LETTER OF TRANSMITTAL
15365 NE 90th Street, Suite 100 Redmond, WA 98052
(425) 449-4704 FAX (425) 449-4711
To: RJ Development
401 Central Street SE
Olympia, WA 98501
Date: June 22, 2021
ESNW No.: ES- 895.06
Project: Weatherly Inn
Attn: Mr. Jeff Bennett
Email: jeffb@accrete.build
No. of
Copies Date Description
1 6/8-6/17/21 Daily Field Report(s) # 308 & 309
Comments:
CC:
1: Mark Richardson ATTN: mark@accrete.build
2: Jennifer Vogele ATTN: jennifer@accrete.build
3: Jonathan Chavez ATTN: jchavez@rentonwa.gov
4: Joe W ATTN: joew@accrete.build
5: Brittany Perry ATTN: brittany@accrete.build
6: ATTN:
7: ATTN:
8: ATTN:
Transmitted By: Earth Solutions NW, LLC
PM: Scott Riegel, L.G., L.E.G.
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 308
Time On Site Time Off Site Date Day of Week
8:45 AM 9:15 AM
6/8/21
Tuesday
Travel Time Weather
1.00Hr. RT 60s, OC
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Johannsen Brad LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site? Project No. Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe and test utility trench backfill at the Weatherly Inn
development.
Utility Trench Backfill:
ESNW rep arrived onsite and observed contractor had backfilled approximately 200’ of 2’x2’ trench along the
North margin of the site for a 2’’ schedule 40 PVC conduit. ESNW rep observed contractor had added water to
material in order to reach optimum moisture. ESNW rep used a ½’’ steel T-probe and observed the backfill to be
suitably dense, firm, and unyielding. ESNW rep observed that the contractor had achieved minimum
compaction standards of 95% or greater in tested locations.
Light Pole Basins:
ESNW rep observed contractor excavating approximately 5’ basins for light poles. ESNW rep used a ½’’ steel
T-probe and to probe the light pole basins and recommended over-excavation and backfill with
structural material such as quarry spalls and woven geotextile fabric in the light pole basin adjacent to
Catch Basin #7.
ESNW rep will return as requested to continue observation and testing of further earthwork activities.
Fig.1: Utility trench along North margin of site, approx. location of test #307
1/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 308
Time On Site Time Off Site Date Day of Week
8:45 AM 9:15 AM
6/8/21
Tuesday
Travel Time Weather
1.00Hr. RT 60s, OC
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Johannsen Brad LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site? Project No. Permit No.
Test Number Test Location
(Stormwater
trench backfill) Elevation Reference
Compaction
Curve
Maximum Dry
Density (pcf) Fill Moisture
(%) Test
Dry Density
(pcf)
% of Maximum
Dry Density
307 See map SG 3 122.0 9.8 116.3 95
308 See map SG 3 122.0 8.7 117.1 96
309 See map SG 3 122.0 10.1 116.8 96
310 See map SG 3 122.0 9.8 115.9 95
311 See map SG 3 122.0 8.5 118.2 97
312 See map SG 3 122.0 10.2 117.0 96
Fig. 2 Approximate location of compaction tests 307-312 on utility trench backfill
Jackson Lundgren, G.I.T.
Senior Field Technician
206-468-0991
2/2
309
307
308
310
311
312
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 309
Time On Site Time Off Site Date Day of Week
11:15 AM 12:00 PM
6/17/21
Thursday
Travel Time Weather
1.00Hr. RT 60s, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Johannsen Brad LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site? Project No. Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe light pole basin backfill and test stormwater line backfill
at the Weatherly Inn development.
Stormwater Trench Backfill:
ESNW rep arrived onsite and observed contractor had backfilled approximately 50’ of 4’ deep trench around a
12’’ductile iron pipe running East from the site entrance with 5/8’’ minus crushed rock compacted in 12’’ lifts to
grade with a jumping jack. ESNW rep observed contractor adding water to material in order to reach optimum
moisture. ESNW rep used a ½’’ steel T-probe and observed the subgrade to be suitably dense, firm, and
unyielding. ESNW rep observed that the contractor had achieved minimum compaction standards of 95%
or greater in tested locations.
Light Pole Basin:
ESNW rep observed contractor had backfilled 4.5’-5’ of concrete light pole bases in locations marked on plans
below. ESNW rep observed contractor had used 1 ¼’’ crushed recycled concrete compacted in 12’’ loose lifts
with a jumping jack. ESNW rep used a ½’’ steel T-probe and observed the backfill to be dense, firm, and
unyielding.
ESNW rep will return as requested to continue observation and testing of further earthwork activities.
Fig.1: Trench with 12’’ ductile iron water main line
Jackson Lundgren, G.I.T.
Senior Field Technician
206-468-0991
1/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 309
Time On Site Time Off Site Date Day of Week
11:15 AM 12:00 PM
6/17/21
Thursday
Travel Time Weather
1.00Hr. RT 60s, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Johannsen Brad LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site? Project No. Permit No.
Test Number Test Location
(Stormwater
trench backfill) Elevation Reference
Compaction
Curve
Maximum Dry
Density (pcf) Fill Moisture
(%) Test
Dry Density
(pcf)
% of Maximum
Dry Density
313 See map -1’ SG 9 122.0 10.5 116.5 95
314 See map -1’ SG 9 122.0 11.0 115.9 95
Fig. 2 Approximate location of compaction tests 313 and 314 on trench backfill, and approximate locations of light pole basins
2/2
313
314
Light Pole