Loading...
HomeMy WebLinkAboutContractConstruction Agreement, Attachment “B” to Schedule 74, Page 1 Renton – Duvall Ave Sch74 from NE 7th Place to Sunset Boulevard SCHEDULE 74 UNDERGROUND CONVERSION Project Construction Agreement Project Name: Renton – Duvall Ave Sch74 Project Number: 101120019 THIS Agreement, dated as of this ____ day of _______________, 2021, is made by and between The City of Renton, a municipal corporation (the “Government Entity”), and PUGET SOUND ENERGY, Inc., a Washington Corporation (the “Company"). RECITALS A.The Company is a public service company engaged in the sale and distribution of electric energy, and pursuant to its franchise or other rights from the Government Entity, currently locates its electric distribution facilities within the jurisdictional boundaries of the Government Entity. B.The Government Entity has determined that it is necessary to replace the existing overhead electric distribution system within the area specified in the Project Plan (as defined below) (the "Conversion Area") with a comparable underground electric distribution system, all as more specifically described in the Project Plan (the "Conversion Project"). C.The Government Entity and the Company have previously entered into a Project Design Agreement dated as of 8/9/2019 (the "Design Agreement"), pursuant to which the parties completed certain engineering design, cost assessment, operating rights planning and other preliminary work relating to the Conversion Project and, in connection with that effort, developed the Project Plan. D.The Government Entity and the Company wish to execute this written contract in accordance with Schedule 74 of the Company's Electric Tariff G ("Schedule 74") to govern the completion of the Conversion Project, which both parties intend shall qualify as an underground conversion under the terms of Schedule 74. AGREEMENT The Government Entity and the Company therefore agree as follows: 1.Definitions. (a)Unless specifically defined otherwise herein, all terms defined in Schedule 74 shall have the same meanings when used in this Agreement, including, without limitation, the following: i)Cost of Conversion; ii)Public Thoroughfare; iii)Temporary Service; iv)Trenching and Restoration; v)Underground Distribution System; and vi)Underground Service Lines. (b)“Company-Initiated Upgrade” shall mean any feature of the Underground Distribution System which is required by the Company and is not reasonably required to make the Underground Distribution System comparable to the overhead distribution system being replaced. For purposes of the foregoing, a "comparable" system shall include, unless the Parties otherwise agree, the number of empty ducts (not to exceed two (2), typically having a diameter of 6" or less) CAG-21-206 September7th Construction Agreement, Attachment “B” to Schedule 74, Page 2 Renton – Duvall Ave Sch74 from NE 7th Place to Sunset Boulevard of such diameter and number as may be specified and agreed upon in the Project Plan necessary to replicate the load-carrying capacity (system amperage class) of the overhead system being replaced. (c)“Estimated Reimbursable Private Conversion Costs” shall mean the Company's good faith estimate of the Reimbursable Private Conversion Costs, as specified in the Project Plan and as changed and adjusted from time to time in accordance with Section 6, below. (d)“Estimated Reimbursable Temporary Service Costs” shall mean the Company's good faith estimate of the Reimbursable Temporary Service Costs, as specified in the Project Plan and as changed and adjusted from time to time in accordance with Section 6, below. (e)“Estimated Reimbursable Upgrade Costs” shall mean the Company's good faith estimate of the Reimbursable Upgrade Costs, as specified in the Project Plan and as changed and adjusted from time to time in accordance with Section 6, below. (f)“Estimated Shared Company Costs” shall mean the Company's good faith estimate of the Shared Company Costs, as specified in the Project Plan and as changed and adjusted from time to time in accordance with Section 6, below. (g)“Estimated Shared Government Costs” shall mean the Government Entity's good faith estimate of the Shared Government Costs, as specified in the Project Plan and as changed and adjusted from time to time in accordance with Section 6, below. (h)“Government-Requested Upgrade” shall mean any feature of the Underground Distribution System which is requested by the Government Entity and is not reasonably required to make the Underground Distribution System comparable to the overhead distribution system being replaced. For purposes of the foregoing, any empty ducts installed at the request of the Government Entity shall be a Government-Requested Upgrade. (i)“Party” shall mean either the Company, the Government Entity, or both. (j)“Private Property Conversion” shall mean that portion, if any, of the Conversion Project for which the existing overhead electric distribution system is located, as of the date determined in accordance with Schedule 74, (i) outside of the Public Thoroughfare, or (ii) pursuant to rights not derived from a franchise previously granted by the Government Entity or pursuant to rights not otherwise previously granted by the Government Entity. (k)“Project Plan” shall mean the project plan developed by the Parties under the Design Agreement and attached hereto as Exhibit A, as the same may be changed and amended from time to time in accordance with Section 6, below. The Project Plan includes, among other things, (i) a detailed description of the Work that is required to be performed by each Party and any third party, (ii) the applicable requirements and specifications for the Work, (iii) a description of the Operating Rights that are required to be obtained by each Party for the Conversion Project (and the requirements and specifications with respect thereto), (iv) an itemization and summary of the Estimated Shared Company Costs, Estimated Shared Government Costs, Estimated Reimbursable Private Conversion Costs (if any), Estimated Reimbursable Temporary Service Costs (if any) and Estimated Reimbursable Upgrade Costs (if any), and (v) the Work Schedule. (l)“Operating Rights” shall mean sufficient space and legal rights for the construction, operation, repair, and maintenance of the Underground Distribution System. (m)“Reimbursable Private Conversion Costs” shall mean (i) all Costs of Conversion, if any, incurred by the Company which are attributable to a Private Property Conversion, less (ii) the distribution pole replacement costs (if any) that would be avoided by the Company on account of such Private Property Conversion, as determined consistent with the applicable Company distribution facilities Construction Agreement, Attachment “B” to Schedule 74, Page 3 Renton – Duvall Ave Sch74 from NE 7th Place to Sunset Boulevard replacement program, plus (iii) just compensation as provided by law for the Company's interests in real property on which such existing overhead distribution system was located prior to conversion; provided that the portion of the Reimbursable Private Conversion Costs attributable to the Costs of Conversion under subparagraph (i) of this paragraph shall not exceed the Estimated Reimbursable Private Conversion Costs without the prior written authorization of the Government Entity. (n) “Reimbursable Temporary Service Costs” shall mean all costs incurred by the Company which are attributable to (i) any facilities installed as part of the Conversion Project to provide Temporary Service, as provided for in Schedule 74, and (ii) the removal of any facilities installed to provide Temporary Service (less salvage value of removed equipment); provided that the Reimbursable Temporary Service Costs shall not exceed the Estimated Reimbursable Temporary Service Costs without the prior written authorization of the Government Entity. (o) “Reimbursable Upgrade Costs” shall mean all Costs of Conversion incurred by the Company which are attributable to any Government-Requested Upgrade; provided that the Reimbursable Upgrade Costs shall not exceed the Estimated Reimbursable Upgrade Costs without the prior written authorization of the Government Entity. (p) “Shared Company Costs” shall mean all Costs of Conversion (other than Reimbursable Upgrade Costs, Reimbursable Private Conversion Costs and Reimbursable Temporary Service Costs) incurred by the Company in connection with the Conversion Project; provided, however, that the Shared Company Costs shall not exceed the Estimated Shared Company Costs without the prior written authorization of the Government Entity. For the avoidance of doubt, the "Shared Company Costs" shall, as and to the extent specified in the Design Agreement, include the actual, reasonable costs to the Company for the "Design Work" performed by the Company under the Design Agreement. (q) “Shared Government Costs” shall mean all Costs of Conversion incurred by the Government Entity in connection with (i) any duct and vault installation Work which the Parties have specified in the Project Plan is to be performed by the Government Entity as part of the Government Work, and (ii) the acquisition of any Operating Rights which the Parties have, by mutual agreement, specified in the Project Plan are to be obtained by the Government Entity for the Conversion Project, but only to the extent attributable to that portion of such Operating Rights which is necessary to accommodate the facilities of the Company; provided, however, that the Shared Government Costs shall not exceed the Estimated Shared Government Costs without the prior written authorization of the Company. (r) “Total Shared Costs” shall mean the sum of the Shared Company Costs and the Shared Government Costs. For the avoidance of doubt, the Total Shared Costs shall not include, without limitation, (i) costs to the Government Entity for Trenching and Restoration, or (ii) costs associated with any joint use of trenches by other utilities as permitted under Section 3(b). (s) “Work” shall mean all work to be performed in connection with the Conversion Project, as more specifically described in the Project Plan, including, without limitation, the Company Work (as defined in Section 2(a), below) and the Government Work (as defined in Section 3(a), below). (t) “Work Schedule” shall mean the schedule specified in the Project Plan which sets forth the milestones for completing the Work, as the same may be changed and amended from time to time in accordance with Section 6, below. 2. Obligations of the Company. (a) Subject to the terms and conditions of this Agreement, the Company shall do the following as specified in, and in accordance with the design and construction specifications and other requirements set forth in, the Project Plan (the "Company Work"): Construction Agreement, Attachment “B” to Schedule 74, Page 4 Renton – Duvall Ave Sch74 from NE 7th Place to Sunset Boulevard i) furnish and install an Underground Distribution System within the Conversion Area (excluding any duct and vault installation or other Work which the Parties have specified in the Project Plan is to be performed by the Government Entity); ii) provide a Company inspector on-site at the times specified in the Work Schedule to inspect the performance of any duct and vault installation Work which the Parties have specified in the Project Plan is to be performed by the Government Entity; and iii) upon connection of those persons or entities to be served by the Underground Distribution System and removal of facilities of any other utilities that are connected to the poles of the overhead system, remove the existing overhead system (including associated wires and Company-owned poles) of 15,000 volts or less within the Conversion Area except for Temporary Services. (b) Upon request of the Government Entity, the Company shall provide periodic reports of the progress of the Company Work identifying (i) the Company Work completed to date, (ii) the Company Work yet to be completed, and (iii) an estimate regarding whether the Conversion Project is on target with respect to the Estimated Shared Company Costs, the Estimated Reimbursable Private Conversion Costs (if any), the Estimated Reimbursable Temporary Service Costs (if any), the Estimated Reimbursable Upgrade Costs (if any) and the Work Schedule. (c) Except as otherwise provided in the Company's Electric Tariff G, the Company shall own, operate and maintain all electrical facilities installed pursuant to this Agreement including, but not limited to, the Underground Distribution System and Underground Service Lines. (d) Subject to the terms and conditions of this Agreement, the Company shall perform all Company Work in accordance with the Project Plan, the Work Schedule and this Agreement. 3. Obligations of the Government Entity. (a) Subject to the terms and conditions of this Agreement, the Government Entity shall do the following as specified in, and in accordance with the design and construction specifications and other requirements set forth in, the Project Plan (the "Government Work"): i) provide the Trenching and Restoration; ii) perform the surveying for alignment and grades for ducts and vaults; and iii) perform any duct and vault installation and other Work which the Parties have specified in the Project Plan is to be performed by the Government Entity. (b) Other utilities may be permitted by the Government Entity to use the trenches provided by the Government Entity for the installation of their facilities so long as such facilities or the installation thereof do not interfere (as determined pursuant to the Company's electrical standards) with the Underground Distribution System or the installation or maintenance thereof. Any such use of the trenches by other utilities shall be done subject to and in accordance with the joint trench design specifications and installation drawings set forth or otherwise identified in the Project Plan, and the Government Entity shall be responsible for the coordination of the design and installation of the facilities of the other utilities to ensure compliance with such specifications and drawings. (c) Upon request of the Company, the Government Entity shall provide periodic reports of the progress of the Government Work identifying (i) the Government Work completed to date, (ii) the Government Work yet to be completed, and (iii) an estimate regarding whether the Conversion Project is on target with respect to the Estimated Shared Government Costs and the Work Schedule. (d) The Government Entity shall be responsible for coordinating all work to be performed in connection with the street improvement program within the Conversion Area. th Construction Agreement, Attachment “B” to Schedule 74, Page 5 Renton – Duvall Ave Sch74 from NE 7th Place to Sunset Boulevard (e) Subject to the terms and conditions of this Agreement, the Government Entity shall perform all Government Work in accordance with the Project Plan, the Work Schedule and this Agreement. 4. Work Schedule. (a) The Government Entity and the Company have agreed upon the Work Schedule as set forth in the Project Plan. Changes to the Work Schedule shall be made only in accordance with Section 6, below. (b) Promptly following the execution of this Agreement, and upon completion by the Government Entity of any necessary preliminary work, the Government Entity shall hold a pre-construction meeting involving all participants in the Conversion Project to review project design, coordination requirements, work sequencing and related pre-mobilization requirements. Following the pre- construction meeting, the Government Entity shall give the Company written notice to proceed with the Work at least ten (10) business days prior to the commencement date specified in the Work Schedule. (c) Subject to the terms and conditions of this Agreement, each Party shall perform the Work assigned to it under this Agreement in accordance with the Work Schedule. So long as the Company performs the Company Work in accordance with the Work Schedule, the Company shall not be liable to the Government Entity (or its agents, servants, employees, contractors, subcontractors, or representatives) for any claims, actions, damages, or liability asserted or arising out of delays in the Work Schedule. 5. Location of Facilities. All facilities of the Company installed within the Conversion Area pursuant to this Agreement shall be located, and all related Operating Rights shall be obtained, in the manner set forth in the applicable provisions of Schedule 74, as specified by the Parties in the Project Plan. 6. Changes. (a) Either Party may, at any time, by written notice thereof to the other Party, request changes in the Work within the general scope of this Agreement (a "Request for Change"), including, but not limited to: (i) changes in, substitutions for, additions to or deletions of any Work; (ii) changes in the specifications, drawings and other requirements in the Project Plan, (iii) changes in the Work Schedule, and (iv) changes in the location, alignment, dimensions or design of items included in the Work. No Request for Change shall be effective and binding upon the Parties unless signed by an authorized representative of each Party. (b) If any change included in an approved Request for Change would cause a change in the cost of, or the time required for, the performance of any part of the Work, an equitable adjustment shall be made in the Estimated Shared Company Costs, the Estimated Shared Government Costs, the Estimated Reimbursable Private Conversion Costs (if any), the Estimated Reimbursable Temporary Service Costs (if any), the Estimated Reimbursable Upgrade Costs (if any) and/or the Work Schedule to reflect such change. The Parties shall negotiate in good faith with the objective of agreeing in writing on a mutually acceptable equitable adjustment. If the Parties are unable to agree upon the terms of the equitable adjustment, either Party may submit the matter for resolution pursuant to the dispute resolution provisions in Section 10, below. (c) The Work Schedule, the Estimated Shared Company Costs, the Estimated Shared Government Costs, the Estimated Reimbursable Private Conversion Costs, the Estimated Reimbursable Temporary Service Costs and/or the Estimated Reimbursable Upgrade Costs shall be further equitably adjusted from time to time to reflect any change in the costs or time required to perform the Work to the extent such change is caused by: (i) any Force Majeure Event under Section 11, below, (ii) the discovery of any condition within the Conversion Area which affects the scope, cost, Construction Agreement, Attachment “B” to Schedule 74, Page 6 Renton – Duvall Ave Sch74 from NE 7th Place to Sunset Boulevard schedule or other aspect of the Work and was not known by or disclosed to the affected Party prior to the date of this Agreement, or (iii) any change or inaccuracy in any assumptions regarding the scope, cost, schedule or other aspect of the Work which are expressly identified by the Parties in the Project Plan. Upon the request of either Party, the Parties will negotiate in good faith with the objective of agreeing in writing on a mutually acceptable equitable adjustment. If, at any time thereafter, the Parties are unable to agree upon the terms of the equitable adjustment, either Party may submit the matter for resolution pursuant to the dispute resolution provisions in Section 10, below. (d) Notwithstanding any dispute or delay in reaching agreement or arriving at a mutually acceptable equitable adjustment, each Party shall, if requested by the other Party, proceed with the Work in accordance with any approved Request for Change. Any request to proceed hereunder must be accompanied by a written statement setting forth the requesting Party's reasons for rejecting the proposed equitable adjustment of the other Party. 7. Compensation and Payment. (a) Subject to and in accordance with the terms and conditions of this Agreement (including, without limitation, the payment procedures set forth in this Section 7), payment in connection with the Conversion Project and this Agreement shall be as follows: i) The Total Shared Costs shall be allocated to the Parties in the following percentages: (A) sixty percent (60%) to the Company, and (B) forty percent (40%) to the Government Entity. ii) The Government Entity shall pay one hundred percent (100%) of all Reimbursable Private Conversion Costs, if any. iii) The Government Entity shall pay one hundred percent (100%) of all Reimbursable Upgrade Costs, if any. iv) The Government Entity shall pay one hundred percent (100%) of all Reimbursable Temporary Service Costs, if any. v) The Government Entity shall pay one hundred percent (100%) of the costs it incurs to perform that portion of the Government Work specified in Section 3(a)(i) and (ii) (i.e., Trenching and Restoration and surveying). vi) The Company shall pay one hundred percent (100%) of the costs it incurs to design, provide and construct any Company-Initiated Upgrade. vii) The Company shall pay one hundred percent (100%) of the costs it incurs to obtain Operating Rights outside the Public Thoroughfare. (b) Based on the allocation of responsibilities set forth in Section 7(a), above, the Parties shall determine the net amount payable by the Government Entity or the Company, as applicable, to the other Party under this Agreement (the "Net Amount"). The Net Amount shall be determined by using the amount of the Total Shared Costs allocated to the Government Entity under Section 7(a)(i), and adjusting such amount as follows: i) Subtracting (as a credit to the Government Entity) the amount of the Shared Government Costs. ii) Adding (as a credit to the Company) the amount of all Reimbursable Private Conversion Costs, Reimbursable Upgrade Costs and Reimbursable Temporary Service Costs. iii) Subtracting (as a credit to the Government Entity) any payments previously made to the Company by the Government Entity under the Design Agreement which, under the terms of the Design Agreement, are to be credited to the Government Entity under this Agreement. The Net Amount, as so calculated, (A) will be an amount payable to the Company if it is a positive number, and (B) shall be an amount payable to the Government Entity if it is a negative number. Construction Agreement, Attachment “B” to Schedule 74, Page 7 Renton – Duvall Ave Sch74 from NE 7th Place to Sunset Boulevard (c)Within sixty (60) business days of completion of the Conversion Project, the Government Entity shall provide the Company with an itemization of the Shared Government Costs (the "Government Itemization"), together with such documentation and information as the Company may reasonably request to verify the Government Itemization. The Government Itemization shall, at a minimum, break down the Shared Government Costs by the following categories, as applicable: (i) property and related costs incurred and/or paid by the Government Entity, including any costs of obtaining Operating Rights, and (ii) construction costs incurred and/or paid by the Government Entity, including and listing separately inspection, labor, materials and equipment, overhead and all costs charged by any agent, contractor or subcontractor of the Government Entity. (d)Within thirty (30) business days after the Company's receipt of the Government Itemization and requested documentation and information, the Company shall provide the Government Entity a written statement (the "Company Statement") showing (i) an itemization of the Shared Company Costs, (ii) the Parties' relative share of the Total Shared Costs based on the Company's itemization of the Shared Company Costs and the Government Entity's itemization of the Shared Government Costs set forth in the Government Itemization, (iii) any Reimbursable Private Conversion Costs, (iv) any Reimbursable Upgrade Costs, (v) any Reimbursable Temporary Service Costs, (vi) any credits to the Government Entity for payments previously made to the Company by the Government Entity under the Design Agreement which, under the terms of the Design Agreement, are to be credited to the Government Entity under this Agreement, and (vii)the Net Amount, as determined in accordance with Section 7(b), above, together with such documentation and information as the Government Entity may reasonably request to verify the Company Statement. The itemization of the Shared Company Costs included in the Company Statement shall, at a minimum, break down the Shared Company Costs by the following categories, as applicable: (i) design and engineering costs, and (ii) construction costs, including and listing separately inspection, labor, materials and equipment, overhead and all costs charged by any agent, contractor or subcontractor of the Company. (e)Within thirty (30) business days after the Government Entity's receipt of the Company Statement and requested documentation and information, the Net Amount shall be paid by the owing Party to the other Party, as specified in the Company Statement. 8.Indemnification. (a)The Government Entity releases and shall defend, indemnify and hold the Company harmless from all claims, losses, harm, liabilities, damages, costs and expenses (including, but not limited to, reasonable attorneys' fees) caused by or arising out of any negligent act or omission or willful misconduct of the Government Entity in its performance under this Agreement. During the performance of such activities the Government Entity's employees or contractors shall at all times remain employees or contractors, respectively, of the Government Entity. (b)The Company releases and shall defend, indemnify and hold the Government Entity harmless from all claims, losses, harm, liabilities, damages, costs and expenses (including, but not limited to, reasonable attorneys' fees) caused by or arising out of any negligent act or omission or willful misconduct of the Company in its performance under this Agreement. During the performance of such activities the Company's employees or contractors shall at all times remain employees or contractors, respectively, of the Company. (c)Solely for purposes of enforcing the indemnification obligations of a Party under this Section 8, each Party expressly waives its immunity under Title 51 of the Revised Code of Washington, the Industrial Insurance Act, and agrees that the obligation to indemnify, defend and hold harmless provided for in this Section 8 extends to any such claim brought against the indemnified Party by or on behalf of any employee of the indemnifying Party. The foregoing waiver shall not in any way preclude the indemnifying Party from raising such immunity as a defense against any claim brought against the indemnifying Party by any of its employees. Construction Agreement, Attachment “B” to Schedule 74, Page 8 Renton – Duvall Ave Sch74 from NE 7th Place to Sunset Boulevard 9. Conversion of Service to Customers within Conversion Area. (a) Upon commencement of the Work, the Government Entity shall notify all persons and entities within the Conversion Area that service lines to such customers must be converted from overhead to underground service within the applicable statutory period following written notice from the Government Entity that service from underground facilities are available in accordance with RCW 35.96.050. Upon the request of any customer, other than a single family residential customer, within the Conversion Area, the Company shall remove the overhead system and connect such persons’ and entities’ Underground Service Lines to the Underground Distribution System. (b) The Parties acknowledge that single family residences within the Conversion Area must (i) provide a service trench and conduit, in accordance with the Company's specifications, from the underground meter base to the point of service provided during the conversion, and (ii) pay for the secondary service conductors as defined in Schedule 85 of the Company's Electric Tariff G. The Government Entity shall exercise its authority to order disconnection and removal of overhead facilities with respect to owners failing to convert service lines from overhead to underground within the timelines provided in RCW 35.96.050. 10. Dispute Resolution. (a) Any dispute, disagreement or claim arising out of or concerning this Agreement must first be presented to and considered by the Parties. A Party who wishes dispute resolution shall notify the other Party in writing as to the nature of the dispute. Each Party shall appoint a representative who shall be responsible for representing the Party's interests. The representatives shall exercise good faith efforts to resolve the dispute. Any dispute that is not resolved within ten (10) business days of the date the disagreement was first raised by written notice shall be referred by the Parties' representatives in writing to the senior management of the Parties for resolution. In the event the senior management are unable to resolve the dispute within twenty (20) business days (or such other period as the Parties may agree upon), each Party may pursue resolution of the dispute through other legal means consistent with the terms of this Agreement. All negotiations pursuant to these procedures for the resolution of disputes shall be confidential and shall be treated as compromise and settlement negotiations for purposes of the state and federal rules of evidence. (b) Any claim or dispute arising hereunder which relates to any Request for Change or any equitable adjustment under Section 6, above, or the compensation payable by or to either Party under Section 7, above, and which is not resolved by senior management within the time permitted under Section 10(a), above, shall be resolved by arbitration in Seattle, Washington, under the Construction Industry Arbitration Rules of the American Arbitration Association then in eff ect. The decision(s) of the arbitrator(s) shall be final, conclusive and binding upon the Parties. All other disputes shall be resolved by litigation in any court or governmental agency, as applicable, having jurisdiction over the Parties and the dispute. (c) In connection with any arbitration under this Section 10, costs of the arbitrator(s), hearing rooms and other common costs shall be divided equally among the Parties. Each Party shall bear the cost and expense of preparing and presenting its own case (including, but not limited to, its own attorneys' fees); provided, that, in any arbitration, the arbitrator(s) may require, as part of his or her decision, reimbursement of all or a portion of the prevailing Party's costs and expenses (including, but not limited to, reasonable attorneys' fees) by the other Party. (d) Unless otherwise agreed by the Parties in writing, the Parties shall continue to perform their respective obligations under this Agreement during the pendency of any dispute. Construction Agreement, Attachment “B” to Schedule 74, Page 9 Renton – Duvall Ave Sch74 from NE 7th Place to Sunset Boulevard 11. Uncontrollable Forces. In the event that either Party is prevented or delayed in the performance of any of its obligations under this Agreement by reason beyond its reasonable control (a "Force Majeure Event"), then that Party’s performance shall be excused during the Force Majeure Event. Force Majeure Events shall include, without limitation, war; civil disturbance; flood, earthquake or other Act of God; storm, earthquake or other condition which necessitates the mobilization of the personnel of a Party or its contractors to restore utility service to customers; laws, regulations, rules or orders of any governmental agency; sabotage; strikes or similar labor disputes involving personnel of a Party, its contractors or a third party; or any failure or delay in the performance by the other Party, or a third party who is not an employee, agent or contractor of the Party claiming a Force Majeure Event, in connection with the Work or this Agreement. Upon removal or termination of the Force Majeure Event, the Party claiming a Force Majeure Event shall promptly perform the affected obligations in an orderly and expedited manner under this Agreement or procure a substitute for such obligation. The Parties shall use all commercially reasonable efforts to eliminate or minimize any delay caused by a Force Majeure Event. 12. Insurance. (a) PSE shall, and shall require each of its contractors to, secure and maintain in force throughout the duration of the Conversion Project (or, if sooner, until termination of this Agreement) comprehensive general liability insurances, with a minimum coverage of $1,000,000.per occurrence and $1,000,000 aggregate for personal injury; and $1,000,000 per occurrence/ aggregate for property damages, and professional liability insurance in the amount of $1,000,000. (b) The Government Entity shall ensure that each of its contractors performing any Government Work secures and maintains in force throughout the duration of the Conversion Project (or, if sooner, until termination of this Agreement) insurance policies having the same coverage, amounts and limits as specified Section 12(a), above. (c) In lieu of the insurance requirements set forth in Section 12(a), above, the Company may self- insure against such risks in such amounts as are consistent with good utility practice. Upon the Government Entity's request, the Company shall provide the Government Entity with reasonable written evidence that the Company is maintaining such self-insurance. 13. Other. (a) Agreement Subject To Tariff. This Agreement is subject to the General Rules and Provisions set forth in Tariff Schedule 80 of the Company's electrical Tariff G and to Schedule 74 of such Tariff as approved by the Washington Utilities and Transportation Commission and in effect as of the date of this Agreement. (b) Termination. The Government Entity reserves the right to terminate the Conversion Project and this Agreement upon written notice to the Company. In the event that the Government Entity terminates the Conversion Project and this Agreement, the Government Entity shall reimburse the Company for all costs reasonably incurred by the Company in connection with the Work performed prior to the effective date of termination. In such event, the costs reimbursable to the Company (i) shall not be reduced by any Shared Government Costs or other costs incurred by the Government Entity, and (ii) shall be paid within thirty (30) days after the receipt of the Company's invoice therefor. Sections 1, 5, 7, 8, 9, 10, 11 and 13 shall survive any termination of the Conversion Project and/or this Agreement. (c) Facilities Greater Than 15,000 Volts. Nothing in this Agreement shall in any way affect the rights or obligations of the Company under any previous agreements pertaining to the existing or future facilities of greater than 15,000 Volts within the Conversion Area. Construction Agreement, Attachment “B” to Schedule 74, Page 10 Renton – Duvall Ave Sch74 from NE 7th Place to Sunset Boulevard (d) Compliance With Law. The Parties shall, in performing the Work under this Agreement, comply with all applicable federal, state, and local laws, ordinances, and regulations. (e) No Discrimination. The Company, with regard to the Work performed by the Company under this Agreement, shall comply with all applicable laws relating to discrimination on the basis race, color, national origin, religion, creed, age, sex, or the presence of any physical or sensory handicap in the selection and retention of employees or procurement of materials or supplies. (f) Independent Contractor. The Company and the Government Entity agree that the Company is an independent contractor with respect to the Work and this Agreement. The Company is acting to preserve and protect its facilities and is not acting for the Government Entity in performing the Work. Nothing in this Agreement shall be considered to create the relationship of employer and employee between the Parties. Neither the Company nor any employee of the Company shall be entitled to any benefits accorded employees of the Government Entity by virtue of the Work or this Agreement. The Government Entity shall not be responsible for withholding or otherwise deducting federal income tax or social security or contributing to the State Industrial Insurance Program, or otherwise assuming the duties of an employer with respect to the Company, or any employee of the Company. (g) Nonwaiver of Rights or Remedies. No failure or delay of either Party to insist upon or enforce strict performance by the other Party of any provision of this Agreement or to exercise any other right under this Agreement, and no course of dealing or performance with respect thereto, shall, except to the extent provided in this Agreement, be construed as a waiver or, or choice of, or relinquishment of any right under any provision of this Agreement or any right at law or equity not otherwise provided for herein. The express waiver by either Party of any right or remedy under this Agreement or at law or equity in a particular instance or circumstance shall not constitute a waiver thereof in any other instance or circumstance. (h) No Third Party Beneficiaries. There are no third-party beneficiaries of this Agreement. Nothing contained in this Agreement is intended to confer any right or interest on anyone other than the Parties, their respective successors, assigns and legal representatives. (i) Governmental Authority. This Agreement is subject to the rules, regulations, orders and other requirements, now or hereafter in effect, of all governmental regulatory authorities and courts having jurisdiction over this Agreement, the Parties or either of them. All laws, ordinances, rules, regulations, orders and other requirements, now or hereafter in effect, of governmental regulatory authorities and courts that are required to be incorporated into agreements of this character are by this reference incorporated in this Agreement. (j) No Partnership. This Agreement shall not be interpreted or construed to create an association, joint venture or partnership between the Parties or to impose any partnership obligations or liability upon either Party. Further, neither Party shall have any right, power or authority to enter into any agreement or undertaking for or on behalf of, to act as or be an agent or representative of, or to otherwise bind the other Party. (k) Severability. In the event that any provision of this Agreement or the application of any such provision shall be held invalid as to either Party or any circumstance by any court having jurisdiction, such provision shall remain in force and effect to the maximum extent provided by law, and all other provisions of this Agreement and their application shall not be affected thereby but shall remain in force and effect unless a court or arbitrator holds they are not severable from the invalid provisions. Construction Agreement, Attachment “B” to Schedule 74, Page 11 Renton – Duvall Ave Sch74 from NE 7th Place to Sunset Boulevard (l)Notice. Any notice under this Agreement shall be in writing and shall be faxed (with a copy followed by mail or hand delivery), delivered in person, or mailed, properly addressed and stamped with the required postage, to the intended recipient as follows: If to the Government Entity: City of Renton 1055 South Grady Way Renton, WA 98057 Attn: Flora Lee Phone: 425-430-7303 If to the Company: Puget Sound Energy, Inc. 6905 S. 228th Street Kent, WA 98032 Attn: Gary Bradley Phone: 253-234-6302 Any Party may change its address specified in this Section 13(l) by giving the other Party notice of such change in accordance with this Section 13(l). (m)Applicable Law. This Agreement shall in all respects be interpreted, construed and enforced in accordance with the laws of the State of Washington (without reference to rules governing conflict of laws), except to the extent such laws may be preempted by the laws of the United States of America. (n)Entire Agreement. This Agreement constitutes the entire agreement of the Parties with respect to the subject matter hereof and all other agreements and understandings of the Parties, whether written or oral, with respect to the subject matter of this Agreement are hereby superseded in their entireties; provided, however, that except as expressly set forth in this Agreement, nothing herein is intended to or shall alter, amend or supersede the Design Agreement and the same shall remain in full force and effect in accordance with its terms. (o)Successors and Assigns. This Agreement shall be binding upon and inure to the benefit of the respective successors, assigns, purchasers, and transferees of the Parties, including but not limited to, any entity to which the rights or obligations of a Party are assigned, delegated, or transferred in any corporate reorganization, change of organization, or purchase or transfer of assets by or to another corporation, partnership, association, or other business organization or division thereof. Government Entity: Company: PUGET SOUND ENERGY, INC. BY BY ITS ATTEST:Date Signed Approved as to form: City of Renton Armondo Pavone, Mayor Approved by Cheryl Beyer via 8/9/2021 email 8/25/2021 Jason A. Seth, City Clerk Supervisor of Public Improvement 9/7/2021 Scope of Work To: City of Renton 1055 South Grady Way Renton, WA 98057 Attn: Flora Lee Project Description:Sch 74 OH/UG conversion Location:Duvall Ave NE, from NE 7th Place to Sunset Blvd PSE Project Manager:Gary Bradley 253-234-6302 Activity: PSE Order #: 40%40%60% PSE Materials $34,549.85 PSE Construction Labor 129,584.00$ 61,890.00$ City Obligation $0.00 PSE Project Management $10,355.13 $15,620.00 PSE Obligation $0.00 PSE Inspection 30,661.00$ PSE Overheads $1,553.27 63,143.94$ Federal Income Tax $1,040.72 $23,907.29 Total Actual Costs:$12,949.12 $297,466.08 $61,890.00 TOTAL PROJECT VALUE:3 Date:12/31/2018 FACILITY CONVERSION/MODIFICATION BILLING DETAIL The City of Renton requests PSE to convert OH/UG Sch74 on Duvall Ave NE, from NE 7th Place to Sunset Blvd. The associated with the portions of this projec are 40% reimbursable to PSE. Customer Installed Duct and VaultPSE Construction Cost Estimate 101120019 101120019 PSE Design Cost Change Orders City of Renton Credit for D+V: 101120019 City Cost Share City Cost Share PSE Cost Share City of Renton Obligation Incl/CO's:$124,166.08 $87,032.08 ($37,134.00) $372,305.20 City of Renton Invoice/Credit Amount: Puget Sound Energy, Inc. PO Box 90868 Bellevue, WA 98009-0868 Billing Detail Form 5/01 City of Renton Duvall Ave NE Schedule 74 Underground Conversion Page 1 Work Order 101120019 Exhibit “A” Project Plan Schedule 74 Underground Conversion City of Renton – Duvall Ave NE Schedule 74 Conversion PSE Project Number: 101120019 August 5, 2021 Pursuant to Puget Sound Energy (“PSE”) Rate Schedule 74 and as described in this Project Plan, PSE will convert its existing overhead electrical distribution system of 15,000 volts or less to an equivalent Underground Distribution System. This Project Plan describes the scope of construction work (the “Construction Work”) to be performed by PSE and the City of SeaTac (the “City”) for the conversion of certain PSE electrical distribution system facilities as described herein (the “Conversion Project”). Construction of this Conversion Project is contingent upon and shall commence only after both written acceptance of this Project Plan and written execution of a Schedule 74 Construction Agreement by the City and PSE. This Project Plan includes and consists of: Description of the Construction Work to be performed Construction Drawings, Standards, Specifications and Requirements for the Construction Work (attached) Operating Rights to be obtained for the Conversion Project are depicted in the attached PSE design. Construction Work Schedule Construction Costs Estimate Summary (attached) Revisions to this Project Plan must be mutually approved by the City and PSE. Construction Work This Conversion Project will replace PSE’s existing overhead electrical distribution system with an Underground Distribution System within the following area (the “Conversion Area”): Duval Ave NE between NE 7 th Pl and NE 12th St. the Conversion Project is approximately (1,095’) feet in length, including laterals and road crossings. The Conversion Project includes modification or replacement of all existing services lines within the Conversion Area to connect to the Underground Distribution System and removal of PSE’s existing overhead electric distribution facilities (including PSE distribution poles and pole mounted street lights) from the Conversion Area. City of Renton Duvall Ave NE Schedule 74 Underground Conversion Page 2 Work Order 101120019 There are no Company Initiated Upgrades, Government Entity Requested Upgrades or Temporary Service elements included in the Conversion Project Scope of Work. In conjunction with this Conversion Project, PSE will remove its existing street lighting system from the Conversion Area. Provision of a replacement street lighting system within the Conversion Area is not included in this Project Plan. Replacement street lighting service can be provided by separate arrangement in accordance with applicable PSE Tariff Schedules. Responsibilities of Parties City Responsibilities a) At least ten (10) business days prior to the scheduled commencement of Construction Work, hold a pre-construction meeting involving all participants in the Conversion Project to review project design, coordination requirements, work sequencing and related premobilization requirements. b) At least fifteen (15) business days prior to the scheduled commencement of Construction Work, give PSE written notice to proceed with the Construction Work to allow for delivery of PSE materials to the job site and scheduling of PSE’s on-site Inspector. c) Provide written notice to customers within the Conversion Area in advance of Conversion Project Construction Work start. The notice will include contact information for both the City and PSE, the expected Conversion Project schedule, anticipation of service interruptions and work required to be performed by customers. d) Coordinate other utility conversion, removal and relocation from PSE’s poles. e) Provide all surveying for equipment placement, locations, and establish all grade elevations for the Underground Distribution System within the Conversion Area. f) Provide all necessary excavation, bedding, backfill, off-site disposal, site restoration and coordination for installation of the Underground Distribution System. This includes trenching, backfill, and restoration for cut-over and transfer of existing underground system and service lines from the existing overhead distribution system to the new Underground Distribution System. g) Coordinate private property trenching, excavation and restoration activity with private property owners affected by this Conversion Project. h) Provide flagging and traffic control as required for all work performed by the City. i) Install and proof all ducts and vaults for the Underground Distribution System (excluding work in ducts or vaults containing energized cables or equipment – see PSE Responsibilities) in accordance with PSE standards and specifications using ducts and vaults provided by PSE. “Proofing” as used herein is defined as verification using a mandrel that the duct and vault system is free and clear of damage, installed to the proper grade and at the proper location and contains a pulling line. j) Provide at least fifteen (15) business days’ notice for scheduled delivery of PSE vaults by PSE’s vault supplier. City of Renton Duvall Ave NE Schedule 74 Underground Conversion Page 3 Work Order 101120019 k) City’s contractor to provide secure staging and storage area(s) for duct and vault materials provided by PSE. The City shall be responsible for the security and condition of these materials until they are installed and accepted by PSE or returned to PSE’s custody. All PSE materials required for the installation of duct and vault will be delivered in one effort to the City’s designated staging area in one effort. Material delivery will not be broken up into multiple efforts or phases. l) Provide labor and equipment for the off-loading of PSE duct and vault materials delivered to the job site. m) Promptly following notice from PSE that the Underground Distribution System has been energized, provide notice to customers within the Conversion Area informing them of their obligation and responsibility to convert their overhead service lines to underground service lines as provided by state law or to modify existing underground service lines for connection to the Underground Distribution System. Affected service lines are listed in the Service Lines section of this Project Plan. n) Facilitate weekly (or as otherwise agreed by the City and PSE) construction coordination meetings to include all relevant parties participating in the conversion including PSE and it’s contractor(s), the City and it’s contractor(s), and other utilities. o) Modify, reroute or replace service lines to City owned facilities to connect to the Underground Distribution System. p) Following notification from PSE that Construction Work is complete, provide to PSE any Shared Government Costs as provided for in the Construction Agreement. Puget Sound Energy Responsibilities a) Provide all duct and vault materials, cables, electrical equipment and components necessary for installation of the Underground Distribution System including certifications of materials origins (COMOs) as may be required for products that must meet applicable provisions of the Buy America Act as administered by the Federal Highways Administration (FHWA) and/or the Federal Transit Administration (FTA). b) Following notice from the City, deliver or cause to be delivered all duct and vault materials to the designated staging/storage area(s). Acknowledge delivered quantities and condition of duct and vault materials by signing shipping manifests. c) Following notice from the City, provide inspection services needed for overseeing the proper installation of ducts and vaults by the City. d) Accept delivery of the completed duct and vault system once the new system has been proofed (as described above) by the City. PSE will provide a mandrel to the City to be used in proofing of the duct and vault system. e) Provide PSE electrical workers to complete duct installation and proofing when such work is performed at or in any energized vault containing energized cables or equipment. f) Install (except for ducts and vaults installed by the City) and energize the Underground Distribution System. Provide written notice to the City when the Underground Distribution System is energized. City of Renton Duvall Ave NE Schedule 74 Underground Conversion Page 4 Work Order 101120019 g) Perform cut-over and transfer of existing Underground Distribution System and existing underground service lines from the overhead distribution system to the new Underground Distribution System where applicable (see City Responsibility item “f” concerning trenching responsibility). PSE will notify the City for excavation and the affected customers at least two (2) business days prior to installation, transfer, and connection of underground service lines. Affected service lines are listed in the Service Lines section of this Project Plan. h) Install and connect replacement underground service lines to single family residences and connect modified and replacement non-residential underground service lines provided by customers within the Conversion Area pursuant to PSE Tariff Schedule 85. Affected service lines are listed in the Service Lines section of this Project Plan. i) Remove the existing overhead electric distribution system including, conductors, equipment, down guys, anchors and poles after all service lines to customers within the Conversion Area are connected to the Underground Distribution System and all other utilities have been removed from PSE’s poles. Holes left following removal of poles will be filled with crushed rock and compacted in accordance with applicable City standards or specifications. j) Provide flagging and traffic control as required for all work performed by PSE (except as may otherwise be reasonably provided by the City during installation of ducts and vaults in conjunction with City performed trenching, excavation, back-fill and restoration). k) Attend weekly (or as otherwise agreed by the City and PSE) construction coordination meetings facilitated by the City and its contractor during periods of Conversion Project construction. The Underground Distribution System will be located within existing Public Thoroughfare. No additional operating rights have been identified as being needed for this Conversion Project. Construction Work Schedule The Construction Work will be performed in accordance with the following Work Schedule, unless this schedule is revised by mutual agreement of the City and PSE or circumstances beyond the reasonable control of the City and/or PSE preclude such performance. Installation of ducts and vaults: Duct and Vault schedule will begin around summer of 2021. PSE inspector will be scheduled based on the assumption of the city’s contractor producing an average of 40 (forty) trench feet per day. An anticipated 1,095’ for trench at 40 feet per day a PSE inspector will be required for 211 hours or 27 working days. Additional inspection time will require a change order. Installation and energization of the Underground Distribution System: is estimated to begin fall of 2021. PSE anticipates 138 hours or (17 working days) to pull in new underground conductor and energize the new underground system. Removal of overhead facilities and poles: is estimated to begin (once all utilities have been removed from PSE poles.) and is anticipated to be (6 working days) of construction. Work Schedule Restrictions: (Work retractions will be provided to PSE in the City Right of Way permit). No restrictions are anticipated at the time of quoting PSE’s work City of Renton Duvall Ave NE Schedule 74 Underground Conversion Page 5 Work Order 101120019 Construction Cost Estimate The estimated costs to perform the Construction Work and the allocation of costs between the parties are presented in the attached Construction Costs Estimate Summary. These estimated costs are valid for ninety (90) days from the date shown on the attached Construction Costs Estimate Summary. If this Project Plan and a Schedule 74 Construction Agreement are not fully executed within ninety (90) days from this date, the estimated costs shall be subject to revision. The scope of work provided for in the previously executed Design Agreement has been completed with written acceptance of this Project Plan by the City and PSE. The Construction Cost Estimate reflects and provides for Construction Work costs commencing with PSE attendance at the required pre-construction meeting and receipt of the City’s written notice to proceed with Construction Work. Work performed and/or costs incurred by PSE in response to City request following acceptance of the Project Plan and prior to the pre-construction meeting are not included in the Construction Cost Estimate, and shall be subject to addition to the Construction Cost Estimate by revision as described below. Estimated Inspection and Service Provider Outside Services costs are based on 2021 contract rates. Costs for Construction Work performed by PSE in 2022 shall be subject to revision to reflect PSE Service Provider contract rates which become effective after this date. Changes in Construction Work scope, performance and/or schedule can result in actual Construction Costs that differ from estimated costs shown in the Construction Cost Estimate Summary. In the event performance of the Construction Work cannot or does not proceed substantially as provided in this Project Plan, such changes shall promptly be brought to the attention of PSE and the City when anticipated or known and shall be documented in a revision to the Construction Cost Estimate (a “Cost Estimate Revision”) mutually agreed and executed by the City and PSE. Project Assumptions The project design, construction plans and cost estimates are based on and reflect the following assumptions. Construction conditions that are not consistent with these assumptions may result in a request for change or an equitable adjustment to project compensation under Section 6 of the Construction Agreement and addressed by a Cost Estimate Revision. Cost Assumptions 1. The Construction Work will be performed in accordance with the Construction Drawings and Construction Work Schedule. 2. PSE’s Project Manager will accept or reject (with written justification) the duct and vault installation work performed by the City within five (5) business days’ notice of completion City of Renton Duvall Ave NE Schedule 74 Underground Conversion Page 6 Work Order 101120019 from the City. In the event PSE rejects any of the ducts or vaults (with reasonable written justification), the City will perform the necessary remedial work. The City will then re- notify PSE and PSE shall have five (5) business days to accept or reject the remedial work. 3. All PSE cables can be pulled through the ducts and vaults system, including existing ducts and vaults if applicable, to be used for the Conversion Project utilizing normal cable pulling equipment and methods. 4. A City Street Use permit is the only permit necessary for PSE to perform its work for this Conversion Project and will be issued within two (2) weeks of PSE submitting a complete permit application (including any supporting documentation reasonably required by the City). There will be no charge for the permit or inspection fees. 5. The estimated daily productivity rate for PSE duct and vault installation is based on the City’s contractor opening a minimum of (60) feet of trench per working day. The daily productivity rate is used to estimate the number of days a PSE Inspector will be required during installation of ducts & vaults. The Inspector will be scheduled in full day increments and in one continuous effort. Changes to a continuous schedule require a minimum of five days advance notice and must be mutually agreed between the City and PSE. 6. Attendance by the PSE Project Manager at scheduled weekly construction coordination meetings is included and reflected in the Construction Cost Estimate during periods when the PSE ducts and vaults are actively being installed and when the PSE line crew is performin g installation, energization, cut-over and removal work. Attendance at additional meetings that may be requested/required during other periods will be addressed by a Cost Estimate Revision. 7. Traffic control provided by PSE assumes the use of two flaggers, basic signage and simple channelization. Additional traffic control measures are not included and if requested/required will be addressed by a Cost Estimate Revision. 8. Work to be performed by PSE does not include installation and/or removal of Temporary Service facilities at the request of others during construction. 9. Cut-over and transfer work will be completed during regular working hours except as described in Schedule Assumption #3 below. Changes in the performance of this work will be addressed by a Cost Estimate Revision. 10. New guy anchors shall be installed prior to installation of new ducts in the same area. 11. When Fluidized Thermal Backfill (FTB) is used, associated cost will be allocated 100% to PSE when required for a Company Initiated Upgrade and otherwise 100% to the City. 12. Installation of protective bollards may be necessary at some locations and may not be included in the project design. In the event unplanned bollards are required, associated costs will be a Shared Cost and addressed by a Cost Estimate Revision. Schedule 1. There will be a total of two (2) PSE crew mobilizations as follows: i) one mobilization of an underground line crew for installation of underground conductors and equipment; and ii) one mobilization of an overhead line crew for removal of the existing overhead facilities. Once City of Renton Duvall Ave NE Schedule 74 Underground Conversion Page 7 Work Order 101120019 mobilized PSE crews will have continuous productive work until all PSE Construction Work is complete. 2. All PSE Construction Work will be performed during regular working hours excluding holidays. In the event that lane closures are necessary for performance of work, PSE shall be limited to working between the hours of . PSE and the City will mutually agree to weekly work schedules for the Construction Work. PSE shall be allowed to perform PSE work as scheduled without changes or interruptions caused by other construction activities. 3. PSE customers within the Conversion Area will experience interruption of electric service during performance of the Construction Work when cutting over and transferring system and customer loads from the overhead distribution system to the Underground Distribution System. Cut-over and transfer work will be performed during the regular working hours specified in Schedule Assumption #2 above except as otherwise provided below. PSE will notify customers at least two (2) business days in advance of scheduled service interruptions. Additional Considerations Service Lines Service lines within the Conversion Area must be modified or replaced to provide underground service from the Underground Distribution System as described in Construction Drawings. Performance of the work and associated costs shall be governed by PSE Tariff Schedule 85. New Service Connection of new or increased load for City facilities (such as new traffic signals) under terms of PSE Tariff Schedule 85 will be addressed on a separate work order and work sketch. Additional costs may apply and will be quoted separately. PSE Design & Construction Standards This Conversion Project has been designed and will be constructed in accordance with PSE design and construction standards in effect as of the date of this Project Plan. PSE standards applicable to Construction Work to be performed by the City have been provided to the City in PSE’s “Electric Distribution Trench/Duct/Vault Construction Standards, 2013”. All relevant PSE standard described above are attached to this Project Plan by this reference. Temporary Support (Holding) of PSE Poles Whenever any pole(s) are required to be temporarily supported (held) due to excavation in proximity to such poles, the City will coordinate with PSE to provide such support. The need to temporarily support such poles shall be determined by PSE, and if required, such support shall be provided by PSE. As used herein, “temporary support” means supporting one or more poles for a continuous working period of ten hours or less. City of Renton Duvall Ave NE Schedule 74 Underground Conversion Page 8 Work Order 101120019 Adjusting Energized Vaults to Final Grade If PSE is required to adjust (newly installed) and energized vault lids to final grade PSE will submit a change order to the City for labor and materials required for finial adjustment. This change order will be 100% City Cost. Any “existing” energized vault’s that require final grade adjustments will be performed by PSE at 100% PSE cost. Acceptance of Project Plan The City and PSE mutually agree to and accept this Project Plan as of the date indicated below: For the City: For PSE: By: ______________________________ By: _____________________________ Its: ______________________________ Its: _____________________________ Date: ____________________________ Date: ___________________________ Armondo Pavone, Mayor 8/25/2021 Jason Airey, Supervisor of Public Improvement 9/7/2021 P01 NE 7TH ST P01 NE 7TH ST N Vicinity Map 101120019ARE TO BE INSTALLED, CROSS SECTION DETAILS OF THE TYPICAL EROSION STRUCTURES, & SPECIAL REQUIREMENTS FOR WORK IN SENSITIVE AREAS.) EROSION & SEDIMENT CONTROL REQUIREMENTS NOTES DETAILING WHERE EROSION OR SEDIMENT CONTROL STRUCTURES (LOCAL JURISDICTIONS MAY HAVE ADDITIONAL REQUIREMENTS INCLUDING 0150.3200 TECHNIQUES FOR TEMPORARY EROSION & SEDIMENT CONTROL EROSION & SEDIMENT CONTROL SHALL BE PER PSE STANDARD PRACTICE & ANY ADDITIONAL LOCAL JURISDICTION REQUIREMENTS. FOREMAN (CHECK BOX WHEN COMPLETED) PSE Equipment LOCKED/SECURED & Work Area left in CLEAN/SAFE Condition. Grid, Cable, and Switch numbers INSTALLED & VERIFIED. Field Changes RED-LINED on As-built. Indicate correct FUSE SIZE on As-built & VERIFY proper PHASE. Foreman's Signature _______________________________________________ Print Name ___________________________________ Date ______________ Material VERIFIED and CHANGES noted on Paperwork. Total PRIMARY Cable noted on As-built. Company ID#'s RECORDED in correct location on As-built. Deviations noted on the As-built and their reason. I certify that the work performed meets PSE's standards and procedures and that all quality requirements are met. Yes Yes Yes "Flagging Required" "Outages Required" "Locates Required" LEGEND EXISTING PROPERTY LINE EXISTING UG RISER NEW UG RISER SVC STUB J-BOX NEW TRENCH LINE EXIST. 3Ø WIRE EXISTING CENTER LINE EXISTING CONDUCTOR TO BE REMOVED DISCONNECT - FUSED EXIST. 1Ø WIRE EXISTING RIGHT OF WAY PROPOSED PULL VAULT EXISTING POLE DOWN GUY EXISTING SECONDARY SERVICE LINE DISCONNECT - UNFUSED EXISTING STREETLIGHT NEW POLE PROPOSED PADMOUNT TRANSFORMER EXISTING PADMOUNT TRANSFORMER PROPOSED TOTAL UNDERGROUND TRANSFORMER EXISTING TOTAL UNDERGROUND TRANSFORMER HANDHOLE PRIMARY METERING POINT RENTON DUVALL AVE NE SCHEDULE 74 OH TO UG CONVERSION PSE GENERAL SPECIFICATIONS Scope of Work - OH to UG conversion along Duvall Ave NE between NE 7th Pl and NE Sunset Blvd. General -All work is to be completed per PSE Standards & Practices. Copies of all PSE Standards are available upon request. -Work sites shall be kept clear of debris and all construction materials; equipment and packing shall be removed daily. -Return all unused and removed poles, transformers and hardware to PSE, storeroom. All copper shall be coiled and returned the day it is removed from the poles. Remove all unused pins and insulators. -Return all streetlights, area lights and floodlights to Sumner yard. Pre-Construction -Notify appropriate city, County or DOT authorities 48 to 72 hours, or as required by permitting agency, in advance of starting work in Right-of-way involving a Permit. -All system switching shall be approved by System Operations (425-882-4652) a minimum of 48 hours in advance. -Notify customers of all outages 48 hours in advance. Work Drawings & Documents -PSE Project Manager or Engineer shall approve field design changes. -Mark all field changes, equipment ID numbers and Underground cable information in red on Foreman's copy of work sketch. -Return one Foreman's copy of work sketch to Project Manger at completion of job. -When permits are required, a copy of the permits shall be available on work site at all times. Safety - efer to PSE standards 6275.3000 for requirements on System Grounding -Refer to PSE standards 6275.9210, 6275.9230 and 6275.6250 for personal protective grounding requirements. -Refer to PSE standards 6275.9150 for vehicle grounding and barricading requirements. -Proper line clearances shall be taken at the beginning, and released at the end, of each workday, or as otherwise instructed by the System Operator. -Provide signs, barricades, and traffic control in conformance with permit regulations. -Utilize flagging and other vehicle traffic control as necessary and in conformance with local traffic regulations. -Maintain traffic flow as required by permitting agency. Joint Facilities -Coordinate with Communication Companies for transfers. OVERHEAD CONSTRUCTION Poles & Structures -Poles are to be installed or relocated as staked. Unless otherwise noted, all pole location measurements are from the center of the pole. -All new poles set shall be the class indicated on the sketch, or better. Do not set a lower class pole than specified. -Install ground plate assembly on all new poles. Install Switch Ground Assembly per standard specification 6014.1000 at new gang operated switch locations. -Install grid numbers on all new and existing poles as shown on sketch. -Straighten existing poles as indicated or as necessary. -Treat all field-drilled poles with copper napthenate wood preservative. -Remove old poles after communication companies have transferred off and return to PSE storeroom. Fill and crown pole holes and restore the area similar to adjacent landscaping. Conductors & Equipment -Transfer all overhead and underground primary, secondary and service conductors and guys to new poles set, unless otherwise indicated on this sketch. -Transfer existing transformers to new poles unless otherwise indicated on this sketch. -Use stirrups to connect all overhead and underground primary taps, and all transformers. Install at all sites being worked within the scope of the project where they are currently missing. - For 12vK construction, install avian protection with #4 CU-covered jumpers (MID#9998076) and #4 SD Aluminum covered tie-wire (MID#8309760). For 34vK construction use bare wire primary jumpers with pre-formed helical-grip ties and avian protection devices when required per Std. 6015.2000. Jumpers for poles that are double dead ended with tree wire can be either the same size tree wire conductor or covered CU. -Apply grit inhibitor on all Ampact, stirrup, and dead-end connections. -Connect primary taps and transformers to same phase as existing unless otherwise shown on the drawing. -All neutral connections to be made with solid compression connectors. Connect all pole grounds to common neutral. -Use Load-interrupter cutouts (with arc shields) on all primary overheads and underground taps with fused protection above 40T. -Install Wildlife Protectors on all transformers. Cable Tags and Pulling -Primary Underground Cable Identification Tag installation shall conform to PSE standards 6825.6050. -Cable Pulling shall conform to PSE standards 6825.6100 and 6825.6150 RESPONSIBILITIES OF THE CITY Documentation -The city and their contractor shall attend a pre-construction meeting specifically for installation of bare duct and vault system. -PSE will provide to the city contractor with construction plans for the installation of PSE duct and vault system. -All installations shall conform to specifications contained in this document and all relevant PSE standards. Safety -Field changes shall be pre-approved by PSE or designated representative prior to construction with proof of acceptance required prior to PSE acceptance of completed duct and vault system. -The city contractor shall not access energized power vaults without the assistance of PSE line workers. Trench and Excavation -The city contractor shall not expose energized power conductors (direct buried or in conduit) without the assistance of PSE line workers. -The city shall provide all trench excavation and backfill for the installation of new or modified PSE underground distribution system within the construction area. -All trench excavation shall conform to PSE standards 6790.0075, 6790.0130, 6790.0140, 6790.0250, and 6790.3050. -PSE plans show general trench alignment. They do not show specific cross sections with existing or proposed other utilities. It is the City's responsibility to install PSE facilities at necessary depths to avoid and provide required clearances to other existing or proposed utilities. -Construct the shared utility trench where the various utilities can transition in and out of the trench line in an orderly fashion without altering duct bank alignments of other utility. Separation of crossing utilities sharing the common utility trench is 6”. -After the new underground system is installed an energized, additional excavation may be necessary to re-train existing underground cables into the new vaults. This excavation will be provided by the city with 48 hours notice. - Placement of other utility vaults within the trench line alignment encumbering access to PSE facilities is not allowed. - If four or more six inch conduits are installed in a trench, fluidized thermal backfill (FTB) shall be installed around the conduits to a depth of six inches above and to the sides of the conduit, and two inches underneath, per PSE Standard 6790.0140. Vault Installation -City shall install PSE vaults in accordance with PSE standards 6775.0035 and 6775.0040. -Vault hole excavation shall be prepared level and free of debris with a minimum 6” base of crushed rock to prevent vault settling. -PSE Vaults in planter areas shall be set 2” above final grade. -PSE Vaults in hard surface locations such as sidewalks shall be adjusted to match finished grade prior to the installation of PSE conductors and equipment. Maximum adjustment up is 5”- more than 5” require and additional riser. - Note: The city contractor will not be allowed to make vault adjustments after PSE conductors and equipment are energized. PSE line crew will perform the adjustments on a change order basis. -City shall provide all surveying necessary to assure all PSE vaults are installed in the alignment location specified in this document. The city shall be responsible for establishing grade elevation for PSE vaults. -All PSE vaults shall be clean and clear of construction debris with all knockouts and cover adjustments grouted to PSE satisfaction prior to PSE accepting delivery of bare conduit & vault system. Conduit Installation -All PSE conduit installations shall conform to PSE standards 6800.6000, 6800.8050, and 6825.6505. -All conduits shall be routed and installed per conduit tables, installation diagrams, and details in this work sketch. -The city shall proof every PSE conduit run prior to final PSE acceptance. Proofing is defined as pulling a mandrel of the same diameter through the conduit. Mule tape provided by PSE shall be pulled in behind the mandrel in each conduit run as evidence of proofing. A plug shall be installed in all spare conduits. -All conduits entering PSE vaults shall be through the appropriate knockouts to ensure proper cable lay. Vault entries causing cables to cross each other in the vault, or lay in the vault unevenly, will be rejected and corrected at the expense of the city contractor. - All conduit entries into PSE vault shall be straight and level with a minimum of 6' straight section outside the vault wall and 2” on conduit extending into the vault with bell ends installed. - PSE conduits shall be placed in the trench maintaining a minimum of 1-1/2” of separation. Use conduit spacers (provided by PSE) every 10'. -PSE conduit runs shall be placed straight and level. Should it become necessary to alter conduit alignments to avoid other utilities the maximum bend radius allowed is 22-1/2 degrees. Bend radius greater than 22-1/2 degrees require prior approval from PSE engineering representatives. -All PSE conduits shall be placed with the minimum separation between other utility facilities as specified in PSE standard 6790.0130. Refer to the typical utility trench cross section detail in this work sketch. -All PSE conduits shall have a minimum of 36” of cover. Cover of less than 36” is permissible on a case by case basis provided that such installations adhere to PSE standard 6790.0130 figure 2. Pre-approval by PSE engineering representatives is required. -City installed empty conduit is not able to be located by normal means. It is the City's responsibility to note the location and depth of the installed conduit and protect it from damage by themselves or others throughout the duration of the project. Materials -The city shall not backfill PSE facilities until authorized by the PSE Inspector. -City shall be responsible for the security all PSE materials delivered to the job site. -The city contractor shall sign material manifest slips for all PSE materials delivered to the job site. -Initial delivery of PSE materials to the job site requires 10 days minimum advanced notice to PSE storeroom. -After the initial delivery of materials subsequent bulk material deliveries to the job site by PSE vendors require a minimum of 5 days- advanced notice to PSE storeroom. -PSE representatives will provide delivery of all miscellaneous material necessary for duct & vault installation, such as couplings, glue, bends, etc., with minimum 3 days advanced notice to the PSE storeroom. -City shall provide equipment and labor necessary to off load material on site. -All vaults will be delivered by the manufacture to the job site as follows: --575 and smaller with a minimum 3 days advanced notice to PSE storeroom. --5106 and larger with a minimum 5 days advanced notice to PSE storeroom. -If vault excavation is not ready when vaults are delivered, city contractor will provide necessary equipment to install vaults. Install mastic sealant between the sections of mult-section vaults (sealant provided by manufacturer). -All unused material shall be returned to PSE stores and reconciled after PSE duct & vault installations are complete. Inspection -PSE will provide an Inspector during city contractor installation of PSE bare duct and vault system. -The roll of the PSE Inspector is limited to verification of compliance to all relevant PSE standards and practices. The PSE Inspector will not approve changes to planned PSE facility locations or change orders. -The PSE Inspector will be the contact for all issues concerning installation of bare duct and vault system for PSE and provide a liaison between the field and engineering for change requests. -The city shall provide the PSE Inspector the means (survey staking) to verify proper depth of burial and location for all PSE facilities to the satisfaction of the PSE Inspector on site. If the Inspector is unable to verify proper depth of burial, location, or grade of PSE facilities a non-compliance document will be issued effecting PSE final acceptance of city installed facilities for PSE. Owner / Developer Contact Info officeATTN: FLORA LEE CITY OF RENTON FLEE@RENTONWA.GOV 425-430-7303PHONE CABLE TV 11504976 101120019 583061726 108113555 PROJECT PHASE PWR NOTIF#ORDER# Superior UG Expense Removal OH Expense 593207689 594127951 OH Expense E-Mail: Cell Phone: Project Manager Contact Information: Manager:HONG NGUYEN 425-449-6609 HONG.NGUYEN@PSE.COM THIS SKETCH NOT TO BE RELIED UPON FOR EXACT LOCATION OF EXISTING FACILITIES CALL 811 TWO BUSINESS DAYS BEFORE YOU DIG For contacts below dial 1-888-CALL PSE (225-5773) UTILITIES CONTACT PHONE# COUNTY 1/4 SEC U-MAP NO (POWER) OP MAP Emer Sect Gas Wk Ctr POWER WK CTR PLAT MAP JOINT FACILITIES ARRANGEMENTS DRAWN BY CHECKED BY APPROVED BY FOREMAN #1 FOREMAN #2 MAPPING INCIDENT MAOP Gas Order Elect Order SCALE PAGE ENGR - POWER ENGR - GAS FUNCTION PROJECT MGR PERMITREAL ESTATE/EASEMENT 2 1 REV# 3 DATE DESCRIPTIONBY CONTACT PHONE NO DATE OH CKT MAP CIRCUIT NOUG CKT MAP HONG NGUYEN 425-449-6609 9/13/19 KEANG LIM 253-395-6916 9/13/19 N/A N/A N/A KEANG LIM 253-395-6916 9/13/19 REQUIRED CITY OF RENTON RENTON DUVALL AVE NE SCH74 OH TO UG CONVERSION 1100 DUVALL AVE NE RENTON, WA 98059 N/A N/A N/A 101120019 AS NOTED 1/6 KING N/A N/A CSPSKEPI S10 T23 R05E N/A N/A 2305E011, 37 2305E040 N/A PRE-14 N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A JOB SITE 141..Fiber PRE14 PRE 14 101120019SCALE: NONE OVERHEAD CIRCUIT MAP (2305E040) UNIVERSAL CIRCUIT MAP (2305E011, 38) SCALE: NONE UTILITIES CONTACT PHONE# COUNTY 1/4 SEC U-MAP NO (POWER) OP MAP Emer Sect Gas Wk Ctr POWER WK CTR PLAT MAP JOINT FACILITIES ARRANGEMENTS DRAWN BY CHECKED BY APPROVED BY FOREMAN #1 FOREMAN #2 MAPPING INCIDENT MAOP Gas Order Elect Order SCALE PAGE ENGR - POWER ENGR - GAS FUNCTION PROJECT MGR PERMITREAL ESTATE/EASEMENT 2 1 REV# 3 DATE DESCRIPTIONBY CONTACT PHONE NO DATE OH CKT MAP CIRCUIT NOUG CKT MAP HONG NGUYEN 425-449-6609 9/13/19 KEANG LIM 253-395-6916 9/13/19 N/A N/A N/A KEANG LIM 253-395-6916 9/13/19 REQUIRED CITY OF RENTON RENTON DUVALL AVE NE SCH74 OH TO UG CONVERSION 1100 DUVALL AVE NE RENTON, WA 98059 N/A N/A N/A 101120019 AS NOTED 2/6 KING N/A N/A CSPSKEPI S10 T23 R05E N/A N/A 2305E011, 37 2305E040 N/A PRE-14 N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A UNIVERSAL CIRCUIT MAP (2305E011, 38) SCALE: NONE JOB SITE JOB SITE JOB SITE GROUND ROD 895+00896+00897+00898+00EXIST OH SL SVC318416 167323 318394 167322DUVALL AVE NE"809" "818" "824" "815" "821" "830" "836" "842" "848" MATCHLINE - STA 895+00 PAGE 3 MATCHLINE - STA 898+50 PAGE 3 899+00900+00NE 9TH ST J02 318434 167331 EXIST EXIST UG EXIST OH SL SVCSLAH3608 DUVALL AVE NER/WNEW 3-4"R/W"861" FB1 318433 167331 NEW MATCHLINE - STA 898+50 PAGE 3 BREAKLINE TO STA 916+50 PAGE 4 UTILITY EASEMENTNEW 2-4" NEW 1-4"892+00893+00894+00895+00NE 8TH ST NE 7TH PLDUVALL AVE NE"4704" "800" "806" P01 318357 167324 EXIST P02 318373 167324 REMOVE 15T UNK #2 ACSRABM906-B EXIST OH SVCJ01 318372 167324 NEW HH1 NEW R/W#2 ACSR NEW 3-4" NEW 1-2" INTERCEPT SPARES IF FOUND NEW 1-3" "803" "CITY OF RENTON" "809" NEW 3-4" "812" R/W PRE-14 IP01 NEW 1-4" FIBER MATCHLINE - STA 895+00 PAGE 3 V02 318386 167308 EXIST 25kVA 120/240v T83471 EXISTING OH TPX NEW 2-4" NEW 2-4" SITE PLAN 101120019SCALE: 1" = 20' UTILITIES CONTACT PHONE# COUNTY 1/4 SEC U-MAP NO (POWER) OP MAP Emer Sect Gas Wk Ctr POWER WK CTR PLAT MAP JOINT FACILITIES ARRANGEMENTS DRAWN BY CHECKED BY APPROVED BY FOREMAN #1 FOREMAN #2 MAPPING INCIDENT MAOP Gas Order Elect Order SCALE PAGE ENGR - POWER ENGR - GAS FUNCTION PROJECT MGR PERMITREAL ESTATE/EASEMENT 2 1 REV# 3 DATE DESCRIPTIONBY CONTACT PHONE NO DATE OH CKT MAP CIRCUIT NOUG CKT MAP HONG NGUYEN 425-449-6609 9/13/19 KEANG LIM 253-395-6916 9/13/19 N/A N/A N/A KEANG LIM 253-395-6916 9/13/19 REQUIRED CITY OF RENTON RENTON DUVALL AVE NE SCH74 OH TO UG CONVERSION 1100 DUVALL AVE NE RENTON, WA 98059 N/A N/A N/A 101120019 AS NOTED 3/6 KING N/A N/A CSPSKEPI S10 T23 R05E N/A N/A 2305E011, 37 2305E040 N/A PRE-14 N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Vault & Equipment Table Site Working Space Grid Number Vault Size & Cover Type & Size Equipment In Vault Primary Bushings Transformer ID Numbers (Company ID) MATERIAL INFORMATION ASBUILT INFORMATION Foreman-CompleteLBDC J01 NEW 318372 167324 4'8"X7'X5' w/ (2) 3' Sq Doors Mat ID: 7663200 J-Box below grade w/ 4-pos J-Bus Mat ID: 7625900 5 7 JBOX15L INSTALL 5-ELB10J INSTALL 7 DC-7630600 J02 EXISTING 318434 167331 3 -INSTALL 3-ELB10J FB1 NEW 318443 167331 SEE DETAIL (PAGE 6) SITE SPECIFIC NOTES: P01-EXISTING 318357-167324 INSTALL 12kV 1Ø TERM, LB (TSU1C1) [6043.1000] INSTALL SWITCH #T83471 FUSE @ 25T (3412400) INSTALL (3) 4" CONDUIT RISERS (RIS4CSS) 6042.1000 CAP (2) SPARE 4" CONDUIT RISERS 10' UP POLE INSTALL (1) 3" CONDUIT RISER (RIS3CSS) 6042.1000 IP01 EXPOSE AND INTERCEPT EXISTING 1-4" CONDUIT AND EXTEND EAST TO J01 SECONDARY HH TABLE Site Vault Size & Cover Type & Size Equipment in Vault REMARKS HH1 HH14350AS (1Ø) With 2'-4" sq AS Cover PER STD 6050.2020 (3) 4 Position Connector MAT ID: 7651005 INSTALL 3-POS CONNECTOR BARS NOTE: Per Standard 6050.2000 all metal lids of secondary hand holes must be grounded. 917+00918+00919+00920+00"1155" "1160" P04 318612 167316 EXIST P03 318612 167326 RELC 75kVA 120/240v#2 ACSRE X O H S V C J03 318611 167326 NEW NE 12TH ST "1155" J04 318628 167330 NEW P05 318629 167330 REMV 25T UNK EXIST UG SVC EXIST 115kV HH2 NEW J05 318633 167322 EXIST 318630 167312 42158-B 30469-C R/WR/WR/WDUVALL AVE NENEW 1-3", 1-4" EXIST OH SVC NEW 2-4", 1-3" 318630 167300 NEW 2-4" BREAKLINE TO STA 900+00 PAGE 3 MATCHLINE - STA 920+00 PAGE 4 NEW 1-2" NEW 2-4", 2-6" J06 EXIST NEW 2-4" NEW 1-3" EX O H S V C NEW 1-3" TRANSFER 318610 167332 5' X 15' EASEMENT 5' X 25' EASEMENT DWY920+00921+00"4621"DUVALL AVE NEEXIST 318630 167312 42155-A 42156-B 42157-C "1332" 318644 167315 J07 REMV 318644 167314 J08 NEW AAS310-A AAS311-B AAS312-C 30467-A 30468-B 30469-C R/WR/WV03 318650 167308 EXIST 500kVA 120/208v MATCHLINE - STA 920+00 PAGE 4 NEW 2-4", 2-6" J06 EXIST 30464-A 30465-B 30456-C IP04 IP02 318650 167295 FEED PRE 14J09 EXIST 5' X 15' EASEMENT IP03 SITE PLAN 101120019SCALE: 1" = 20' UTILITIES CONTACT PHONE# COUNTY 1/4 SEC U-MAP NO (POWER) OP MAP Emer Sect Gas Wk Ctr POWER WK CTR PLAT MAP JOINT FACILITIES ARRANGEMENTS DRAWN BY CHECKED BY APPROVED BY FOREMAN #1 FOREMAN #2 MAPPING INCIDENT MAOP Gas Order Elect Order SCALE PAGE ENGR - POWER ENGR - GAS FUNCTION PROJECT MGR PERMITREAL ESTATE/EASEMENT 2 1 REV# 3 DATE DESCRIPTIONBY CONTACT PHONE NO DATE OH CKT MAP CIRCUIT NOUG CKT MAP HONG NGUYEN 425-449-6609 9/13/19 KEANG LIM 253-395-6916 9/13/19 N/A N/A N/A KEANG LIM 253-395-6916 9/13/19 REQUIRED CITY OF RENTON RENTON DUVALL AVE NE SCH74 OH TO UG CONVERSION 1100 DUVALL AVE NE RENTON, WA 98059 N/A N/A N/A 101120019 AS NOTED 4/6 KING N/A N/A CSPSKEPI S10 T23 R05E N/A N/A 2305E011, 37 2305E040 N/A PRE-14 N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Vault & Equipment Table Site Working Space Grid Number Vault Size & Cover Type & Size Equipment In Vault Primary Bushings Transformer ID Numbers (Company ID) MATERIAL INFORMATION ASBUILT INFORMATION Foreman-Complete LB DC J03 NEW 318611 167326 4'8"X7'X5'8" w/ (2) 3' Anti-Skid Doors Mat ID: 9996162 J-Box below grade w/ 4-pos J-Bus Mat ID: 7625900 4 8 JBOX3AS INSTALL 4-ELB10J INSTALL 8 DC-7630600 J04 NEW 318628 167330 4'8"X7'X5'8" w/ (2) 3' Anti-Skid Doors Mat ID: 9996162 J-Box below grade w/ 4-pos J-Bus Mat ID: 7625900 6 6 JBOX3AS INSTALL 6-ELB10J INSTALL 6 DC-7630600 J08 NEW 318611 167326 4'8"X7'X5'8" w/ (2) 3' Anti-Skid Doors Mat ID: 9996162 J-Box below grade w/ 4-pos J-Bus Mat ID: 7625900 9 3 JBOX3AS INSTALL 9-ELB10J INSTALL 3 DC-7630600 V03 EXISTING 318650 167308 3 - J09 EXISTING 318650 167285 3 -INSTALL 3-ELB10J SITE SPECIFIC NOTES: P03-NEW 318612-167326 INSTALL 45' CL3 DISTRIBUTION POLE (PD453) [6010.1000] INSTALL 12kV 1Ø TERM, LB, ONE TRF (TSU1C1WT) 6043.1003 INSTALL NEW SWITCH #T83472 FUSE @ 40T (3412500) INSTALL (2) 3" CONDUIT RISERS (RIS3CSS) [6042.1000] INSTALL (1) 2" CONDUIT RISERS (RIS2CSS) [6042.1000] TRANSFER 75kVA TRANSFORMER WITH FUSE AND CUTOUT FROM OLD POLE INSTALL NEW GRID NUMBERS TRANSFER OH SVC P04-EXISTING SERVICE POLE TO REMAIN 318612-167316 INSTALL (1) 3" CONDUIT RISER (RIS3CSS) [6042.1000] IP02 EXPOSE AND INTERCEPT EXISTING 1-4" CONDUIT AND EXTEND WEST TO J08 EXTEND ANY SPARE CONDUITS IF FOUND IP03 EXPOSE AND INTERCEPT EXISTING 1-4" CONDUIT AND EXTEND EAST TO J08 IP04 EXPOSE AND INTERCEPT EXISTING 1-4" CONDUIT AND EXTEND NORTHWEST TO V03 POLE RETIREMENT TABLE TEMP TRANSFERS ST. LIGHT TRANSFERS SITE # POLE DATA POLE TEL TV FIBER TRAN RMVD ID NUMBER GRID #HEIGHT CLASS YEAR TOPPED RMVD P05 318629-167330 WIRE REMOVAL TABLE Location Wire Size & Type Quantity Length (per conductor)RemarksFromTo P03 P04 1/0 TRIPLEX 1 190' P03 P05 #2 ACSR 3 175' Total Feet (Wire Size & Type) Removed CABLE REMOVAL SCHEDULE CABLE NO. LOCATIONS CABLE (LF) EST CABLE TYPE YEAR INST FROM TO BØ42158 P05 J05 135 1/0 AL JKT AØ30467 J06 J07 115 1/0 AL JKT BØ30467 J06 J07 115 1/0 AL JKT CØ30467 J06 J07 115 1/0 AL JKT Total Feet 20 (1/0 AL JKT) ACTUAL________Removed SECONDARY HH TABLE Site Vault Size & Cover Type & Size Equipment in Vault REMARKS HH2 HH14350AS (1Ø) With 2'-4" sq AS Cover PER STD 6050.2020 (3) 4 Position Connector MATID: 7651005 NOTE: Per Standard 6050.2000 all metal lids of secondary hand holes must be grounded. P01 EXIST H J HH1 NEW J01 NEW IP01 H J J JJ IP02 J NEW 1-3" V02 EXIST J02 EXIST FB1 NEW P04 EXIST BREAKLINE J STA 916+50 J03 NEW J08 NEW J06 EXIST J05 EXIST HH2 NEW J04 NEW P03 RELC NE 12TH ST NE 9TH ST EXIST 1-2" NEW 2-4" NEW 2-4" NEW 2-6" EXIST 1-4" NEW 1-3" NEW 1-4 FIBER" NE 8TH ST NEW 1-2" NEW 2-4" NEW 1-4" NEW 1-2" NEW 2-4" NEW 2-4" SPARE 1-4" FB J J09 EXIST EXIST 1-4" IP03 NEW 1-4" V03 EXIST IP04 EXIST 1-4" NEW 1-3" P01 EXIST H J HH1 NEW J01 NEW J J JJ J V02 EXIST J02 EXIST BREAKLINE STA 916+50 J06 EXIST J05 EXIST J04 NEW NE 12TH ST NE 9TH ST 350 TPX NEW 350 TPLX EIJ529-B NE 8TH ST EIJ530-B EIJ535-A EIJ536-B EIJ537-C EIJ534-B EIJ541-A EIJ542-B EIJ543-C EIJ538-A EIJ539-B EIJ540-C EIJ531-A EIJ532-B EIJ533-C J J09 EXIST V03 EXIST J08 NEWEIJ544-A EIJ545-B EIJ546-C EIJ547-A EIJ548-B EIJ549-C 1/Ø AL JKT H J J03 NEW HH2 NEW P03 RELC NEW 1-3" P04 EXIST CONDUIT DIAGRAM 101120019SCALE: NONE UTILITIES CONTACT PHONE# COUNTY 1/4 SEC U-MAP NO (POWER) OP MAP Emer Sect Gas Wk Ctr POWER WK CTR PLAT MAP JOINT FACILITIES ARRANGEMENTS DRAWN BY CHECKED BY APPROVED BY FOREMAN #1 FOREMAN #2 MAPPING INCIDENT MAOP Gas Order Elect Order SCALE PAGE ENGR - POWER ENGR - GAS FUNCTION PROJECT MGR PERMITREAL ESTATE/EASEMENT 2 1 REV# 3 DATE DESCRIPTIONBY CONTACT PHONE NO DATE OH CKT MAP CIRCUIT NOUG CKT MAP HONG NGUYEN 425-449-6609 9/13/19 KEANG LIM 253-395-6916 9/13/19 N/A N/A N/A KEANG LIM 253-395-6916 9/13/19 REQUIRED CITY OF RENTON RENTON DUVALL AVE NE SCH74 OH TO UG CONVERSION 1100 DUVALL AVE NE RENTON, WA 98059 N/A N/A N/A 101120019 AS NOTED 5/6 KING N/A N/A CSPSKEPI S10 T23 R05E N/A N/A 2305E011, 37 2305E040 N/A PRE-14 N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Primary Cable & Conduit Table (Foreman to Complete) LOCATION CONDUIT PRIMARY CABLE QTY OF LUBE (gal.)AS BUILT INFORMATION From To Size (in) Qty Design Length (ft) Actual Length (ft) TYPE BENDS PULL (lbs) PULL Rev (lbs) Cable Size Design Length (ft) Actual Length (ft) CABLE NUMBERS MANUFACTURING INFORMATION FOR FEEDER CABLE ONLY Check applicable box DB120 HDPE SCH 80 90°45°22°11°A B C Manufacturer Compound Year Tape CN #4/0 NEU Design As Built Actual Amount Installed (Conduit & Cable) P01 J01 4 2 180 X 1 2 1/0 AL JKT 185 EIJ529 P01 FB1 4 1 765 J01 V02 2 1 295 X 2 1/0 AL JKT 300 EIJ530 J01 J02 4 2 605 X 2 2 1 1/0 AL JKT 610 EIJ531 EIJ532 EIJ533 P03 J03 2 1 5 X 1 1/0 AL JKT 15 EIJ534 J03 P04 4 1 85 CONDUIT ONLY J03 J04 4 2 170 X 4 1/0 AL JKT 175 EIJ535 EIJ536 EIJ537 J04 J05 4 2 140 X 1 2 1/0 AL JKT 145 EIJ538 EIJ539 EIJ540 J05 J06 4 2 120 X 1 CONDUIT ONLY J05 J06 6 2 120 X 1 CONDUIT ONLY J06 J08 4 1 125 X 1/0 AL JKT 130 EIJ541 EIJ542 EIJ543 J08 J09 4 1 215 X 1/0 AL JKT 130 EIJ544 EIJ545 EIJ546 J08 V03 4 1 105 X 1 1/0 AL JKT 130 EIJ547 EIJ548 EIJ549 Secondary Cable & Conduit Table LOCATION CABLE Assumed Lot Corner CONDUIT VOLTAGE DROP VOLTAGE FLICKER ASBUILT INFORMATION SIZE LENGTH Design (ft) SIZE LENGTH Design (ft) BENDS Foreman - Complete FROM TO (1/0,4/0,350)to Meter(ft)(in)90°45°22°11°(Percent)(Percent)Actual Amount Installed (Conduit & Cable) P01 HH1 1/0 40 3 10 1 1 P03 HH2 350 230 3 200 5 4 P03 P04 1/0 120 3 90 1 2 CABLE ONE-LINE DIAGRAM SCALE: NONE 101120019UTILITIES CONTACT PHONE# COUNTY 1/4 SEC U-MAP NO (POWER) OP MAP Emer Sect Gas Wk Ctr POWER WK CTR PLAT MAP JOINT FACILITIES ARRANGEMENTS DRAWN BY CHECKED BY APPROVED BY FOREMAN #1 FOREMAN #2 MAPPING INCIDENT MAOP Gas Order Elect Order SCALE PAGE ENGR - POWER ENGR - GAS FUNCTION PROJECT MGR PERMITREAL ESTATE/EASEMENT 2 1 REV# 3 DATE DESCRIPTIONBY CONTACT PHONE NO DATE OH CKT MAP CIRCUIT NOUG CKT MAP HONG NGUYEN 425-449-6609 9/13/19 KEANG LIM 253-395-6916 9/13/19 N/A N/A N/A KEANG LIM 253-395-6916 9/13/19 REQUIRED CITY OF RENTON RENTON DUVALL AVE NE SCH74 OH TO UG CONVERSION 1100 DUVALL AVE NE RENTON, WA 98059 N/A N/A N/A 101120019 AS NOTED 6/6 KING N/A N/A CSPSKEPI S10 T23 R05E N/A N/A 2305E011, 37 2305E040 N/A PRE-14 N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 2" to 3" Excavation - 24 cubic yards SIDE VIEW 6'-4" to 6'-5"Crushed 6" Rock TOP VIEW 9' 11' 7'-0" 4'-0" 8" 4'-8" Final Grade (Pavement) 1'-0" Tubes for 1" Adjustable Cover Section 1835 lbs 4760 lbs (2) 3' Square Anti-Skid 5'-8" Adjustable Bolts (4) Doors 2490 lbs Top Handhole NOTE: The Top Cover shall be leveled and adjusted to Final Grade using the Adjustable Bolts. This Installation is for Pavement or Sidewalks only. Adjustable Cover (See NOTE Below) 575 J-BOX & PULL VAULT EXCAVATION DETAIL - J01,J03, J04, J08 SCALE: NONE MID# 9996162 FIBER VAULT DETAIL - FB1 SCALE: NONE CLINK PID# 2378448 COVER WITH ADJUSTABLE FRAME No. 38/25-TA No. 25-T VAULT A A PLAN VIEW SECTION AA END VIEW SINGLE PHASE SECONDARY CONCRETE HANDHOLE - HH1,HH2 Not to scale 6050.2020-1 TOP VIEW SIDE VIEW 2'-4" EXCAVATION: 5-1/3 CUBIC YARDS 7'-0" 6'-0" 6" Crushed rock 2" 2'-6" Install PVC bell ends and grout into wall 2'-6" Handhole 820 lbs Conduits and conductors shall enter from ends of handhole through knockouts provided Typical customer run service conductors in duct Steel Door Seal conduit with foam Customer-installed grounding wires ( the "4th" wire on the single-phase systems and the "5th" wire on the three-phase systems) shall no t be connected to PSE's ground or neutral bus. They shall be removed by customer or cut off at the vault wall. Excavated Dirt Pile Final Grade 24" Min Backfill for Schedule 40 Conduit (NO Rocks over 10" Diameter or foreign objects)Separation 12" Min 18" Min TYP TRENCH DETAIL Primary-Schedule 80 (NTS) 48" Max 36" Min Cover Phone & TV Primary Power Cable in Customer Provided Schedule 40 Conduit ROADSIDE To Excavated Dirt Pile