Change Order No. 10
Contract Title: Lake Washington Loop Trail
Contract No. CAG -20-126
Page 2 of 3
THE CONTRACT IS MODIFIED AS FOLLOWS:
Description of Change:
Change to Contract Plans:
As required by Field Work Directive No 14, the Contractor is directed perform additional work to
construct T-patches.
As required by Field Work Directive No 5.1, the Contractor is directed to perform additional work to
remove and replace castings along the cycle track.
This change order addresses the additional time impact due to this additional work. Future change
orders will address added costs due to the additional work.
Reason for Change:
Contract Plans:
The Contract plans did not include the City of Renton Standard T Patch repair detail.
The Contract Plans did not include removal and replacement of existing castings within the cycle track,
which were later determined to require replacement.
Materials:
Associated material changes to be addressed in future change orders.
Plans:
Associated plan revisions to be addressed in future change orders
Estimated Change Order Cost:
This Change Order does not include an equitable adjustment per Section 1-09.4 of the
2020 WSDOT/APWA Standard Specifications.
Cost changes to be addressed in future change orders.
Extension of Time:
The Contractor agrees that the time for Completion is extended 9 Working Days for the
additional work.
Change Order No. 10
Contract Title: Lake Washington Loop Trail
Contract No. CAG -20-126
Page 3 of 3
Sections 1-04.4 and 1-04.5 of the 2020 WSDOT/APWA Standard Specifications shall govern
this Change Order. The Work of the referenced Contract is modified to include the changes
detailed herein.
Attachments:
Forms to be attached to Change Order
Plans
Field Directive
Change Order Quotation
Estimated Change Order Cost
Project Labor List
Force Account Equipment Rate Request (DOT Form 422-010 EF)
Equitable Adjustment Determination
Schedule Update submitted 6-30-21
Actual Grind Startwas 7/13/21
Potholing for the underground signal and illumination work isincidental and a first order of work under activity ID’s 32, 44and 49.Activity ID’s 66-72 will be deleted once this baseline scheduleis accepted and the FWD directive is received officially deletingthe Work.Preconstruction meetings prior to storm structure construc-tion and ADA ramp construction required per the ContractProvisions.This schedule is acceptedwith the comments noted inyellow below 5/3/21
Original Baseline Schedule 5-6-21