department of Natural Resources and Parks
Wastewater Treatment Division
King Street Center, KSC-NR-0505
201 South Jackson Street
Seattle, WA 98104
Environmental Checklist
for
Loop® Compost Pilot Project at South Treatment Plant
December 23, 2020
Prepared in compliance with the State Environmental Policy Act (SEPA)
(RCW 43.21C), the SEPA Rules (WAC 197-11), and Chapter 20.44 King
County Code, implementing SEPA in King County procedures.
This information is available in accessible formats upon request at
(206) 477-5371 (voice) or 711 (TTY).
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
December 2020 1
ENVIRONMENTAL CHECKLIST
A. BACKGROUND
1. Name of proposed project, if applicable:
Loop® Compost Pilot Project at South Treatment Plant
2. Name of applicant:
King County Department of Natural Resources and Parks
Wastewater Treatment Division
3. Address and phone number of applicant and contact person:
King County Department of Natural Resources and Parks
Wastewater Treatment Division
Environmental Services Unit
KSC-NR-0505
201 S. Jackson Street
Seattle, WA 98104
CONTACT: Jacob Sheppard, Environmental Planner
Phone: (206) 477-5395
Email: jacob.sheppard@kingcounty.gov
4. Date checklist prepared:
December 23, 2020
5. Agency requesting checklist:
King County Department of Natural Resources and Parks
Wastewater Treatment Division
6. Proposed timing or schedule (including phasing, if applicable):
Project construction is scheduled to occur in 2022. The proposed pilot-scale
composting facility is temporary, with an expected operation period of approximately
five years, or according to the term of its temporary land use permit from the City of
Renton.
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 2
7. Do you have any plans for future additions, expansions, or further activity
related to or connected with this proposal? If yes, explain.
Once operational, information from the project will be used to demonstrate proof of
concept and develop a business case for composting, develop reliable sources of
feedstocks and bulking agents, conduct product and process optimization, develop
markets and distribution channels, build community support and collect data to inform
the capital project process for a potential larger, permanent facility which would be
located off-site. Such a facility would be subject to a separate SEPA process in the
future.
8. List any environmental information you know about that has been prepared, or
will be prepared, directly related to this proposal.
• Dispersion Modeling Protocol, King County South Treatment Plant Loop
Compost Pilot Project. Prepared by Jacobs Engineering and HDR Engineering
on behalf of King County Wastewater Treatment Division (2020). W3X90702
[Technical Memorandum].
9. Do you know whether applications are pending for governmental approvals of
other proposals directly affecting the property covered by your proposal? If yes,
explain.
None known
10. List any government approvals or permits that will be needed for your proposal,
if known.
City of Renton
• Temporary Use Permit
• Grading Permit
Puget Sound Clear Air Agency (PSCAA)
• Notice of Construction
Washington Department of Ecology (Ecology)
• Certificate of Compliance
11. Give brief, complete description of your proposal, including the proposed uses
and the size of the project and site. There are several questions later in this
checklist that ask you to describe certain aspects of your proposal. You do not
need to repeat those answers on this page.
King County proposes to construct a temporary pilot composting system at King
County’s South Treatment Plant (STP) which will further process Class B Loop®
biosolids into a Class A Loop compost. The facility is designed to demonstrate the
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 3
practicability of composting of Class B Loop biosolids mixed with bulking agents,
such as wood chips and yard clippings, at various ratios to produce Class A biosolids.
The proposed pilot project will enable the County to demonstrate the business case for
a full-scale Loop composting facility and evaluate various blends of feedstock to
determine the optimal conditions for proceeding into a full-scale facility. This project
is the first step to address a current lack of redundancy in the County’s biosolids
program. The project will operate for three to five years, after which it will be
decommissioned.
Approximately 0.91 acres will be used for the project. The project will have no
permanent above ground structures.
Biosolids are a soil amendment (a natural soil conditioner and fertilizer replacement)
that are made by cleaning the water that arrives at County wastewater treatment plants
(WWTPs). The County’s biosolids, which are branded as “Loop,” are Class B, which
have some detectable pathogens and therefore restrictions for use. At the WWTPs, the
County’s anaerobic digester tanks use naturally occurring bacteria and other
microorganisms to break down the waste and kill disease-causing pathogens. These
microorganisms transform the solids into a renewable, nutrient-rich, fully digested
resource called biosolids. Most biosolids are used directly on farms and forests to
improve crop yield and soil health. But Class B biosolids can also be mixed with
bulking material such as yard clippings and wood chips and processed further into a
compost. Biosolids compost has a Class A regulatory designation from the
Washington State Department of Ecology (Ecology), which allows for unrestricted
use, just like any other retail garden product.
Loop is used directly on farms and forests, with 25 percent applied to western
Washington forests and 75 percent transported and applied to eastern Washington
farms. However, transport of Loop can be suspended by road conditions on the
Cascade mountain passes, which results in a rapid backlog of trucks filled with
biosolids, especially in winter. The County has limited emergency storage options.
The County is looking into composting as a local alternative for recycling Loop
because it would provide distribution options during inclement winter weather as well
as generate a useful local soil amendment with a low energy input requirement.
The completed facility will employ a covered aerated static pile (CASP) technology
using a bunker-style primary composting operation to fit within the limited available
area at STP. The proposed facility will be configured with a series of functional areas,
each equipped to perform the function of a full-scale compost facility. The functional
areas include areas for receipt, mixing, composting, curing, and screening. Each
functional area will be encircled with interlocking stacked concrete blocks that provide
a confining barrier, or bunker, to the respective contents of each area. Some of the
bunkers may be covered by an open-sided fabric structure that is not fully enclosed but
is intended to protect the bunkers from rainfall. The active composting and curing
areas are anticipated to have three blowers in nearly constant operation.
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 4
The facility will function in a series of batches based on the amount of material
received from the delivery of a single truckload of Loop from one of the County’s
treatment plants. The facility will be equipped to receive up to one truck per week but
could receive material less frequently, if desired. Each Loop delivery will initiate a
two-month-long process. Mixing of biosolids with bulking material will occur
immediately upon receipt of a load of biosolids, directly followed by placement of the
mixed material into an active composting bunker. This is intended to occur on the
same day as receipt. Doing so will reduce the propensity of odorous emissions. The
mixer will be powered by electricity. Active composting will last 28 days per batch.
Curing, which will occur after active composting, will last an additional 28 days. Once
curing is complete, the compost will be screened using a trommel to remove large-
diameter material from the finished product. The finished product area will be sized to
accommodate approximately 400 cubic yards of material, or approximately four to
seven batches of processed material depending on the bulking ratio employed.
During the active composting and curing processes, temperature will be managed by
forced aeration. The aeration system will run according to a system of temperature
sensors and programmable controls for optimal process conditions and odor control,
according to desired testing parameters, industry standards and best management
practices. The aeration system is automatically reversing, drawing cool air into the
compost piles either from the top or bottom. The negative aeration process will draw
air from beneath the pile, into air ducts placed on-grade beneath the pile, and out to a
manifold directing the collected air to an odor-scrubbing biofilter. The positive
aeration process will draw cool air into the fan and push it into the plenum on the floor
and up through the pile, which is covered by a biolayer of finished compost or wood
chips for odor and temperature control.
Material will be moved between functional areas using a front-end loader.
12. Location of the proposal. Give sufficient information for a person to understand
the precise location of your proposed project, including a street address, if any,
and section, township, and range, if known. If a proposal would occur over a
range of area, provide the range or boundaries of the site(s). Provide a legal
description, site plan, vicinity map, and topographic map, if reasonably available.
While you should submit any plans required by the agency, you are not required
to duplicate maps or detailed plans submitted with any permit applications
related to this checklist.
The proposed project is located in Renton WA, at 1200 Monster Road SW. The
project will occupy King County Parcel Numbers 2423049097 and 2423049006,
which are located in NE Quarter-Section, Section 24, Township 23 North, Range 9
East.
The project is located on the STP property. See Figure 1 below.
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 5
Figure 1. Site and vicinity map
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 6
B. ENVIRONMENTAL ELEMENTS
1. Earth
a. General description of the site
(circle one): Flat, rolling , hilly, steep slopes, mountainous, other __________.
b. What is the steepest slope on the site? (approximate percent slope)?
The steepest slopes on the site are approximately 25%.
c. What general types of soils are found on the site? (for example, clay, sand,
gravel, peat, muck)? If you know the classification of agricultural soils,
specify them and note any agricultural land of long-term commercial
significance and whether the proposal results in removing any of these soils.
In general, the site overlies previous fill consisting of silty sand with gravel to a
depth of approximately 25 feet. The fill layer is underlain by native sand, silt,
and gravel to a depth of approximately 80 feet.
Neither the project site nor its surroundings contain agricultural land of long-
term commercial significance.
d. Are there surface indications or history of unstable soils in the immediate
vicinity? If so, describe.
No.
e. Describe the purpose, type, total area, and approximate quantities and total
affected area of any filling, excavation, and grading proposed. Indicate
source of fill.
The project will occupy approximately 0.91 acre of the approximately 72-acre
STP property. Minor grading will be required. Minor excavation will be
required, including for shallow trenches that will be cut and filled in order to
install utility lines on the site. Subsequent backfill will consist of native soil to
the greatest extent possible, supplemented by clean fill when required by permit
conditions or engineering specifications.
f. Could erosion occur as a result of clearing, construction, or use? If so,
generally describe.
Some localized erosion could occur during clearing and construction. However,
erosion control measures will be used to minimize the potential for this to occur.
See Section B.1.h below for typical Best Management Practices (BMPs) and
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 7
other measures that could be utilized to minimize the potential for erosion.
Erosion is not expected to occur as a result of the completed facility.
g. About what percent of the site will be covered with impervious surfaces
after project construction (for example, asphalt or buildings)?
The project site is currently composed entirely of impervious surfaces, and will
remain so after project construction.
h. Proposed measures to reduce or control erosion, or other impacts to the
earth, if any:
Temporary erosion and sedimentation control measures will be employed
throughout project construction, including prior to all clearing, excavation,
filling, grading, and other soil-disturbing activities in the project area. These
control measures will be identified in the project plans and construction
specifications and will be implemented as required by the City of Renton,
Ecology, and other permitting agencies.
Typical measures that may be used include installing filter fabric fences and
other sediment barriers, placing silt traps in storm drain inlets, covering soil
stockpiles and exposed soils, and using settling facilities to prevent sediment
from leaving the site.
Additional best management practices (BMPs) and other measures could include
the following:
• Designation of personnel to inspect and maintain temporary erosion and
sediment control measures
• Use of appropriate means such as stabilized entrances and wheel washes
to minimize tracking of sediment onto roadways by construction vehicles
• Regular street cleaning for mud and dust control
• Disposing of excess excavated soil at an approved disposal site as soon as
practical
• Restoration of disturbed areas by repaving or replanting as soon as
practical after construction is completed
2. Air
a. What types of emissions to the air would result from the proposal during
construction, operation, and maintenance when the project is completed? If
any, generally describe and give approximate quantities if known.
Project construction will involve temporary, mobile source air emissions (NOx,
VOC, CO, PM10, PM2.5), including diesel exhaust from construction
equipment and dust generated by earth-moving activities. The exhaust emissions
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 8
will be intermittent and spread across the project area. They are not expected to
affect attainment of air quality standards in the project area.
Potential emissions from the composting operations include odors, volatile
organic compounds (VOCs), hazardous air pollutants (HAPs) and toxic air
pollutants (TAPs), greenhouse gases (GHG), and fugitive dust which includes
particulate matter with diameter <10 micrometers (PM10) and particulate matter
with diameter <2.5 micrometers (PM2.5). There will be minor emissions of
nitrogen oxides (NOx), carbon monoxide (CO) and sulfur dioxide (SO2) from
the combustion of diesel in a 38 kW (51 Hp) diesel engine used to power the
trommel screen. The trommel screen is expected to operate for less than four
hours each week. Front-end loader operations and material deliveries will also
generate occasional minor diesel exhaust emissions.
The facility will go through new source review (NSR) with the local permitting
authority, the Puget Sound Clean Air Agency (PSCAA). As part of NSR, the
County will submit a Notice of Construction (NOC) application and receive an
Order of Approval issued by PSCAA under PSCAA Regulation I, Article 6 prior
to commencement of construction. To minimize emissions and comply with all
state and local emission standards, the process will use Best Available Control
Technology (BACT) and BACT for TAPs (tBACT).
Facilities submitting a NOC application are also required to complete a review
of the air quality impacts from TAPs to demonstrate that the proposed project
does not have the potential to adversely affect the health of people in the
surrounding community. Washington Administrative Code (WAC) 173-460-150
lists the regulated TAPs along with their respective averaging period, acceptable
source impact level (ASIL), small quantity emission rates (SQER), and de
minimis emission values.
Potential emissions of VOC, PM10 and PM2.5 are estimated to be below NSR
exemption levels (2.0 tons per year, 0.75 ton per year, and 0.5 ton per year
respectively) per WAC 173-400-110(5)(a)(i). Of the 33 TAPs identified as being
potential emissions from the facility, 11 exceeded their de minimis thresholds.
The de minimis values are defined as the maximum level of emissions that do
not pose a threat to human health or the environment. If emissions of a given
TAP from a source do not exceed the associated de minimis emission values,
then that TAP is exempt from further NSR evaluation.
None of the TAPs exceeded their SQER, so dispersion modeling of TAP
emissions is not required to demonstrate compliance with the ASIL. See Table 1
for a summary of emissions from facility operations, and Appendix A for King
County greenhouse gas emissions worksheets.
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 9
Table 1. Emissions summary
Pollutant Potential Emissions
Odors 52,808 OU/min
Volatile organic compounds (VOCs) 347 lb/year
Hazardous and toxic air pollutants (HAPs and TAPs) 1,421 lb/year
Particulate matter with a diameter <10 micrometers (PM10) 3.1 lb/year
Particulate matter with a diameter <2.5 micrometers (PM2.5) 0.5 lb/year
Nitrogen oxides (NOx) 78 lb/year
Carbon monoxide (CO) 87 lb/year
Sulfur dioxide (SO2) 0.02 lb/year
Greenhouse Gases (GHG) 2,820 lb/year CO2eq
Notes:
OU/min = odor units per minute
lb/year = pounds per year
b. Are there any off-site sources of emissions or odor that may affect your
proposal? If so, generally describe.
There are no known off-site sources of air emissions or odors that may affect the
project.
c. Proposed measures to reduce or control emissions or other impacts to air, if
any:
During construction, BMPs will be implemented to control dust. Types of BMPs
that will be used may include street sweeping, watering exposed soil surfaces,
and covering soil stockpiles to help minimize the amount of fugitive dust and
particulate pollution to the surrounding areas. Construction equipment-related
emissions will be reduced by requiring proper maintenance of equipment, using
electrically-powered equipment where practical, and avoiding prolonged idling
of vehicles and equipment.
To minimize emissions during operation and comply with all state and local
emission standards, the process will use BACT and tBACT. In addition, a
biofilter will be operated and maintained according to recommendations
provided by industry experts, in order to minimize odors. Odor management is
vital to the success of a compost facility. No compost facility is expected to be
odor free. However, WAC 173-350-040 requires the facility to not violate the
regulating air authority’s emission standards or ambient air quality standards at
the property boundary.
Composting is an aerobic process; when the process lacks sufficient oxygen it
can be classified as hypoxic or anoxic. In the hypoxic or anoxic states, odorous
volatile compounds are produced including alcohols, acids, H2S, and NH3.
Maintaining aerobic conditions requires management of oxygen content and
temperature in the compost piles. Aeration to manage temperature – keeping
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 10
piles uniform in temperature and cooler than 65 degrees Celsius – will also
provide sufficient fresh air to stay well above the threshold of 2 parts per million
of oxygen required to maintain aerobic conditions. The facility’s aeration
equipment will be designed and operated to provide a constant, uniform aeration
capacity of 5 cubic feet per minute per cubic yard of material.
Process air from the active composting and curing areas will be direct through a
biofilter, which will scrub volatile organic compounds (VOCs) and odorous air
contaminants. The biofilter will be oversized compared to industry standards
and will provide an empty-bed retention time (the average time process air will
spend getting through the volume occupied by the biofilter material) of 75
seconds, whereas the industry standard is 60 seconds.
Air quality modeling indicates that additional detectable odors beyond the STP
property line will be very infrequent, of short duration, and unlikely to be
discernable from other odors in the area.
3. Water
a. Surface Water:
1) Is there any surface water body on or in the immediate vicinity of the
site (including year-round and seasonal streams, saltwater, lakes,
ponds, or wetlands)? If yes, describe type and provide names. If
appropriate, state what stream or river it flows into.
Springbrook Creek, a Type S water (shoreline of the state), is located east
of STP. Waterworks Gardens, located north of the project site across an
access road, is a complex of connected wetponds and a Category II
wetland that provides stormwater detention and treatment for much of the
STP property, and outlets into Springbrook Creek.
2) Will the project require any work over, in, or adjacent to (within 200
feet) the described waters? If yes, please describe and attach available
plans.
The project will not require any work over, in, or within 200 feet of water
bodies.
3) Estimate the amount of fill and dredge material that would be placed
in or removed from surface water or wetlands and indicate the area of
the site that would be affected. Indicate the source of fill material.
No fill or dredge material will be placed in or removed from surface
waters or wetlands.
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 11
4) Will the proposal require surface water withdrawals or diversions?
Give general description, purpose, and approximate quantities if
known.
The project will not require surface water withdrawals or diversions.
5) Does the proposal lie within a 100-year floodplain? If so, note location
on the site plan.
The project does not lie within a 100-year floodplain.
6) Does the proposal involve any discharges of waste materials to surface
waters? If so, describe the type of waste and anticipated volume of
discharge.
The project will not involve any discharges of waste materials to surface
waters.
b. Ground Water:
1) Will ground water be withdrawn, from a well for drinking water or
other purposes? If so, give a general description of the well, proposed
uses, and approximate quantities withdrawn from the well. Will water
be discharged to ground water? Give general description, purpose,
and approximate quantities if known.
No groundwater will be withdrawn as part of the project, and no water will
be discharged to groundwater.
2) Describe waste material that will be discharged into the ground from
septic tanks or other sources, if any (for example: Domestic sewage;
industrial, containing the following chemicals...; agricultural; etc.).
Describe the general size of the system, the number of such systems,
the number of houses to be served (if applicable), or the number of
animals or humans the system(s) are expected to serve.
No waste material related to the project will be discharged into the ground
from septic tanks or other sources.
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 12
c. Water Runoff (including storm water):
1) Describe source of runoff (including storm water) and method of
collection and disposal, if any (include quantities, if known). Where
will this water flow? Will this water flow into other waters? If so,
describe.
At present, the surface water in the project area flows into STP’s
stormwater conveyance and treatment system, which includes multiple
biofiltration swales, catch basins, pipes, a large pump station, and a series
of wetponds and wetlands in Waterworks Gardens.
During construction, the primary source of water runoff onto and off of
work areas will be stormwater. Stormwater drainage patterns may be
altered during construction due to surface alterations. Stormwater runoff
during construction will be managed to prevent runoff from leaving the
site using storm water BMPs such as those described below in Section
B.3.d.
When the project is completed, stormwater from the project site will be
collected and routed to the wastewater influent stream at STP. Stormwater
flow in the vicinity will not be affected.
2) Could waste materials enter ground or surface waters? If so,
generally describe.
During construction, the County will implement BMPs to prevent
introduction of potential contaminants into ground and surface waters,
which could include:
• Storing fuels and other potential contaminants in secured
containment areas
• Containing equipment, materials, and wash water associated with
construction
• Conducting regular inspections, maintenance, and repairs of fuel
hoses, hydraulically operated equipment, lubrication equipment, and
chemical/petroleum storage containers
• Maintaining spill containment and clean up material at the
construction site
• Establishing a communication protocol for handling spills
After the facility is completed, runoff will be contained on-site and
prevented from entering local water bodies prior to treatment.
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 13
3) Does the proposal alter or otherwise affect drainage patterns in the
vicinity of the site? If so, describe.
The project will not alter drainage patterns in the vicinity of the site.
d. Proposed measures to reduce or control surface, ground, and runoff water,
and drainage pattern impacts, if any:
Stormwater management during and after construction will comply with all
applicable permits and government approvals, including requirements and
guidelines from the City of Renton, King County, and Ecology. In particular,
King County will meet performance standards included within the 2017 City of
Renton Surface Water Manual and City Amendments. Stormwater management
BMPs will be used during construction to control stormwater runoff. Examples
of typical BMPs that could be used during construction are presented in Section
B.1.h above.
The completed facility will include stormwater containment measures to direct
runoff to the wastewater influent stream at STP.
4. Plants
a. Check or circle types of vegetation found on the site:
deciduous tree: alder , maple , aspen, other : ash, sweet gum, crabapple, pear,
cottonwood
evergreen tree: fir , cedar , pine, other: Norway spruce
shrubs: salal, Oregon grape
grass
pasture
crop or grain
orchards, vineyards, or other permanent crops
wet soil plants: cattail, buttercup, bulrush, skunk cabbage, other
water plants: water lily, eelgrass, milfoil, other types of vegetation
b. What kind and amount of vegetation will be removed or altered?
The project site currently contains landscaping that will need to be removed.
Plants to be removed include 13 ornamental cedar trees.
c. List threatened or endangered species known to be on or near the site.
There are no threatened or endangered plants known to be on or near the site.
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 14
d. Proposed landscaping, use of native plants, or other measures to preserve
or enhance vegetation on the site, if any:
No landscaping is currently proposed as part of the project.
e. List all noxious weeds and invasive species known to be on or near the site.
No noxious weeds are known to be located on the site. However, tansy ragwort
and spotted knapweed have been documented on neighboring parcels. Invasives
on the project site are limited to sporadic, herbaceous species.
5. Animals
a. List any birds and other animals which have been observed on or near the
site or are known to be on or near the site.
The project site does not include significant habitat for birds or mammals,
although small mammals and some urban-adapted bird species are expected to
occur in the general area and at the site. Washington Department of Fish and
Wildlife’s Priority Habitats and Species list does not list priority species on the
site. However, the Black River Riparian Forest, just north of the treatment plant
property, contains the largest document great blue heron rookery in the Puget
Sound Region. The Black River wetlands and Springbrook Creek also provide
habitat numerous other waterfowl species, as well as a variety of fish species
(Chinook, coho, resident coastal cutthroat, steelhead, and winter steelhead).
b. List any threatened or endangered species known to be on or near the site.
Chinook and steelhead are federally-listed, threatened species that occur in the
Springbrook Creek segment of the Black River, which is also federally-
designated as critical habitat.
c. Is the site part of a migration route? If so, explain.
The project site is within the Pacific Flyway avian migration route.
d. Proposed measures to preserve or enhance wildlife, if any:
Impacts to wildlife are not anticipated as a result of this proposal; therefore, no
special measures to preserve wildlife are proposed.
e. List any invasive animal species known to be on or near the site.
None known
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 15
6. Energy and Natural Resources
a. What kinds of energy (electric, natural gas, oil, woodstove, solar) will be
used to meet the completed project's energy needs? Describe whether it will
be used for heating, manufacturing, etc.
The completed facility will use electricity to operate the mixer, and aeration
system. The front-end loader and mobile trommel will be diesel-powered.
b. Would your project affect the potential use of solar energy by adjacent
properties? If so, generally describe.
The completed facility will not affect the potential use of solar energy by
adjacent properties.
c. What kind of energy conservation features are included in the plans of this
proposal? List other proposed measures to reduce or control energy
impacts, if any:
Blower fans will be equipped with variable speed motors to save energy when
less aeration is needed.
7. Environmental Health
a. Are there any environmental health hazards, including exposure to toxic
chemicals, risk of fire and explosion, spill, or hazardous waste, that could
occur as a result of this proposal? If so, describe.
1) Describe any known or possible contamination at the site from
present or past uses.
The STP site was developed in 1965 as a wastewater treatment facility,
and prior, was undeveloped land. There are five leaking underground
storage tanks (LUSTs) located within the vicinity of the project site, but
none are located in the project area and there is no confirmed groundwater
contamination associated with the LUSTs.
2) Describe existing hazardous chemicals/conditions that might affect
project development and design. This includes underground
hazardous liquid and gas transmission pipelines located within the
project area and in the vicinity.
There are no hazardous chemicals or conditions in the vicinity that might
affect project development or design.
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 16
3) Describe any toxic or hazardous chemicals that might be stored, used,
or produced during the project's development or construction, or at
any time during the operating life of the project.
Construction-related materials such as fuel and hydraulic fluid will be
stored and used on site during construction. BMPs will be implemented
during construction to minimize the potential for spills or mechanical
failures to occur, and to minimize the potential for adverse effects from
hazardous chemicals to workers or nearby residents.
The completed facility will process Class B biosolids, which may contain
low levels of pathogens. These pathogens do not pose a risk to human
health unless ingested. The composting process will reduce or eliminate
these pathogens from the finished product.
4) Describe special emergency services that might be required.
None anticipated
5) Proposed measures to reduce or control environmental health
hazards, if any:
As described in items B.1.h and B.3.d. above, BMPs and other measures
will be used to avoid or contain and control any accidental spills or
releases of hazardous materials during project construction. Project plans
and construction specifications include measures to safely handle and
dispose of contaminated materials. No sources of contaminated materials
are known to be on the project site. However, if unexpectedly encountered
during construction, contaminated materials will be removed from the
work area and transported to a permitted disposal site. The contractor will
prepare a health and safety plan as a deliverable for the proposed project
prior to the start of construction. This plan will comply with all applicable
health regulations and will detail measures to control environmental health
hazards.
The composting process generates enough heat that combustion is possible
if temperature is not managed effectively. The facility will operate using
industry best practices to maintain an appropriate and safe temperature in
the compost piles.
Facility staff will adhere to the same environmental safety requirements
and guidelines, prescribed by King County, as the rest of the STP facility.
These requirements and guidelines include BMPs for the proper handling
of Class B biosolids, as well as BMPs for storage, handling, disposal, and
clean-up of hazardous materials.
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 17
b. Noise
1) What types of noise exist in the area which may affect your project
(for example: traffic, equipment, operation, other)?
Noise in the project area will not affect the project.
2) What types and levels of noise would be created by or associated with
the project on a short-term or a long-term basis (for example: traffic,
construction, operation, other)? Indicate what hours noise would
come from the site.
Construction noise may exceed existing background noise levels at times.
Noise levels will vary depending on the specific equipment used for
particular activities. Based on previous construction projects, typical noise
levels can be expected to range from about 70 to 90 dBA measured at a
distance of 50 feet from the source. Throughout project construction,
short-term, intermittent construction related noise may include engine and
mechanical equipment noises associated with the use of heavy equipment
such as bulldozers, excavators, cranes, haul trucks, generators, chainsaws,
and air compressors.
Construction-related noises will be limited to construction hours allowable
by the City of Renton’s noise control code. If work outside of daytime
working hours is required, an application for a variance will be submitted
to the City of Renton.
In the completed facility, mechanical equipment will generate noise during
the day and night. None of the noises generated on the completed facility
will exceed the City of Renton’s maximum permissible sound level for the
site’s zoning or that of nearby receiving sites.
3) Proposed measures to reduce or control noise impacts, if any:
All construction and facility operation activities will be consistent with the
City of Renton noise control code. All impacts from noise generated by
construction will be short-term and temporary in nature. Construction
BMPs will be used to minimize construction noise and could include:
• Using effective vehicle mufflers, engine intake silencers, and engine
enclosures, and shutting off equipment when not in use
• Using temporary noise barriers around stationary equipment
• Positioning noise-generating equipment in the project area so that it
is as far away as possible from sensitive receptors
• Notifying residents and businesses near the project site of upcoming
noisy construction activities
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 18
• 24-hour construction hotline to promptly respond to questions and
complaints
Sound generated by facility operations will be attenuated and muffled by
vegetation and the distance to receptors. Because the maximum predicted
acoustical level of noise at the property line of adjacent properties is below
code limits, no additional mitigation is proposed.
8. Land and Shoreline Use
a. What is the current use of the site and adjacent properties? Will the
proposal affect current land uses on nearby or adjacent properties? If so,
describe.
The site is currently occupied by King County’s South Treatment Plant.
Adjacent properties include commercial and industrial sites. The proposed
project will not affect current land uses on adjacent or nearby properties.
b. Has the project site been used as working farmlands or working forest
lands? If so, describe. How much agricultural or forest land of long-term
commercial significance will be converted to other uses as a result of the
proposal, if any? If resource lands have not been designated, how many
acres in farmland or forest land tax status will be converted to nonfarm or
nonforest use?
Historic aerial photographs suggest the project area was part of a farm between
the late 1930s and late 1950s. The site has not been used as agricultural land
since that time, and is not designated as agricultural land of long-term
commercial significance. The project will not result in conversion of farm or
forest land to a nonfarm or nonforest use.
1) Will the proposal affect or be affected by surrounding working farm
or forest land normal business operations, such as oversize equipment
access, the application of pesticides, tilling, and harvesting? If so,
how:
No.
c. Describe any structures on the site.
The area of STP that contains the project site currently includes numerous
industrial buildings associated with wastewater treatment, administrative
buildings, and access roads.
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 19
d. Will any structures be demolished? If so, what?
No.
e. What is the current zoning classification of the site?
Industrial Heavy (IH)
f. What is the current comprehensive plan designation of the site?
The site is located within the designated Employment Area (EA).
g. If applicable, what is the current shoreline master program designation of
the site?
The proposed project will occur outside of the shoreline zone.
h. Has any part of the site been classified as a critical area by the city or
county? If so, specify.
The project site is within two City of Renton-designated geologic hazard areas: a
moderate Coal Mine Hazard Area and a high Seismic Hazard Area.
i. Approximately how many people would reside or work in the completed
project?
Approximately 140 people currently work at STP. The proposed facility will not
result in additional staff being employed.
j. Approximately how many people would the completed project displace?
None
k. Proposed measures to avoid or reduce displacement impacts, if any:
None
l. Proposed measures to ensure the proposal is compatible with existing and
projected land uses and plans, if any:
Construction of the project will not conflict with existing land use plans and
policies; however, a number of permits or approvals will be required. The City
of Renton is being consulted to ensure that the project is compatible with
existing and projected land uses and plans.
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 20
The City of Renton anticipates that the surrounding area will continue to be
used for commercial and light industrial uses during the temporary duration of
the project. Therefore, the completed facility is not expected to be incompatible
with existing or future land use plans for the area.
m. Proposed measures to ensure the proposal is compatible with nearby
agricultural and forest lands of long-term commercial significance, if any:
None
9. Housing
a. Approximately how many units would be provided, if any? Indicate
whether high, middle, or low-income housing.
None
b. Approximately how many units, if any, would be eliminated? Indicate
whether high, middle, or low-income housing.
None
c. Proposed measures to reduce or control housing impacts, if any:
None
10. Aesthetics
a. What is the tallest height of any proposed structure(s), not including
antennae; what is the principal exterior building material(s) proposed?
Temporary structures for the project will be no higher than approximately one
story. Exterior building materials will include asphalt, concrete blocks, and
fabric overhead coverings.
b. What views in the immediate vicinity would be altered or obstructed?
Views of the site will remain generally the same. The size of the overall Plant
will not change and character of the site will continue to be that of an industrial
operation, and the project site will not be visible from outside of the Plant
property.
c. Proposed measures to reduce or control aesthetic impacts, if any:
There are no measures proposed to address aesthetic impacts of the project.
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 21
11. Light and Glare
a. What type of light or glare will the proposal produce? What time of day
would it mainly occur?
Project construction will take place largely during daylight hours. Temporary
site lighting may be used at the beginning and end of work days during
construction when daylight hours are short.
The completed project will require sufficient light for safety and security,
similar in nature to the existing STP site. Outside areas that are currently lit at
night at STP include entry and exit driveways, truck staging and parking areas,
and building entrances.
b. Could light and glare from the finished project be a safety hazard or
interfere with views?
No. The site is surrounded by buildings to the west, east, and south with similar
exterior lighting.
c. What existing off-site sources of light or glare may affect your proposal?
None
d. Proposed measures to reduce or control light and glare impacts, if any:
All exterior lights will be focused or shielded as necessary to cast light only in
areas that require it and to minimize light spilling onto neighboring properties.
12. Recreation
a. What designated and informal recreational opportunities are in the
immediate vicinity?
Waterworks Gardens is a King County-owned eight-acre park located north of
the project area. The main feature of the gardens are wetlands established to
provide storm water treatment for STP.
Other recreational opportunities in the general vicinity include Springbrook
Trail, a 2.3-mile trail that parallels the eastern boundary of the 50-acre STP site
until it crosses Oakesdale Ave SW and enters the Black River Riparian Forest
and Wetland. The Black River Riparian Forest is a 93-acre refuge that is popular
for birdwatching.
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 22
b. Would the proposed project displace any existing recreational uses? If so,
describe.
No.
c. Proposed measures to reduce or control impacts on recreation, including
recreation opportunities to be provided by the project or applicant, if any:
None
13. Historic and Cultural Preservation
a. Are there any buildings, structures, or sites, located on or near the site that
are over 45 years old listed in or eligible for listing in national, state, or
local preservation registers located on or near the site? If so, specifically
describe.
No buildings, structures, or sites that are listed in or eligible for listing in
preservation registers have been identified on the project site, or within 0.5 miles
of the project site.
Two unevaluated historic properties are within or adjacent to the project site.
The first is South Treatment Plant itself, described as “Renton Sewage
Treatment Plant” in the Washington Department of Archaeology and Historic
Preservation (DAHP) database, which was constructed in 1965, and is therefore
over 45 years old. South Treatment Plant was recorded on a DAHP Historic
Property Inventory form in 2010, but no determination has been made regarding
eligibility for listing in the National Register of Historic Places (NRHP). An
update to this inventory form may be required by DAHP. The second
unevaluated historic property is the Graphic Packaging International factory,
located adjacent to STP at 601 Monster Road SW. The building, constructed in
1956, was recorded in the Historic Property Inventory as part of an import of
county assessor data, but no recommendation has been made regarding its
eligibility for listing in the NRHP. However, that building is outside of the view-
shed of the project, and no impact is anticipated.
b. Are there any landmarks, features, or other evidence of Indian or historic
use or occupation? This may include human burials or old cemeteries. Are
there any material evidence, artifacts, or areas of cultural importance on or
near the site? Please list any professional studies conducted at the site to
identify such resources.
Numerous cultural resources investigations have been conducted in the recent
past associated with construction projects at STP. No landmarks, features, or
other evidence of Indian or historic use have been identified on the project site
during these investigations; however, there are several nearby sites, including
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 23
precontact- and historic-era sites. Historic resources are railroad grades and
historic debris scatters. Precontact resources are village sites, including sites
where human burials have been identified. Three of the village sites have been
determined eligible for listing on the NRHP. Based on proximity of the project
site to recorded archaeological sites, its location above the former Black River
channel and near the confluence with the Green (White) River, and the presence
of ethnographic sites within the vicinity, it is likely that people used the
landforms contained within the project area during the precontact and
ethnographic periods. However, due to the previous development of STP, which
involved large-scale earth work, the likelihood for intact archaeological sites is
diminished.
c. Describe the methods used to assess the potential impacts to cultural and
historic resources on or near the project site. Examples include consultation
with tribes and the department of archeology and historic preservation,
archaeological surveys, historic maps, GIS data, etc.
The project was screened by the King County Historic Preservation Program for
the presence of cultural and historic resources within the project area and the
probability of an inadvertent discovery of cultural resources during project
construction. This screening included a review of historic registers, databases
including the DAHP records database (“WISAARD”), historic maps and
reports, and predictive GIS modeling. Environmental Science Associates also
conducted an in-depth review of existing cultural resources reports and
databases.
d. Proposed measures to avoid, minimize, or compensate for loss, changes to,
and disturbance to resources. Please include plans for the above and any
permits that may be required.
King County will prepare an inadvertent discovery plan (IDP) for project
construction. The IDP will provide guidance to contractors for identifying
potential cultural resources, and establish procedures to follow in the event of
the unanticipated discovery of potential cultural resources in order to protect the
discovery until it can be assessed by a professional archaeologist.
14. Transportation
a. Identify public streets and highways serving the site or affected geographic
area, and describe proposed access to the existing street system. Show on
site plans, if any.
The site is bordered by SW Grady Way and I-405 to the south, Oakesdale
Avenue SW to the east and north, and Monster Road SW to the west. The
primary access to the northern portion of STP, where the project will be
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 24
developed, is via SW 7th Street. However, there are additional driveways located
off of Monster Road SW, Longacres Drive SW, and SW Grady Way.
b. Is the site or affected geographic area currently served by public transit? If
so, generally describe. If not, what is the approximate distance to the
nearest transit stop?
The 50-acre STP site is served by public transit. King County Metro stops for
the 161 and 280 are located on SW Grady Way and the Tukwila Station for
Amtrak and the Sounder Train are located a mile to the south of STP.
c. How many additional parking spaces would the completed project or non-
project proposal have? How many would the project or proposal eliminate?
The completed project will not include additional parking spaces, nor will it
eliminate any existing parking spaces.
d. Will the proposal require any new or improvements to existing roads,
streets, pedestrian, bicycle, or state transportation facilities, not including
driveways? If so, generally describe (indicate whether public or private).
No such improvements are included as part of this proposal.
e. Will the project use (or occur in the immediate vicinity of) water, rail, or air
transportation? If so, generally describe.
No.
f. How many vehicular trips per day would be generated by the completed
project or proposal? If known, indicate when peak volumes would occur
and what percentage of the volume would be trucks (such as commercial
and nonpassenger vehicles). What data or transportation models were used
to make these estimates?
Project construction will require the delivery of equipment and materials by
truck, generating approximately 275 truck trips. Once complete, small amounts
of wood chips and yard waste will be regularly transported on-site and finished
compost product will regularly be transported off-site. Given the existing
vehicular activity on the STP property, including daily biosolids hauling, and the
industrial nature of the project vicinity, there will be negligible changes in
vehicular traffic as a result of the project.
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 25
g. Will the proposal interfere with, affect or be affected by the movement of
agricultural and forest products on roads or streets in the area? If so,
generally describe.
No.
h. Proposed measures to reduce or control transportation impacts, if any:
Long-term transportation impacts are not anticipated; therefore, mitigation
measures have not been developed.
15. Public Services
a. Would the project result in an increased need for public services (for
example: fire protection, police protection, public transit, health care,
schools, other)? If so, generally describe.
No.
b. Proposed measures to reduce or control direct impacts on public services, if
any:
None
16. Utilities
a. Circle utilities currently available at the site:
electricity , natural gas , water , refuse service , telephone , sanitary sewer ,
septic system, other________
b. Describe the utilities that are proposed for the project, the utility providing
the service, and the general construction activities on the site or in the
immediate vicinity which might be needed.
The project will primarily involve short extensions of the existing utilities
located on site. Electric and natural gas service on the site is provided by Puget
Sound Energy, water and refuse service is provided by City of Renton, and
wastewater service is provided by King County.
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 26
C. SIGNATURE
The above answers are true and complete to the best of my knowledge. I understand
that the lead agency is relying on them to make its decision.
Signature:
Katherine Fischer, Environmental Programs Managing Supervisor
King County WTD
12/23/20
Date Submitted:
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 27
Appendix A. King County greenhouse gas emissions worksheets
Table A.1. Net project impact (metric tons of CO2)
Project or Tool Input Output Additional Calculations Final Output NET Project Impact a Energy MTCO2e Project Life (years) MTCO2e
Construction phase ‐ ‐ MTCO2e
Operations phase 123 5 614.82 686.10
b Water MTCO2e Project Life (years) MTCO2e
Construction phase ‐ ‐
Operations phase ‐ 0 ‐
c Transportation (VMT) MTCO2e
KC Employee Commute Climate Pollution Map Av MTCO2e # employees
‐ 0 ‐
KC Residential Transportation Climate Pollution
Map
Av MTCO2e # households MTCO2e
‐ 0 ‐
d Embodied Energy MTCO2e MTCO2e
71 71.28
1 Waste Reduction Model (WARM) MTCO2e MTCO2e
‐ ‐
2 URBEMIS lbsCO2/day # project days MTCO2e
‐ 0 ‐
3 Roadway Construction Emissions Model tonsCO2/project MTCO2e
‐ ‐
4 Build Carbon Neutral MTCO2 MTCO2e
‐ ‐
5 Tree Carbon Calculator kgCO2 #
trees
MTCO2e
‐ 0 ‐
6 Reforestation Calculator MTCO2e MTCO2e
‐ ‐
*Beneficial use of Loop compost sequesters, or removes, CO2 from the atmosphere. This project will sequester an estimated 514 metric tons of CO2 over its
duration, offsetting much of the emissions shown in this worksheet.
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 28
Table A.2. Energy use (metric tons of CO2)
Project Input Data Input Input Unit Output Additional Calculations
Energy Use Construction Operations MTCO2e Project Life (years)
enter in the amount of electricity or fuel used by project phase
Electricity 77,743 kWh 0 49.6311312 5
Gasoline1 gallons 0 0
Diesel1 5,876 gallons 0 73.33248
Natural Gas therms 0 0 Heating Oil gallons 0 0 Jet Fuel gallons 0 0 Steam Mlb 0 0 Propane gallons 0 0
Energy Use‐‐Biofuels Project Life (years)
Green Electricity2 51,829 kWh 0 0
Biogenic Sources3
Biodiesel1 gallons 0 0 Landfill gas or Biogas2 MMBtu 0 0
Project Input Data Input Input Unit Output
Vehicle Miles Traveled (VMT) MTCO2e Project Life (years)
enter the estimated annual VMT for the project ‐ miles 0 0 0
Project Input Data Input Input Unit Output
Water Use ('watergy') MTCO2e Project Life (years)
enter the amount of water used by project phase ‐ gallons 0 0 0
1. Lifecycle GHG Emissions (includes both combustion and fuel production)
2. Green electricity and biogas are considered carbon‐neutral energy sources; CO2e output is zero
3. Please separately calculate and note any biogenice sources of greenhouse gas emissions
DocuSign Envelope ID: 6CE3899A-1D0A-43F4-A678-6B93041EB30C
SEPA Environmental Checklist Loop® Compost Pilot Project at South Treatment Plant
December 2020 29
Table A.3. Embodied energy (metric tons of CO2)
Project Input Data Input Input Unit Output
Materials Use MTCO2e
enter tons (US tons, or short tons) of material used
Concrete
Cement
Asphalt
648
US tons
US tons
US tons
0
0
71
Dimensional lumber
Glass