Description of Change:
Change to Contract Plans:
As required in Field Directive 4, the Contractor is directed to delete CB 175 and the 8-inch DI storm pipe
run to the existing CB 170. The Contractor is also directed to delete CB 190 and CB 200. Associated
connections to existing drainage structures are deleted. Associated sawcutting, pavement and
curb/gutter removals are deleted. Associated pavement repair is deleted. Associated cement concrete
curb and gutter replacement is deleted. Associated PSIPE Prunis Laurocerasus ‘Mount Vernon’/Mount
Vernon Laurel is deleted.
The net effect of these modifications includes: a reduction of 126 LF of Sawcutting, a reduction of 33 TN
of Crushed Surfacing Top Course, a reduction of 15 TN of Crushed Surfacing Base Course, a reduction of
50 LF of Ductile Iron Storm Sewer Pipe 8 In. Diam, a reduction of 1 EA of Catch Basin Type 1, a reduction
of 2 EA Catch Basin Type 2, 48 In. Diam., a reduction of 5 EA of Connection to Drainage Structure, a
reduction of 18 EA PSIPE Prunis Laurocerasus ‘Mount Vernon’/Mount Vernon Laurel (2 gal), a reduction
of 55 LF of Cement Conc. Traffic Curb and Gutter and a reduction of 50 SY of pavement and concrete
removals.
Reason for Change:
Contract Plans:
The existing catch basin at CB 175 may remain in place. There were fiber optic line conflicts
with proposed CB 190 and CB 200. These structures were in-line catch basins, not located at
sag points, incorporated into the design to reduce spacing between catch basins, so they can be
deleted.
Materials:
N/A
Plans:
C2.04 revision 1, C3.05 revisions 1, C3.06 revision 1, C3.08 revision 2, C3.10 revision 1, C3.13 revision 2,
L6.04 revision 1,
Equitable Adjustment:
This Change Order does include an equitable adjustment per Section 1-09.4 of the 2020
WSDOT/APWA Standard Specifications.
Change Order No. 3
Contract Title: Lake Washington Loop Trail
Contract No. CAG -20-126
Page 3 of 3
The Work will be measured and paid under the respective unit and lump sum prices.
The attached Equitable Adjustment Summary lists the unit and lump sum bid items that
are adjusted due to this change. The adjustments to the unit bid item quantities are
estimates; the Contractor will be paid based on the actual quantities installed.
See attached.
Extension of Time:
The Time for Completion is extended 0 Working Days.
Sections 1-04.4 and 1-04.5 of the 2020 WSDOT/APWA Standard Specifications shall govern
this Change Order. The Work of the referenced Contract is modified to include the changes
detailed herein. The payment provided for herein shall constitute the complete and final
settlement for all costs of labor, equipment, materials, overhead, profit, permit fees, and all
other claims that may be made by the Contractor as a result of this change.
Attachments:
Forms to be attached to Change Order
܈ Plans
܈Field Directive
܆Change Order Quotation
܈Estimated Change Order Cost
܆Project Labor List
܆Force Account Equipment Rate Request (DOT Form 422-010 EF)
܆Equitable Adjustment Determination
Item
No.Description
Quantity
Change Unit Unit Price Estimated Cost
13 Sawcutting -126 LF $4.25 ($535.50)
16 Crushed Surfacing Top Course -33 TN $52.50 ($1,732.50)
17 Crushed Surfacing Base Course -15 TN $47.00 ($705.00)
29 Ductile Iron Storm Sewer Pipe 8 In. Diam. -50 LF $95.00 -$4,750.00
33 Catch Basin Type 1 -1 EA $1,600.00 -$1,600.00
34 Catch Basin Type 2, 48 In. Diam. -2 EA $3,800.00 -$7,600.00
35 Connection to Drainage Structure -5 EA $1,100.00 -$5,500.00
47 PSIPE Prunis Laurocerasus ‘Mount Vernon’/Mount Vernon Laurel (2 gal) -18 EA $25.00 -$450.00
56 Cement Conc. Traffic Curb & Gutter -55 LF $50.00 -$2,750.00
CO 3-1 CO 4 Pavement and Curb/Gutter Removal Credit (New Item) -50 SY $16.67 ($833.33)
-$26,456.33
0
-$26,456.33
Estimated Bid Item Cost
Estimated Force Account Cost
Total Estimated Change Order Cost
By:
Date: 5/28/2021
Estimated Change Order No 3 Cost
Project Name: Lake Washington Loop Trail
Contractor: Active Construction Inc.
Federal Aid No: TAP-1070(008)
Contract No: CAG 20-126
Construction Manager: Tani Stafford, PE
Bid Item Change
CITY OF RENTONBY: DATE:APPROVED FOR CONSTRUCTIONOF11241 Willows Road NE, Suite 200Redmond, WA 98052425.822.4446www.otak.com
CITY OF RENTONBY: DATE:APPROVED FOR CONSTRUCTIONOF11241 Willows Road NE, Suite 200Redmond, WA 98052425.822.4446www.otak.comVERTHORZ
CITY OF RENTONBY: DATE:APPROVED FOR CONSTRUCTIONOF11241 Willows Road NE, Suite 200Redmond, WA 98052425.822.4446www.otak.comVERTHORZ
CITY OF RENTONBY: DATE:APPROVED FOR CONSTRUCTIONOF11241 Willows Road NE, Suite 200Redmond, WA 98052425.822.4446www.otak.comVERTHORZ
CITY OF RENTONBY: DATE:APPROVED FOR CONSTRUCTIONOF11241 Willows Road NE, Suite 200Redmond, WA 98052425.822.4446www.otak.com
CITY OF RENTONBY:DATE:APPROVED FOR CONSTRUCTIONOF11241 Willows Road NE, Suite 200Redmond, WA 98052425.822.4446www.otak.com