HomeMy WebLinkAboutMFP21003966.pdfDEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Major Franchise Permit: MFP21003966
IVR Number: 21003966
Permit Information
Permit Name: Puget Sound Energy - Electric
Address/Location:08/17/2021Application Date:0423059142Parcel Number: 2611 UNION AVE NE
Permit Type:09/29/2021Issue Date:Franchise
Permit Work Class:09/29/2022Expiration Date:Major Utility
Job Number: 101140385Franchise Type:Electric
Description: Puget Sound Energy Electric RUCK TO BE SET AT P01, P1A, P02, P2A, J01, V01, P05, V02, P4A AND P04. SOUTH
BOUND LANE OF UNION AVE TO BE CLOSED TO WIRE REMOVAL X PULL, EAST BOUND LANE OF NE 27TH PL TO
BE CLOSED FOR RE PULL TO V02. POTHOLE ALL EXISTING UTILITIES. RESTORATION PER CITY OF RENTON
STANDARDS.
Contacts
Name Address PhoneTypeBilling
Corrie Rydberg
Puget Sound Energy
6905 S 228TH St
KENT, WA 98032
C: (253) 905-5031ApplicantX
Vicki Henson
Potelco Inc
8001 212th St S
Kent, WA 98032
B: (253) 863-0484Contractor
Business License Number: 5109Electrical Contractor: POTELI*344O4
Construction Contractor: POTELI*227PL
PULTE HOME OF WASHINGTON IN 3535 FACTORIA BLVD SE STE 110
BELLEVUE , WA 98006
Owner
Corrie Rydberg
Puget Sound Energy
6905 S 228TH St
KENT, WA 98032
C: (253) 905-5031Specialized
Billing
General Conditions & Signature
Permission is hereby given for the work described on this permit according to the conditions hereon and according to the
approved plans and specifications pertaining thereto, subject to compliance with the Ordinance of the City of Renton.
Ÿ
This permit and plans must be posted at the job site at all times.Ÿ
I hereby certify that no work is to be done except as described above and in approved plans, and that work is to conform to
Renton Trench Restoration and Street Overlay Requirements.
Ÿ
Call 425.430.7203 or go to: https://permitting.rentonwa.gov one working day in advance to schedule an inspections and for ANY
work in the Right of Way.
Ÿ
Call 8 1 1 to locate underground utilities at least two full business days prior to any excavation.Ÿ
In accordance with RCW 19.122.033(4) the permit holder is required to contact (Williams Northwest Pipeline at 425.868.1010)
(Olympic Pipeline at 206.510.0575) (Puget Sound Energy at 425.375.3397) to request a consultation with the transmission
pipeline company prior to performing any construction or excavation activities. This requirement to consult with the
transmission pipeline company is in addition to the requirement to Call before You Dig as required in RCW 19.122.
Ÿ
(Date)(Signature)
Page 1 of 1THIS PERMIT AND PLANS MUST BE POSTED AT THE JOB SITE AT ALL TIMES
DEPARTMENT OF PUBLIC WORKS
Note: The Applicant is responsible for compliance with all codes and regulations, whether or not described in this document.
Page 1 of 2 | Published: 1ϭ/Ϯϱ/2019
Transportation Division | 1055 South Grady Way, 5th Floor | Renton, WA 98057 | 425-430-7380
Website: rentonwa.gov
TRAFFIC CONTROL PLAN (TCP) APPLICATION
Published: 1ϭ/Ϯϱ/2019
TRAFFIC CONTROL PLAN (TCP) MUST BE SUBMITTED TO PUBLIC WORKS TRANSPORTATION DIVISION
FOR REVIEW/APPROVAL NO LATER THAN FIVE (5) WORKING DAYS BEFORE THE DATE OF WORK.
The City of Renton requires any contractor, firm, corporation, or other public/private agency to prepare a TCP and
obtain City of Renton's approval of that plan when construction, repair, or maintenance work is to be conducted
within the city's right-of-way.
TO THE APPLICANT: Submit the TCP application form and required submittal documents to
TCP@rentonwa.gov with the subject line “TCP Application – [Project Name]” or the above address.
The following items, electronic copies preferred, are all required for submittal of the TCP Application:
1.܆ A copy of the Traffic Control Plan (TCP) Application form.
2.܆ A copy of the required TCP layout, preferred 11” X 17” paper size format, which shall:
܆ Include map(s) showing the location of the project and work area.
܆ Be legible lettering and clear, contrasting, symbols of viewing or printing.
܆ Must indicate street names, and north arrow and scale.
܆ All signs and detour routes shall conform to the MUTCD, WSDOT TCPs, and the Washington State
Traffic Control Flagger Certification handbook, by the Evergreen Safety Council.
܆ Types of plans required:
܆ Work hour plan – show all mobility impacts during construction hours.
܆ Non-work plan - show all mobility impacts after work hours when limited or no work is
happening in the right-of-way (ROW), if applicable.
܆ Changing construction phases – show construction sequence and each construction phase
change even if the traffic control is not modified, if applicable.
܆ Pedestrian access/detour plan, if applicable.
Project Name: ______________________________________________ Permit #: _____________________
Project Address: ____________________________________________________________________________
Work Date: From _____________ To _____________ Work Time: Start ______________ End ______________
Description of Work, Work Schedule, Equipment Used: _____________________________________________
___________________________________________________________________________________________
___________________________________________________________________________________________
Construction Company: ________________________________________ Phone/Cell: (_____) _____-________
Applicant Name: _________________________________ Email: ______________________________________
Business Address: _________________________________ City/State: __________________ Zip: __________
Approved By: _______________________________________________ Date: ________________________
Transportation Operations Engineering
4
4
4
4
4
4
4
4
4
4
4
101140385
2611 Union Ave NE
Monday Friday 8:00am 3:00pm
PLEASE SEE ATTACHED
POTELCO, INC 425 892 0416
Lee Brown Lee.Brown@PSE.com
6905 S. 228TH ST KENT, WA 98032
MFP21003966
Scott Warlick CED 9/29/2021
Note: The Applicant is responsible for compliance with all codes and regulations, whether or not described in this document.
Page 2 of 2 | Published: 1ϭ/Ϯϱ/2019
APPLICANT AGREES TO ALL THE FOLLOWING:
x TCP must be approved prior to commencing the work, and all permit conditions shall be met.
x Existing pedestrian access shall be maintained. The work on pedestrian facilities shall be limited to one corner
at a time, with the least possible inconvenience or delay to pedestrians.
x Signage shall be used to warn motorcyclists/bicyclists of the potential hazards on any uneven surfaced or
slippery road conditions during work and non-work hours.
x The start of Work Time begins when any street or travel lane is fully/partially closed or impacts the follow of
traffic. This includes set up within the traveled way or immediately adjacent to the roadway.
x Emergency services (253-852-2121) shall be notified twenty-four (24) hours before any street or lane closures.
x Contractor or entity must call Renton School District (425-204-4455) or any public/private agency, including
public transit, to be affected by a temporary lane or road closure.
x TCP for all street and/or lane closures shall be implemented and performed in compliance with the Manual on
Uniform Traffic Control Devices (MUTCD) and/or State of Washington Department of Transportation (WSDOT)
and all traffic regulations of the City of Renton and Revised Code of Washington (RCW).
x Any lane or street closures not in conformance with the approved traffic control plan and/or without
notification of emergency services may result in receiving a citation for violation of RCW 47.36.200 Signs or
Flaggers at thoroughfare work sites and RCW 9A.36.050 Reckless Endangerment, and other applicable State
and City codes.
x Indemnify and hold harmless the City of Renton from any and all claims, actions, and judgments, including all
costs of defense and attorney’s fees incurred in defending against same, arising from and related to
implementation of the approved traffic control plans including claims arising from towing of private vehicles
and the acts of the Applicant’s agents and employees.
x The City of Renton shall be entitled, in its reasonable discretion, to settle claims prior to suit or judgment, and
in such event shall indemnify and hold harmless the City for any such claims paid, including the City’s
reasonable attorney’s fees and litigation costs incurred resulting from such claim.
x In the event any claim or suit is brought against the City within the scope of this Agreement, Applicant will pay
for legal counsel chosen by the City to defend against same.
x Flagger and sign placement are subject to revision by the City Inspector on site, if needed to address traffic or
pedestrian safety or travel.
x Total road closure lasting more than twenty-four (24) hours is subject to the approval by the City Council.
x Approved Temporary TCP must be at the work site during work hours.
x Complete assistance and accommodation shall be provided to all kinds of pedestrian traffic when sidewalk or
walkway is impeded to safely redirect pedestrians around a work zone.
x Any vehicle, equipment, barricade, or portable tow-away sign used within the work area must display a
company logo or any legally acceptable sign showing the company name, address, and telephone number at a
conspicuous place on the vehicle or equipment.
In the case of Temporary No Parking Zones, all the following apply in addition to previous:
x Contractor must complete form to show limits of Temporary No Parking Zone identifying barricade locations
for vacate parking or curb lane usage.
x Contractor must post notice of dates and time of Temporary No Parking Zone with at least two signs per block
seventy-two (72) hours in advance of effective date and time.
x The cover sheet of this TCP form must be attached to each Temporary No Parking Sign on the project site.
x Temporary traffic control devices must be removed immediately when work is done or no construction
activities are going on. If deemed abandoned, City crews will remove and store them at the City’s maintenance
shop (3555 NE 2nd Street; 425-430-7423).
_______________________________ _______________________________ _______________________
Applicant’s Signature Print Name Date
CORRIE RYDBERG
P01
P1A
P02
P2A
RIGHTKEEPR4-7BRIGHT
KEEP
R4-7BW1-4LROADWORKAHEADW20-1200'200'200'CENTER LANE
CLOSED
AHEAD W9-3ROAD
WORK
AHEAD W20-1200'200'CENTER LANECLOSEDAHEADW9-311 11
18 14 12 1616NE 25TH PL
UNION AVE NERESIDENT(S) WILL BE INFORMED
OF POSSIBLE TEMPORARY
DRIVEWAY CLOSURE
PLACE SIGNS
BOTH SIDES OF
WORK AREA
FROMTOTOW AWAY AREAPHONE 888-9999INFRASOURCE LLC
000
0000000 NO PARKINGNO-PAR
K FROMTOTOW AWAY AREAPHONE 888-9999INFRASOURCE LLC 000 0000000NO PARKINGNO-PAR
K
LEGEND
28" TRAFFIC CONE
SIGN LOCATION
TRAFFIC FLOW
POLE
WORK VEHICLE/
FLASHING LIGHTS
RIGHT OF WAY
SIGN SPACING
MPH
60/65
45/55
35/40
30
25
"X"
1000'
500'
350'
200'
100'
CHANNELIZATION
DEVICE SPACING
MPH
55/70
35/45
25/30
TAPER
40
30
20
TANGENT
80
60
40
TEMPORARY TRAFFIC CONTROL PLAN
N
Notes:
1. All signs and spacing to conform to the
MUTCD and City of Renton standards.
2. All sidewalks, driveways, exits and egresses
shall be completely clear unless otherwise indicated.
3. Channelizing devices are 28" traffic cones.
Use traffic drums (barrels) with steady burning
Type C lights on all State State Routes and Hwys.
4. Sign size can be a minimum of 36" x 36" and
shall not obstruct pedestrian access.
5. Crew is required to leave a minimum of 11' for
traveling lane width.
6. Alert affected residents and businesses.
7. Work to take place between 9 a.m. and 4 p.m
unless otherwise specified. All work for arterials
and major roadways will be from 9 a.m. to 3 p.m.
Project Address:
Page
PSE PUGETSOUNDENERGY
Designer:
Job #
REV
08/04/2021
101140385
0
2611 Union Ave NE, Renton, WA
Kali-Jamal Collins
425-424-6425
Kali-Jamal.Collins@pse.com
1 OF 5
Puget Sound Energy
Traffic Control Supervisor:
Gregory Harwood
Card No. 012238
Card Exp. 09/30/2023
gregory.harwood@pse.com
(425)424-6425
MFP21003966
P03
J01
V01
W20-7AROAD
WORK
AHEAD W20-1W20-4ONE LANEROADAHEAD200'200'200'W20-7AROADWORKAHEADW20-1W20-4ONE LANEROADAHEAD200'200'200'ROADWORKAHEADW20-1161610 10
10 13 UNION AVE NENE 27TH PL
STOP
FLAGGER
STOP
FLAGGER
RESIDENT(S) WILL BE INFORMED
OF POSSIBLE TEMPORARY
DRIVEWAY CLOSURE
PLACE SIGNS
BOTH SIDES OF
WORK AREA
FROMTOTOW AWAY AREAPHONE 888-9999INFRASOURCE LLC
000
000
0000 NO PARKINGNO-PA
RK FROMTOTOW AWAY AREAPHONE 888-9999INFRASOURCE LLC 000 0000000NO PARKINGNO-PARK
TEMPORARY TRAFFIC CONTROL PLAN
N
Notes:
1. All signs and spacing to conform to the
MUTCD and City of Renton standards.
2. All sidewalks, driveways, exits and egresses
shall be completely clear unless otherwise indicated.
3. Channelizing devices are 28" traffic cones.
Use traffic drums (barrels) with steady burning
Type C lights on all State State Routes and Hwys.
4. Sign size can be a minimum of 36" x 36" and
shall not obstruct pedestrian access.
5. Crew is required to leave a minimum of 11' for
traveling lane width.
6. Alert affected residents and businesses.
7. Work to take place between 9 a.m. and 4 p.m
unless otherwise specified. All work for arterials
and major roadways will be from 9 a.m. to 3 p.m.
28" TRAFFIC CONE
LEGEND
TRAFFIC FLOW
SIGN LOCATION
FLAGGER
STOP
VAULTVault
WORK VEHICLE/
FLASHING LIGHTS
RIGHT OF WAY
SIGN SPACING
MPH
60/65
45/55
35/40
30
25
"X"
1000'
500'
350'
200'
100'
CHANNELIZATION
DEVICE SPACING
MPH
55/70
35/45
25/30
TAPER
40
30
20
TANGENT
80
60
40
Project Address:
Page
PSE PUGETSOUNDENERGY
Designer:
Job #
REV
08/04/2021
101140385
0
2611 Union Ave NE, Renton, WA
Kali-Jamal Collins
425-424-6425
Kali-Jamal.Collins@pse.com
2 OF 5
Puget Sound Energy
Traffic Control Supervisor:
Gregory Harwood
Card No. 012238
Card Exp. 09/30/2023
gregory.harwood@pse.com
(425)424-6425
MFP21003966
P05
W20-7AROAD
WORK
AHEAD W20-1W20-4ONE LANEROADAHEAD200'200'200'W20-7AROADWORKAHEADW20-1W20-4ONE LANEROADAHEAD200'200'200'ROADWORKAHEADW20-1161610 10
10 13 UNION AVE NENE 27TH PL
STOP
FLAGGER
STOP
FLAGGER
RESIDENT(S) WILL BE INFORMED
OF POSSIBLE TEMPORARY
DRIVEWAY CLOSURE
PLACE SIGNS
BOTH SIDES OF
WORK AREA
FROMTOTOW AWAY AREAPHONE 888-9999INFRASOURCE LLC
000
000
0000 NO PARKINGNO-PA
RK FROMTOTOW AWAY AREAPHONE 888-9999INFRASOURCE LLC 000 0000000NO PARKINGNO-PARK
TEMPORARY TRAFFIC CONTROL PLAN
N
Notes:
1. All signs and spacing to conform to the
MUTCD and City of Renton standards.
2. All sidewalks, driveways, exits and egresses
shall be completely clear unless otherwise indicated.
3. Channelizing devices are 28" traffic cones.
Use traffic drums (barrels) with steady burning
Type C lights on all State State Routes and Hwys.
4. Sign size can be a minimum of 36" x 36" and
shall not obstruct pedestrian access.
5. Crew is required to leave a minimum of 11' for
traveling lane width.
6. Alert affected residents and businesses.
7. Work to take place between 9 a.m. and 4 p.m
unless otherwise specified. All work for arterials
and major roadways will be from 9 a.m. to 3 p.m.
28" TRAFFIC CONE
LEGEND
TRAFFIC FLOW
SIGN LOCATION
FLAGGER
STOP
POLE
WORK VEHICLE/
FLASHING LIGHTS
RIGHT OF WAY
SIGN SPACING
MPH
60/65
45/55
35/40
30
25
"X"
1000'
500'
350'
200'
100'
CHANNELIZATION
DEVICE SPACING
MPH
55/70
35/45
25/30
TAPER
40
30
20
TANGENT
80
60
40
Project Address:
Page
PSE PUGETSOUNDENERGY
Designer:
Job #
REV
08/04/2021
101140385
0
2611 Union Ave NE, Renton, WA
Kali-Jamal Collins
425-424-6425
Kali-Jamal.Collins@pse.com
3 OF 5
Puget Sound Energy
Traffic Control Supervisor:
Gregory Harwood
Card No. 012238
Card Exp. 09/30/2023
gregory.harwood@pse.com
(425)424-6425
MFP21003966
NE 27TH PLV021010101016 16
UNION AVE NE
S/WCLOSEDR9-9S/W
CLOSEDR9-9W20-7AROAD
WORK
AHEAD W20-1W20-4ONE LANE
ROADAHEAD100'100'100'W20-7AROADWORKAHEADW20-1 BEPREPAREDTOSTOPW3-4 200'200'200'W20-7AROADWORKAHEADW20-1BEPREPAREDTOSTOPW3-4200'200'200'STOPFLAGGER STOPFLAGGER
STOP
FLAGGERRESIDENT(S) WILL BE INFORMEDOF POSSIBLE TEMPORARYDRIVEWAY CLOSUREPLACE SIGNSBOTH SIDES OFWORK AREAFROMTOTOW AWAY AREAPHONE 888-9999INFRASOURCE LLC 000 0000000NO PARKINGNO-PARK
FROM TO
TOW AWAY AREA
PHONE 888-9999
INFRASOURCE LLC 000 0000000
NO PARKING
NO-PARK
THE CREW SHALL CEASEWORK FOR A FLAGGER/SPOTTERTO ESCORT PEDESTRIANSAROUND THE WORK AREATEMPORARY TRAFFIC CONTROL PLAN28" TRAFFIC CONELEGENDTRAFFIC FLOWSIGN LOCATIONFLAGGERSTOPVAULTVaultWORK VEHICLE/FLASHING LIGHTSRIGHT OF WAYSIGN SPACINGMPH60/6545/5535/403025"X"1000'500'350'200'100'CHANNELIZATIONDEVICE SPACINGMPH55/7035/4525/30TAPER403020TANGENT806040Notes:1. All signs and spacing to conform to theMUTCD and City of Renton standards.2. All sidewalks, driveways, exits and egressesshall be completely clear unless otherwise indicated.3. Channelizing devices are 28" traffic cones.Use traffic drums (barrels) with steady burningType C lights on all State State Routes and Hwys.4. Sign size can be a minimum of 36" x 36" andshall not obstruct pedestrian access.5. Crew is required to leave a minimum of 11' fortraveling lane width.6. Alert affected residents and businesses.7. Work to take place between 9 a.m. and 4 p.munless otherwise specified. All work for arterialsand major roadways will be from 9 a.m. to 3 p.mNProject Address:PagePSEPUGETSOUNDENERGYDesigner:Job #REV08/04/2021 10114038502611 Union Ave NE, Renton, WAKali-Jamal Collins425-424-6425Kali-Jamal.Collins@pse.com4 OF 5Puget Sound EnergyTraffic Control Supervisor:Gregory HarwoodCard No. 012238Card Exp. 09/30/2023gregory.harwood@pse.com(425)424-6425MFP21003966
P4A
P04
ROADWORKAHEADW20-11616NE 27TH PL
STOP
FLAGGER
STOP
FLAGGER
W20-7AROAD
WORK
AHEAD W20-1W20-4ONE LANE
ROADAHEAD200'200'200'W20-7AROADWORKAHEADW20-1W20-4ONE LANEROADAHEAD200'200'200'10 10
UNION AVE NE10 10
RESIDENT(S) WILL BE INFORMED
OF POSSIBLE TEMPORARY
DRIVEWAY CLOSURE
PLACE SIGNS
BOTH SIDES OF
WORK AREA
FROMTOTOW AWAY AREAPHONE 888-9999
INFRASOURCE LLC
000
00000
00 NO PARKINGNO-PARK FROMTOTOW AWAY AREAPHONE 888-9999INFRASOURCE LLC 000 0000000NO PARKINGNO-PARKTEMPORARY TRAFFIC CONTROL PLAN
N
Notes:
1. All signs and spacing to conform to the
MUTCD and City of Renton standards.
2. All sidewalks, driveways, exits and egresses
shall be completely clear unless otherwise indicated.
3. Channelizing devices are 28" traffic cones.
Use traffic drums (barrels) with steady burning
Type C lights on all State State Routes and Hwys.
4. Sign size can be a minimum of 36" x 36" and
shall not obstruct pedestrian access.
5. Crew is required to leave a minimum of 11' for
traveling lane width.
6. Alert affected residents and businesses.
7. Work to take place between 9 a.m. and 4 p.m
unless otherwise specified. All work for arterials
and major roadways will be from 9 a.m. to 3 p.m.
28" TRAFFIC CONE
LEGEND
TRAFFIC FLOW
SIGN LOCATION
FLAGGER
STOP
POLE
WORK VEHICLE/
FLASHING LIGHTS
RIGHT OF WAY
SIGN SPACING
MPH
60/65
45/55
35/40
30
25
"X"
1000'
500'
350'
200'
100'
CHANNELIZATION
DEVICE SPACING
MPH
55/70
35/45
25/30
TAPER
40
30
20
TANGENT
80
60
40
Project Address:
Page
PSE PUGETSOUNDENERGY
Designer:
Job #
REV
08/04/2021
101140385
0
2611 Union Ave NE, Renton, WA
Kali-Jamal Collins
425-424-6425
Kali-Jamal.Collins@pse.com
5 OF 5
Puget Sound Energy
Traffic Control Supervisor:
Gregory Harwood
Card No. 012238
Card Exp. 09/30/2023
gregory.harwood@pse.com
(425)424-6425
MFP21003966
42°'
N
Vicinity Map
47.5163, -122.1646
Owner / Developer Contact Info
officeATTN:
PULTE HOMES OF WASHINGTON, INC
3535 FACTORIA BLVD SE, STE 600
BELLEVUE, WA 98006
Lance Adams 206.406.6059
THIS SKETCH NOT TO BE RELIED UPON FOR EXACT LOCATION OF EXISTING FACILITIES
CALL (800) 424-5555
2 BUSINESS DAYS BEFORE YOU DIG
For contacts below dial 1-888-CALL PSE (225-5773)
PSE
No
No
No
Yes
Yes
Yes
No
YesDeveloper
"Flagging Required"
"Outages Required"
"Locates Required"
FOREMAN (CHECK BOX WHEN COMPLETED)
PSE Equipment LOCKED/SECURED & Work Area left in CLEAN/SAFE Condition.
Grid, Cable, and Switch numbers INSTALLED & VERIFIED.
Field Changes RED-LINED on As-built.
Indicate correct FUSE SIZE on As-built & VERIFY proper PHASE.
Foreman's Signature _______________________________________________
Print Name ___________________________________ Date ______________
Material VERIFIED and CHANGES noted on Paperwork.
Total PRIMARY Cable noted on As-built.
Company ID#'s RECORDED in correct location on As-built.
Deviations noted on the As-built and their reason.
I certify that the work performed meets PSE's standards and procedures
and that all quality requirements are met.
PHONE
CABLE TV
511440209 101140385
N/A 101135322
N/A 108125639
N/A 583065874
N/A 593229143
N/A N/A
N/A N/A
N/A N/A
N/A N/A
PROJECT PHASE
PWR
NOTIF#ORDER#
Superior
Relocate
Removal
OH XFMR
OH Wire
UG Svc 13611 #Shop
OH Light 13633
N/A
N/A 101140385.DESIGNED BY
UTILITIES
CONTACT
PHONE#
COUNTY
1/4 SEC
U-MAP NO (POWER)
OP MAP
Emer Sect Gas Wk Ctr POWER WK CTR
PLAT MAP
JOINT FACILITIES ARRANGEMENTS
DRAWN BY
CHECKED BY
APPROVED BY
FOREMAN #1
FOREMAN #2
MAPPING
INCIDENT MAOP
Gas Order Elect Order
SCALE PAGE
ENGR - POWER
ENGR - GAS
FUNCTION
PROJECT MGR
PERMITREAL ESTATE/EASEMENT
2
1
REV#
3
DATE DESCRIPTIONBY
CONTACT PHONE NO DATE
OH CKT MAP CIRCUIT NOUG CKT MAP
LEE BROWN 425.417.8620 4.01.21
A. DUNN 206.437.9150 7.21.21
...
J.COSSETTE 206.584.4408 6.13.21
REDT # ( RW-112327 )RENTON/ KING COUNTY
FOREST TERRACE SCH 73
SCHEDULE 73 OH-UG CONVERSION - 2 SPANS
2611 UNION AVE NE, RENTON, WA 98059
PUGET SOUND ENERGY
..
.101140385
AS SHOWN 1 OF 5
KING N/A N/A QCSOKE
NE 4-T23N-R05E N/A N/A
2305E013 2305E040 2305E013 PRE-14
COMCAST
JAMES COHN
253.569.0636
CENTURYLINK
KENNETH LUU
206.346.0144
RENTON SCHOOL DIST.
JAY GRAY
253.226.8314
PSE RIGHT OF WAY
AMBER YANG
425.456.2774
E-Mail:
Cell Phone:
Project Manager Contact Information:
Manager:LEE BROWN
425.417.8620
lee.brown@pse.com
x x
...
...
...
xx
lance.adams@pultegroup.com
SITE
FOREST TERRACE
SCHEDULE 73
OH TO UG CONVERSION
& ANY ADDITIONAL LOCAL JURISDICITON REQUIREMENTS.
EROSION & SEDIMENT CONTROL SHALL BE PER PSE STANDARD PRACTICE
0150.3200 TECHNIQUES FOR TEMPORARY EROSION & SEDIMENT CONTROL
(LOCAL JURISDICTIONS MAY HAVE ADDITIONAL REQUIREMENTS INCLUDING
NOTES DETAILING WHERE EROSION OR SEDIMENT CONTROL STRUCTURES
EROSION & SEDIMENT CONTROL REQUIREMENTS
STRUCTURES, & SPECIAL REQUIREMENTS FOR WORK IN SENSITIVE AREAS.)
ARE TO BE INSTALLED, CROSS SECTION DETAILS OF THE TYPICAL EROSION
GENERAL 1.
Pre-construction Notify appropriate City or County 48 to 72 hours or as required by
permitting agency before starting work on any right-of-way involving a permit.
Follow all requirements as outlined by the permitting agency.
Locate and mark all underground utilities prior to start of construction. If there is a
conflict with the intended trench route as shown on the site plan and existing utilities or
obstructions, trench route may need to be moved to opposite side of street.
Cooperation with Quality Inspector, Puget Sound Energy Contractor, City or County
authorities during Pre-construction meeting will determine the final trench route.
2. Existing Utilities
Hand excavate (pothole) all marked utility crossings to verify exact location and depth
at point of crossing. Protect underground utilities during excavation. Use hand
excavation methods if necessary to avoid damage. Fabricate and install adequate
temporary structures to support and protect underground utilities while exposed during
construction.
Maintain 6" minimum clearance at crossings between existing utilities and new duct
installations. Transition trench or tunnel profile gradually as required at crossings.
Maintain 24" minimum separation between new trench or tunnel and parallel existing
utilities or as required by the permit agency.
In the event of damage to an underground utility, notify Puget Sound Energy at once.
Contractor agrees to make work force and resources available at once to Puget Sound
Energy or municipal authorities to repair damage at no cost.
3. Work Drawings
Maintain on site, in good condition, a complete file of all work drawings. These
drawings shall be available at all times to a Puget Sound Energy representative.
Corrections and changes made during the job shall be recorded continuously on these
drawings. All underground electrical facilities shall have a minimum of 36 inches of
cover. Any change must be approved by the PSE engineer or project manager.
Furnish Puget Sound Energy a complete set of as built prints (foreman's copies) at the
end of the job.
4. Safety
Provide signs, barricades, and traffic control in conformance with local jurisdictions and
regulations. Provide flagging and or other vehicle traffic control as needed in
conformance with local regulations. (see SPM # 100.4000) Provide adequate signage
and protection to traffic during non-working hours. Maintain traffic flow as required by
permitting agency. Provide signs and barricades to warn pedestrians, motorcycles and
bicycles.
Install warning barricades at least every 50 feet along the trench route from the time the
trench is opened until the trenching is complete.
5. Existing Systems
Maintain existing electrical system in service until new system is complete, tested, and
ready for service. Disable existing system only to make cutovers and connections as
directed by Puget Sound Energy's representative.
Provide temporary wiring and connections to maintain existing systems in service during
construction; if a scheduled outage is not possible. When work must be performed on
energized equipment or circuits, use qualified personnel for such operations.
EARTHWORK
See Puget Sound Energy SPM 6800.4050
1. Back hoe, Hand Dug Excavations
Paved Surfaces
Cut the edges of the trench prior to digging. Use the narrowest bucket practical or plow
off the edge of paved surface far enough to minimize asphalt disturbance. Repair any
blow out areas (where edge has been broken) by sawing. The depth of the trench shall
be enough to allow 36" of cover . Backfill material shall be Controlled Density Fill (CDF)
cover or select fill (5/8" minus) to meet permit requirements.
Unpaved Surfaces
Conduit/cable trenches are to be excavated just off the existing road edge or in the
shoulder of the road behind the existing ditch line. Contractor shall use a back hoe with
the narrowest width bucket practical or plow. Trench shall be deep enough to allow a
minimum of 36" of cover over the top most cable. All ditch crossings shall have a
minimum of 36" cover from the lowest point within the existing ditch line.
Culverts; when installing facilities under a culvert, excavation must be filled with packed
crush rock. If any culvert is damaged it will be repaired or replaced in accordance with
permitting agency and contractors responsibility.
Spoils shall be removed quickly to minimize blocking of traffic. All spoils and wastes
become the property of the contractor immediately upon removal. Remove spoils and
wastes promptly to an approved disposal site. Remove spoils containing asphalt or
concrete to a disposal site specifically approved for such materials. Provide Puget
Sound Energy with a disposal receipt for all spoils.
2. Backfill
Unpaved Road Surfaces
Backfill for unpaved road crossings shall consist of 1-1/2" to 2-1/2" material compacted
to 95% density. Backfill for unpaved road sections shall consist of native material
compacted to 95% density.
At the end of each workday, backfill or plate all trench, remove all spoils and clean
roadway surface of large hazardous debris.
3. Surface Restoration
Unpaved Surfaces
Restore ground surface to original contour. Restore to original condition or better.
4. Landscaping
Arrange and perform work to minimize impact to existing landscaping. Restore
landscaping that has been disturbed during the course of work, including seeding of
banks and fills. Vaults set in bank areas may require re-sloping the surrounding land to
avoid sloughing. Leave area in its original state or better at the end of construction.
Hand dig if required to prevent damage to tree roots.
ELECTRICAL
1. Conduit
Conduit for installation in unpaved areas shall be 2", 3", 4", or 6" PVC DB120 direct burial.
Maintain 36" minimum cover above top conduit at all times or as required by the permitting
agency.
Where conduit is routed from road edge to vault location, maintain 36" minimum cover above top
conduit at all times or as required by the permitting agency. Bends shall be made with as long a
radius as possible (48" minimum). Avoid making sharp bends or kinks in conduit during
installation. Obtain exact location of conduit entrance into vault from Puget Sound Energy before
penetrating vault. Penetrate the vault using existing knockout or use core drilled holes. Stub the
4" or 6" PVC 2"-3" into vault interior and grout between the conduit and vault wall. Leave a 10'
minimum of extra pull rope in each end of installed conduit where 4" or 6" PVC is installed and
cap conduit to prevent the entry of dirt and moisture.
Arrange work so conduit plays directly off reel into trench. Place the conduit in the trench as
straight as possible. Avoid vertical and horizontal "snaking" of the conduit. Multiple conduit runs
may be stacked vertically. Where conduit must be pulled through a trench to allow a crossing
under an existing utility, cap conduit end before pulling to avoid contamination. If a kink occurs,
cut the conduit ahead of kink and splice to new conduit to continue run.
2. Underground Primary Cable
Primary cable shall be 1/O Alum Sol Jacketed Cable rated for 15 KV service with a polyethylene
jacket. Primary cable shall be 61 strand 750 MCM aluminum conductor rated for 15 KV service
with a copper tape neutral conductor and polyethylene jacket. A 4/0 copper neutral shall be run
with each 3 phase circuit of 750 MCM.
Install cable into existing or new conduit systems using approved installation equipment.
Approved equipment includes either cable pullers and/or cable pushers. Pulling socks shall be
non-conductive or similar material. Steel pulling socks are prohibited. Bare steel cable shall not
be used to pull cable. Cable pulling equipment (winches, hoist, driven reels, etc.) shall be
equipped with instrumentation to continually monitor and record peak tension encountered during
a pull. Before installing cable, obtain rated pulling tension for cable from Puget Sound Energy.
Do not exceed rating at any time during installation. Notify Puget Sound Energy immediately if
pulling tension equals or exceeds rating (828/1657lbs for 1/0 or 5000lbs for 750 .) Do not exceed
minimum bend radius of cable or impose kinks or sharp bends on cable during pulling operations.
Install cable directly off reel without dragging it on the ground. Apply Puget Sound Energy
approved lubricant to cable continually during pulling to reduce pulling tension and to permit future
removal.
Install adequate amounts of 3/4 " plywood on existing sidewalk areas to support pulling equipment
and prevent un-necessary damage to sidewalks.
Train and coil cables in vaults as required to form a smooth transition from conduit to termination.
if terminations are to be performed by others, coil 15' of cable in vault and cap end.
3. Terminations and Splices
Install approved terminations on cables in accordance with Puget Sound Energy SPM 2247.5115-
5119. Unless otherwise directed, approved terminations will be load break elbows in vaults and
cold shrink pin terminals on pole risers per Puget Sound Energy SPM 2247.9317.
Splice cable with approved splice kits in vaults, hand holes or similar enclosures. Do not splice
cables in runs between vaults. See Puget Sound Energy SPM 2233.2075-2076.
4. Concrete Vaults
Excavate, install base material, and compact base material in accordance with Puget Sound
Energy SPM 6775.0040.
Install and seal precast sections in accordance with Puget Sound Energy SPM 6775.0040. Use
precast neck and shaft sections to bring manhole entrance to proper elevation. Install manholes
plumb. Set the top of each manhole to finished elevation or no higher than 6" above existing road
elevation. Install hillholders as required on sketch or by construction notes.
5. Grounding
Install ground rod per Puget Sound Energy SPM 6275.6100 at each vault in which primary cable
is terminated. Locate rod in trench excavation wherever possible to obtain maximum driven depth
in undisturbed soil. Connect each ground individually to ground loop inside vault with bare no. 2
copper jumper or to Concentric neutral at each splice vault location. Minimum grounding
requirement is 4 grounds per mile.
6. Existing Underground Primary Cable (if applicable)
Abandon existing primary cable in place. Cut off old cable ends inside vault flush with wall.
Before cutting, pigtail concentric neutral strands and connect to ground loop inside vault. Return
scrap cable and existing cable tags to Puget Sound Energy. Remove or fill existing vaults as
required by permitting agency.
7. Traffic Control
All traffic control to comply with current specifications in M.U.T.C.D.
GENERAL OVERHEAD NOTES:
1. Poles, conductors, devices to be installed per PSE Standards & Specifications.
2. Poles are to be installed or relocated as staked.
3. All new poles set shall be the class indicated on the sketch or better.
4. Install ground plate assembly on all new poles.
5. Install grid numbers on all new and existing poles as shown on sketch.
6. Treat all field-drilled poles with copper Naphthenate wood preservative.
7. Customer/Developer to coordinate between utilities.
8. All new and relocated poles -locations- to be approved by King Co.
OVERHEAD CIRCUIT MAP - EXISTING (2305E040)
SCALE: 6" = 1 MILE
EXISTING PROPERTY LINE
EXISTING UG RISER
NEW UG RISER
J-BOX
NEW TRENCH LINE
EXISTING 3Ø WIRE
EXISTING CENTER LINE
CONDUCTOR TO BE REMOVED
DISCONNECT - FUSED
EXISTING 1Ø WIRE
EXISTING RIGHT OF WAY
PULL VAULT
EXISTING POLE
DOWN GUY
EXISTING SECONDARY SERVICE LINE
DISCONNECT - UNFUSED
STREETLIGHT
NEW POLE
NEW PADMOUNT TRANSFORMER
EXISTING PADMOUNT TRANSFORMER
NEW HANDHOLE
P
ELECTRIC SYMBOLS LEGEND
SITE
NOTE:
DEVELOPER TO PROVIDE ALL CIVIL WORK: TO AND INCLUDING
EXCAVATION, BACKFILL, SHORING, TRENCH MAINTENANCE,
SANDING FOR DUCT, SELECT 5/8" CRUSH FOR UNDER VAULTS,
COMPACTION, ALL HARDSURACE RESTORATION AND RELATED
LANDSCAPING RESTORATION. DEVELOPER TO PROVIDE
TEMPORARY EXCAVATION PLATING (IF REQUIRED).
This permit is for Major construction work in the ROW and will be billed at an additional
$60/HR for inspections. After hours and weekend work will be billed at $125/HR
MFP21003966
THIS SKETCH NOT TO BE RELIED UPON FOR EXACT LOCATION OF EXISTING FACILITIES
CALL (800) 424-5555
2 BUSINESS DAYS BEFORE YOU DIG
For contacts below dial 1-888-CALL PSE (225-5773)
DESIGNED BY
UTILITIES
CONTACT
PHONE#
COUNTY
1/4 SEC
U-MAP NO (POWER)
OP MAP
Emer Sect Gas Wk Ctr POWER WK CTR
PLAT MAP
JOINT FACILITIES ARRANGEMENTS
DRAWN BY
CHECKED BY
APPROVED BY
FOREMAN #1
FOREMAN #2
MAPPING
INCIDENT MAOP
Gas Order Elect Order
SCALE PAGE
ENGR - POWER
ENGR - GAS
FUNCTION
PROJECT MGR
PERMITREAL ESTATE/EASEMENT
2
1
REV#
3
DATE DESCRIPTIONBY
CONTACT PHONE NO DATE
OH CKT MAP CIRCUIT NOUG CKT MAP
LEE BROWN 425.417.8620 4.01.21
A. DUNN 206.437.9150 7.21.21
...
J.COSSETTE 206.584.4408 6.13.21
REDT # ( RW-112327 )RENTON/ KING COUNTY
FOREST TERRACE SCH 73
SCHEDULE 73 OH-UG CONVERSION - 2 SPANS
2611 UNION AVE NE, RENTON, WA 98059
PUGET SOUND ENERGY
..
.101140385
AS SHOWN 2 OF 5
KING N/A N/A QCSOKE
NE 4-T23N-R05E N/A N/A
2305E013 2305E040 2305E013 PRE-14
COMCAST
JAMES COHN
253.569.0636
CENTURYLINK
KENNETH LUU
206.346.0144
RENTON SCHOOL DIST.
JAY GRAY
253.226.8314
PSE RIGHT OF WAY
AMBER YANG
425.456.2774
...
...
...
UNIVERSAL MAP - EXISTING (2305E013)
SCALE: 1:50
SCALE: 1:100
UNDERGROUND CIRCUIT MAP - EXISTING (2305E013)
JOB
SITE
JOB
SITE
MFP21003966
UNION AVE NEUNION AVE NENE 27TH PL
TRANSFER
TRANSFER
RE-PULL
1Ø 1/O
40.5'30'
25'
25'
27'
27'
NE 27TH
P
L
10.5' ROW
DEDICATION
10.5' ROW
DEDICATION FEEDPRE14ABCN336.4ACSR336.4ACSRC4/OACSRABCN
4/OACSRTRANSFER 4/OACSRABCN
ABCN
#2ACSR
ABCN
4/OACSRC#4ACSR
'A''B'
'C''D'
'E'
TRANSFER
25.0'
5.0'
5.0'
40.5'30'
2.0'
8.0'
0.5'New R.O.W.New R.O.W.R.O.W.R.O.W.C/LC/L5.0'
2-2" Sch.80 1-6" Sch.80
1-4" Sch.801-3" Sch.80
2-3" Sch.80
1-4" Sch.80
1-6" Sch.80
10.5' ROW
DEDICATION
UNION AVE NEEASEMENTEASEMENTUNION AVE NETHIS SKETCH NOT TO BE RELIED UPON FOR EXACT LOCATION OF EXISTING FACILITIES
CALL (800) 424-5555
2 BUSINESS DAYS BEFORE YOU DIG
For contacts below dial 1-888-CALL PSE (225-5773)
DESIGNED BY
UTILITIES
CONTACT
PHONE#
COUNTY
1/4 SEC
U-MAP NO (POWER)
OP MAP
Emer Sect Gas Wk Ctr POWER WK CTR
PLAT MAP
JOINT FACILITIES ARRANGEMENTS
DRAWN BY
CHECKED BY
APPROVED BY
FOREMAN #1
FOREMAN #2
MAPPING
INCIDENT MAOP
Gas Order Elect Order
SCALE PAGE
ENGR - POWER
ENGR - GAS
FUNCTION
PROJECT MGR
PERMITREAL ESTATE/EASEMENT
2
1
REV#
3
DATE DESCRIPTIONBY
CONTACT PHONE NO DATE
OH CKT MAP CIRCUIT NOUG CKT MAP
LEE BROWN 425.417.8620 4.01.21
A. DUNN 206.437.9150 7.21.21
...
J.COSSETTE 206.584.4408 6.13.21
REDT # ( RW-112327 )RENTON/ KING COUNTY
FOREST TERRACE SCH 73
SCHEDULE 73 OH-UG CONVERSION - 2 SPANS
2611 UNION AVE NE, RENTON, WA 98059
PUGET SOUND ENERGY
..
.101140385
AS SHOWN 3 OF 5
KING N/A N/A QCSOKE
NE 4-T23N-R05E N/A N/A
2305E013 2305E040 2305E013 PRE-14
COMCAST
JAMES COHN
253.569.0636
CENTURYLINK
KENNETH LUU
206.346.0144
RENTON SCHOOL DIST.
JAY GRAY
253.226.8314
PSE RIGHT OF WAY
AMBER YANG
425.456.2774
...
...
...
CIRCUIT FEET REMOVED:486'
CIRCUIT FEET ADDED: 455'
1"=50'
SITE PLAN
SITE SPECIFIC NOTES
AT P01 (319075-167131) 1986 CL1 - 40'
-TRANSFER 3Ø 4/O ACSR OH FEEDER & NEUTRAL (N&S) TO P1A
-REMOVE OH SEC TPX (N&S)
-TRANSFER EX 50kVA OH TRF TO P1A
-REMOVE ALL PSE FACILITIES & TOP POLE 1' ABOVE COMM
-COMM TO TRANSFER TO P1A
-REMOVE POLE (2ND TRIP)
AT P1A (NEW)
-INSTALL NEW 45FT CLASS 1 POLE (PD451) 6010.1000 PER STAKED
LOCATION
-INSTALL EXISTING 3Ø TERM ON NEW 3Ø TANGENT FIBERGLASS 2
ACSR ARM (TANC312) 6033.2010
-INSTALL EXISTING 50kVA OH TRF FROM P01
-TRANSFER 3Ø 4/O ACSR OH FEEDER &-ADD AMR 54404
-INSTALL GRID #319068-167131
AT P02 (319092-167131) 1969 CL1 - 40'
-DISCONNECT OH SEC TPX TO 2616 & TRANSFER TO P05
-REMOVE OH SEC TPX TO 2611
-REMOVE POLE AND ALL PSE EQUIPMENT
AT P2A (NEW)
-INSTALL NEW 50FT CLASS H1 POLE (PD50H1) 6010.1000 PER STAKED
LOCATION
-INSTALL 200A/600A 3Ø DBL TERM (TSU6D31) ON NEW 3Ø TANGENT
FIBERGLASS 339 AAC ARM (TANC313) 6033.2012
-INSTALL (3) STIRRUPS (2254100)
-INSTALL (1) NEW 6" FEEDER RISER ON NEW STNADOFF BRACKETS
(RIS6CSS) 6042.1000
-INSTALL (1) NEW 4" PRI RISER ON NEW STANDOFF BRACKETS
(RIS4CSS) 60421000
-INSTALL NEW GRID#319081-167131
AT P03 (319112-167131) 1961 CL1 - 40'
-REMOVE UG SEC TPX - SPLICE TO RE-FEED FROM V01 (SPL10J)
6041.2000
-REMOVE OH 1Ø 2" PRIMARY UP TO IP1
-REMOVE 25kVA OH TRF
-REMOVE AMR UNIT 54404
-REMOVE 40T SOLID BLADE SWITCH
-REMOVE POLE AND ALL PSE EQUIPMENT
Installed at site:
Grid Number:
kVA Rating:
TRANSFORMER INSTALLATION (OH)
Company ID#:
Primary phase connected to:
Tested Secondary Voltage
Material ID#:
Foreman to redline the following information
50kVA 120/240v
6211350
P1A
319068-167131
1"=10'
SITE DETAIL 'A'
SITE DETAIL 'A'
Developer Note:
The following Fault Current information MUST BE conveyed
to the builder of the units:
All units may require upgraded house electrical equipment as the
fault current at the meter base may exceed 10,000 amps.
FAULT CURRENT TABLE
1Ø PM TRANSFORMERS (240/120V)
120V WINDINGS 240V WINDINGS
LOCATION SIZE R/X MIN.
%Z
FAULT
CURRENT
MIN.
%Z
FAULT
CURRENT
V01 75KVA 0.5 2.30 36,200 1.80 23,100
DEVELOPER TO COORDINATE WITH PSE
PROJECT MANGER & SERVICE PROVIDER
PRIOR TO EXCAVATING WITHIN 3' OF
LOCATE MARKS OF PSE ENERGIZED
FACILITIES
SPAN NOTES
P01 TO P1A
-REMOVE ± 25' 4/0 ACSR AS NEEDED
REMOVED ( ') 4/0 ACSR
-TRANSFER EX OH 4/0 ACSR TO NEW P1A
P01 TO P02
-REMOVE ± 145' OH TPX SEC AS NEEDED
REMOVED ( ') OH TPX SEC
-TRANSFER EX 4/0 ACSR SVC TO NEW P2A
P02 TO 2616
-REMOVE ± 115' OH TPX SEC AS NEEDED
REMOVED ( ') OH TPX SEC
-TRANSFER EX OH TPX SEC TO NEW P05
P02 TO P03
-REMOVE ± 115' OH TPX SEC AS NEEDED
REMOVED ( ') OH TPX SEC
-TRANSFER EX OH TPX SEC TO NEW P05
P2A TO P4A
-INSTALL ± 460' 397.5 MCMAAC FEEDER
INSTALLED ( ') 397.5 NCNAAC FEEDER
P03 TO IP1
-ABANDON ± 135' 2" DB120 CONDUIT
ABANDONED ( ') 2" DB120 CONDUIT
P03 TO 2623
-REMOVE ± 35' OH TPX SEC AS NEEDED
REMOVED ( ') OH TPX SEC
-SPLICE TAIL SP1 TO V01
P03 TO P04
-REMOVE ± 255' 4/0 ACSR AS NEEDED
REMOVED ( ') 4/0 ACSR
P04 TO P4A
-INSTALL ± 35' #2 ACSR OH PRIMARY AS NEEDED
INSTALLED ( ') #2 ACSR OH PRIMARY
P05 TO 2616
-TRANSFER EX OH TPX SEC TO NEW P05
TRANSFERRED ( ') OH TPX SEC
CROSSING CONDUIT TABLE
X-ING
#
LOCATION POWER
XING
LENGTH
ASBUILT
LOCATION
TYPE OF CROSSING
(Feeder, Primary, Secondary,
etc.)FROM TO
SIZE
(IN)TYPE QTY
X01 'A''B'3 SCH80 1 80 ( )'SCL SECONDARY
X02 'C''D'2 SCH80 1 95 ( )'SCL PRIMARY
X03 'C''E'
2 SCH80 1 90 ( )'WCL FUT PRIMARY
4 SCH80 1 90 ( )'WCL PRIMARY
6 SCH80 1 90 ( )'WCL FEEDER
2" SCH80 GREY PVC = 185 FT 2" PVC PLUG /CAPS = 4
3" SCH80 GREY PVC = 80 FT 3" PVC PLUG /CAPS = 2
4" SCH80 GREY PVC = 90 FT 4" PVC PLUG /CAPS = 2
6" SCH80 GREY PVC = 90 FT 6" PVC PLUG /CAPS = 2
Removed at site:
Grid Number:
kVA Rating:
Foreman to redline the following information
TRANSFORMER REMOVAL
Company ID#:
Primary phase connected to:
Tested Secondary Voltage
P03
319112-167131
25kVA
Removed at site:
Grid Number:
kVA Rating:
Foreman to redline the following information
TRANSFORMER REMOVAL
Company ID#:
Primary phase connected to:
Tested Secondary Voltage
P01
319075-167131
50kVA
DEVELOPER TO PROVIDE TYPICAL 5' PSE
FRONTAGE EASEMENT FOR OPERATION
AND MAINTENANCE OF PSE EQUIPMENT.
EASEMENT TO BE CLEAR OF ALL BUILDING
OVERHANGS AND FOUNDATION FOOTINGS
1"=10'
SITE DETAIL 'B'
SITE DETAIL 'B'
SITE SPECIFIC NOTES CONT.
AT P04 (319151-167130) 2001 CL UNK - 45'
-AT EXISTING P04 INSTALL 10" SINGLE HELIX 1" ROD
PLATE ANCHOR (ANDH1) WITH ±30FT LEAD(S)
6012.1000
-INSTALL (2) 3/8 GUY STRANDS (GYD3SA) 6013.0100
-REMOVE EXISTING 3Ø 4/0 ACSR
-ROTATE TRANSFORMER BANK TO NORTH SIDE OF
POLE
-POLE TO REMAIN
AT P4A (NEW)
-INSTALL NEW 45' CLASS 1 POLE (PD451) 6010.1000
-INSTALL 200A/600A TERM (TSUD631) PER STD
6043.1022
-INSTALL FEEDER TERMINATION (3ɸ -
397.5MCMAAC) (TSU3DF1) 6043.1020
-INSTALL (3) WEDGE CONNECTORS (MID: 2368200)
-INSTALL (1) 6'' RISERS (RIS6CSS) 6042.1000
-INSTALL (1) 4'' PRIMARY RISER (RIS4CSS)
-INSTALL GRID #319127-167132
AT P05 (NEW)
-INSTALL NEW 35' CLASS 3 POLE (PS353) 6010.1000
-INSTALL NEW 3" SECONDARY RISER (RIS3CSS)
6042.1000
-INTERCEPT EXISTING OH SECONDARY TPX TO
2616
-INSTALL GRID #319091-167137
AT E01
-INSTALL NEW E MARKER (7668501)
AT E02
-INSTALL NEW E MARKER (7668501)
NEW:
%V DROP: 2.4 @ P05
% FLICKER: 2.3 @ P05
EXISTING:
% V. DROP: 3.6% @ 2616
% FLICKER: 4.0% @ 2616
NEW:
%V DROP: 2.2 @ SP1
% FLICKER: 2.5 @ SP1
EXISTING:
% V. DROP: 1.0% @ P03
% FLICKER: 1.8% @ P03
RESTORATION PER CITY OF RENTON STANDARDS
MFP21003966
DESIGNED BY
UTILITIES
CONTACT
PHONE#
COUNTY
1/4 SEC
U-MAP NO (POWER)
OP MAP
Emer Sect Gas Wk Ctr POWER WK CTR
PLAT MAP
JOINT FACILITIES ARRANGEMENTS
DRAWN BY
CHECKED BY
APPROVED BY
FOREMAN #1
FOREMAN #2
MAPPING
INCIDENT MAOP
Gas Order Elect Order
SCALE PAGE
ENGR - POWER
ENGR - GAS
FUNCTION
PROJECT MGR
PERMITREAL ESTATE/EASEMENT
2
1
REV#
3
DATE DESCRIPTIONBY
CONTACT PHONE NO DATE
OH CKT MAP CIRCUIT NOUG CKT MAP
LEE BROWN 425.417.8620 4.01.21
A. DUNN 206.437.9150 7.21.21
...
J.COSSETTE 206.584.4408 6.13.21
REDT # ( RW-112327 )RENTON/ KING COUNTY
FOREST TERRACE SCH 73
SCHEDULE 73 OH-UG CONVERSION - 2 SPANS
2611 UNION AVE NE, RENTON, WA 98059
PUGET SOUND ENERGY
..
.101140385
AS SHOWN 4 OF 5
KING N/A N/A QCSOKE
NE 4-T23N-R05E N/A N/A
2305E013 2305E040 2305E013 PRE-14
COMCAST
JAMES COHN
253.569.0636
CENTURYLINK
KENNETH LUU
206.346.0144
RENTON SCHOOL DIST.
JAY GRAY
253.226.8314
PSE RIGHT OF WAY
AMBER YANG
425.456.2774
...
...
...
THIS SKETCH NOT TO BE RELIED UPON FOR EXACT LOCATION OF EXISTING FACILITIES
CALL (800) 424-5555
2 BUSINESS DAYS BEFORE YOU DIG
For contacts below dial 1-888-CALL PSE (225-5773)
VAULT & EQUIPMENT TABLE
SITE #GRID #
VAULT SIZE &
COVER
TYPE & SIZE
EQUIPMENT IN
VAULT
PRIMARY
BUSHINGS TRANSFORMER ID NUMBERS
(COMPANY ID)
AS-BUILT INFORMATION
LB DC FOREMAN: INCLUDE PHASE TAPPED
J01 319095
167130
4'8"x7'x5'
w/2-3' Sq Doors
Matid: 7663200
J-Box Below Grade
w/ 4-Pos J-Bus x3
Matid: 7625900
8 4
JBOX15L 6055.1030 3Ø
ELB10J 6041.1000
CAP (7630600)
V01 319094
167129
54"x54"x38"
Unistrut HH
Matid: 7663002
75KVA MP TRF
120/240
Matid: 6247150
1 1
MINU1LR 6045.1010 AØ
EXISTING
V02
319121
167151
42"X48"X38"
Unistrut HH
Matid: Existing
50KVA MP TRF
120/240
Matid: Existing
1 -
ELB10J 6041.1000
PRIMARY CABLE & CONDUIT TABLE
LOCATION CONDUIT CABLE ASBUILT INFORMATION - FOREMAN COMPLETE
FROM TO SIZE
(IN)QTY.
DESIGN
LENGTH
(FT)
BENDS PULL
(LBS)
PULL
REV
(LBS)
CABLE SIZE
DESIGN
LENGTH
(FT)
PHASE - ID TAG RECORD RECORD PHASE TAPPED & ACTUAL FOOTAGE INSTALLED LUBRICANT (Gal.)
90°45°22°11°A B C MANUFACTURER COMPOUND YEAR NOTES CONDUIT CABLE EST.ACTUAL
P04 P4A 4 1 30 ----377 377 3Ø 1/0 AL JKT 90 -0.6
P4A P2A 6 1 460 -2 --1432 1427 3Ø 1/0 AL JKT 520 -3.6
P4A J01 4 1 35 -2 --336 557 3Ø 1/0 AL JKT 340 EIV129 EIV130 EIV131 -2.5
J01 E01 2 1 240 1 1 --CONDUIT ONLY
J01 V01 2 1 5 ----32 32 1/0 AL JKT 15 EIV132 0.1
J01 IP1 CABLE ONLY 126 121 1/0 AL JKT 125 EIV133 0.5
J01 V02 2 1 390 1 ---CONDUIT ONLY
J01 P2A 4 1 135 -1 --468 436 3Ø 1/0 AL JKT 165 EIV134 EIV135 EIV136 1.2
2" PVC (FT) & BENDS =635 2 1 --1/0 AL JKT TOTAL (FT) =140 0.7
4" PVC (FT) & BENDS =470 -3 --3Ø 1/0 AL JKT (FT) =1115 1.1
6" PVC (FT) & BENDS =460 -2 --1.6
NEW PRIMARY UNDERGROUND CIRCUIT ONE-LINE DIAGRAM
NOT TO SCALE
RETIREMENT POLE TABLE
SITE
#
POLE DATA POLE TRANSFERS REMARKS
GRID #HEIGHT CLASS YEAR XFMR CO.
ID#TOPPED RMVD TEL TV FIBER ST. LIGHT (ADDITIONAL INFORMATION)
P01 319075
167131 40'1 1986 DD0360 COMCAST/ RENTON SCHOOL DISTRICT
P02 319092
167131 40'1 1969 LUMEN/ COMCAST/ RENTON SCHOOL DISTRICT
P03 319112
167131 40'1 1961 122904879 LUMEN/ COMCAST/ CELLNET/ RENTON SCHOOL DISTRICT
POLE TABLE (NEW)
Site
#
Pole Data
Grid #Height Class Year Remarks / Location Ref.
P1A 319068
167131 45'1 2021 PSE Equip #
P2A 319081
167131 50'H1 2021 PSE Equip #
P4A 319127
167132 45'1 2021 PSE Equip #
P05 319091
167137 35 3 2021 PSE Equip #
NOT TO SCALE
NEW CONDUIT DIAGRAM
CONDUIT LEGEND
PRIMARY 2"
FEEDER 6"
PRIMARY 4"
SECONDARY 3"
EXISTING 3"
PRIMARY 3"
SECONDARY CABLE & CONDUIT TABLE
LOCATION
CABLE CONDUIT VOLTAGE ASBUILT INFORMATION
SIZE LENGTH ASSUMED SIZE LENGTH BENDS DROP FLICKER Foreman - Complete
FROM TO (1/O,4/O,350)Design (ft)Lot Corner to
Meter (ft)(in)Design (ft)90°45°22°11°(Percent)(Percent)Actual Amount Installed Cable Conduit
V01 P05 1/O 95 70 3 15 2 0 0 0 2.4 2.3 SEE VDROP
V01 SP1 1/O 105 70 3 105 2 0 0 0 2.2 2.5 SEE VDROP
V01 E01 CONDUIT ONLY 3 65 0 1 0 0 FUT. FEED LOT 25
350 UG Triplex (ft) =200 3" PVC & BENDS (ft)=185 4 1 0 0 0.1
TOTAL QTS OF GLUE 0.1
WIRE REMOVAL TABLE
Location
Pri Sec Wire Size & Type Quantity
Length
(ft per
conductor)RemarksFromTo
P02 P04 X 4/O ACSR OH PRI &
NEUTRAL 4 490
P01 P02 X 1/O OH TPX SEC 1 145
P02 2616 X 1/O OH TPX SEC 1 110
Total CKT Feet (4/O ACSR PRI) Removed 490
Total Feet ( 4/O ACSR NEUT) Removed 490
Total Feet ( 1/O OH TPX SEC) Removed 255
CABLE/WIRE REMOVAL TABLE
SPAN ACTUAL REMARKS
FROM TO CABLE TAG SIZE LENGTH WIRE
P03 V02 BØACJ657 1/O AL JKT 125'-
NEW 1/O AL
EIV129-AØ
EIV130-BØ
EIV131-CØ
NEW 1/O AL
EIV134-AØ
EIV135-BØ
EIV136-CØ
NEW 1/O AL
EIV133-BØ
NEW 1/O AL
EIV132-AØ
MFP21003966
DESIGNED BY
UTILITIES
CONTACT
PHONE#
COUNTY
1/4 SEC
U-MAP NO (POWER)
OP MAP
Emer Sect Gas Wk Ctr POWER WK CTR
PLAT MAP
JOINT FACILITIES ARRANGEMENTS
DRAWN BY
CHECKED BY
APPROVED BY
FOREMAN #1
FOREMAN #2
MAPPING
INCIDENT MAOP
Gas Order Elect Order
SCALE PAGE
ENGR - POWER
ENGR - GAS
FUNCTION
PROJECT MGR
PERMITREAL ESTATE/EASEMENT
2
1
REV#
3
DATE DESCRIPTIONBY
CONTACT PHONE NO DATE
OH CKT MAP CIRCUIT NOUG CKT MAP
LEE BROWN 425.417.8620 4.01.21
A. DUNN 206.437.9150 7.21.21
...
J.COSSETTE 206.584.4408 6.13.21
REDT # ( RW-112327 )RENTON/ KING COUNTY
FOREST TERRACE SCH 73
SCHEDULE 73 OH-UG CONVERSION - 2 SPANS
2611 UNION AVE NE, RENTON, WA 98059
PUGET SOUND ENERGY
..
.101140385
N/A 5 OF 5
KING N/A N/A QCSOKE
NE 4-T23N-R05E N/A N/A
2305E013 2305E040 2305E013 PRE-14
COMCAST
JAMES COHN
253.569.0636
CENTURYLINK
KENNETH LUU
206.346.0144
RENTON SCHOOL DIST.
JAY GRAY
253.226.8314
PSE RIGHT OF WAY
AMBER YANG
425.456.2774
...
...
...
THIS SKETCH NOT TO BE RELIED UPON FOR EXACT LOCATION OF EXISTING FACILITIES
CALL (800) 424-5555
2 BUSINESS DAYS BEFORE YOU DIG
For contacts below dial 1-888-CALL PSE (225-5773)
VAULT DETAIL @ V01
NOT TO SCALE
TOP VIEW
SIDE
VIEW
EXCAVATION:
4-2/3 CUBIC YARDS
Rock
Crushed
6"
3'-6"
2"
6'
6'
48"42"
36"
38"
42"
Struts
FRONT
FRONT575 HH
2"
Excavation - 19-1/2 cubic yards
SIDE VIEW
5'-4"Crushed
6"
Rock
TOP VIEW
9'
11'
7'-0"
4'-0"
1'
4'-8"
VAULT DETAIL @ J01
NOT TO SCALE
CLEAR WORKING SPACE FOR VAULTS
NOT TO SCALE
FIELD SIDE (PREFERRED)
ROAD SIDE (PREFERRED)
6' MIN
3'
MIN
3'
MIN
3' MIN
Standoff Bracket
15" Min Length
Conduit Clamp
Conduit Field Face
Quadrant
Climbing
SpaceRoad Face
Quadrant
Climbing
Space
5" Min
CL LCDirection of Vehicular Traffic
CONDUIT RISER PLACEMENT DETAIL
TOP VIEW
NOT TO SCALE
COOLING
5' MIN
5' MIN
10' MIN
5'
MIN
FINS
ACCESS
CONCRETE PAD
MINIMUM CLEARANCES FOR PSE EQUIPMENT
NOT TO SCALE
CURB OR EDGE OF PAVEMENT
CURB OR EDGE OF PAVEMENT
5' MIN
ROAD OR
PARKING AREA
TYP. PAD
& TRANS-
FORMER
3'
MIN
3' MIN
DOOR
ACCESS
DOOR
REQUIRED
WORK SPACE
AREA
3' MIN
JOINT TRENCH DETAIL
Primary-Schedule 40 (NTS)
Excavated Dirt Pile
Final Grade
24" Min
Backfill for Schedule 40 Conduit
(NO Rocks over 10" Diameter
or foreign objects)Separation
4" Min
18" Min
48"
Max
36"
Min
Cover
Phone & TV Primary Power Cable
in PSE Provided
DB-120 Conduit
ROADSIDE
To Excavated Dirt Pile
MINIMUM CLEARANCES FOR PSE EQUIPMENT
NOT TO SCALE
OIL-FILLED EQUIPMENT
TRANSFORMER
APPROVED
AREA
COMBUSTIBLE BUILDING WALLS & ROOF10'
10'
10'
MFP21003966