HomeMy WebLinkAboutMFP21004013.pdfDEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Major Franchise Permit: MFP21004013
IVR Number: 21004013
Permit Information
Permit Name: Century Link Permits
Address/Location:08/13/2021Application Date:0823059165Parcel Number: 801 HOUSER WAY N
Permit Type:09/30/2021Issue Date:Franchise
Permit Work Class:09/30/2022Expiration Date:Major Utility
Job Number: N.736672Franchise Type:Telephone
Description: Century Link/Lumen to install new copper cable in existing conduit from Houser Way to MH 54 (in WSDOT ROW) to
MH 55 @ NE 7th St/sunset Blvd. Access MH55 for splicing and splice at pole on Houser Way. Wreck out 1500pr after
splicing complete. extend vacated conduit from pole to HH 800 on Houser Way then place new innerduct and fiber
from HH 800 to MH 55. Restoration per City of Renton standards
Contacts
Name Address PhoneTypeBilling
Dena Overaa
QWEST / Century Link
23315 66th Ave S
KENT, WA 98032
B: (206) 345-0173
C: (425) 247-6248
Applicant
Austin Sweeney
Century Link
Applicant
Kim Parker
QWest Corporation
931 14th St, Suite 1000A
Denver, CO 80202
B: (303) 992-0752Contact
Michael Smith
Dycom Industries dba North Sky
11818 SE Mill Plain Blvd, SUITE 410
Vancouver, WA 98684
C: (206) 305-5881Contractor
Business License Number: 36846Construction Contractor: NORTHSC857Q4
CITY OF RENTON ROW 1055 S Grady Way
Renton, WA 98057-3232
Owner
QWest/Century Link - Billing 7850 S TRAFTON St
TACOMA, WA 98409
Specialized
Billing
X
General Conditions & Signature
Permission is hereby given for the work described on this permit according to the conditions hereon and according to the
approved plans and specifications pertaining thereto, subject to compliance with the Ordinance of the City of Renton.
Ÿ
This permit and plans must be posted at the job site at all times.Ÿ
I hereby certify that no work is to be done except as described above and in approved plans, and that work is to conform to
Renton Trench Restoration and Street Overlay Requirements.
Ÿ
Call 425.430.7203 or go to: https://permitting.rentonwa.gov one working day in advance to schedule an inspections and for ANY
work in the Right of Way.
Ÿ
Call 8 1 1 to locate underground utilities at least two full business days prior to any excavation.Ÿ
In accordance with RCW 19.122.033(4) the permit holder is required to contact (Williams Northwest Pipeline at 425.868.1010)
(Olympic Pipeline at 206.510.0575) (Puget Sound Energy at 425.375.3397) to request a consultation with the transmission
pipeline company prior to performing any construction or excavation activities. This requirement to consult with the
transmission pipeline company is in addition to the requirement to Call before You Dig as required in RCW 19.122.
Ÿ
(Date)(Signature)
Page 1 of 1THIS PERMIT AND PLANS MUST BE POSTED AT THE JOB SITE AT ALL TIMES
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Page 1 of 1 | Published: 1/2/2019
Planning Division | 1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425-430-7200
Email: franchisepermits@rentonwa.gov Website: rentonwa.gov
FRANCHISE PERMIT APPLICATION
Published: 1/2/2019
TO THE APPLICANT: Submit an electronic copy of the plans with the Franchise Permit Application and the Site
Specific Traffic Control Application to franchisepermits@rentonwa.gov. Permit cost is $630.00. Inspection fee
for trenching more than 60 lineal feet or installation of 6 or more poles will be billed at $60.00 per hour.
Franchise Agency:
Franchise Job Number: Phone:
Contact Name: Email:
Job Site Address: Project Name:
Description of Work:
Please check all that apply:
☐New Construction ☐Repair/Relocate ☐Underground ☐Overhead ☐Sidewalk ☐Street
☐Open Trench ☐ Bore # of feet:
Contractor Name: Phone:
State Contractors License #: City of Renton Business License #:
“I certify that I am the owner or applicant’s authorized agent and do hereby agree to abide to the terms and conditions set forth
under this permit and shall comply with the City of Renton’s Trench Restoration and Street Overlay Requirements. ”
Signature Date
INSPECTIONS SHALL BE REQUESTED 24 HOURS PRIOR TO COMMENCEMENT OF ALL WORK BY CALLING THE
INSPECTION LINE AT 425-430-7203 OR BY GOING TO MYBUILDINGPERMIT.COM
Jobs are required to be called in for job start, re-inspection and project final. Re-inspection fees are billed at
$125/hour. All Pre-Construction meetings shall be scheduled at a maximum of 14 days prior to the job start date.
Plan Review/Development Engineering Date Approved as submitted
Pre-Construction Meeting required
Site Construction Inspector Date Approved with comments or redlines
Camera inspection of utilities required
Development Engineering Manager Date
QWEST corp d/b/a CenturyLink QC
Austin Sweeney
253 766 7549
Austin.sweeney@centurylink.com
Northsky Communications 425 615 7121
NORTHSC857Q4 BL.028638
N.736672
Houser Way & N 8th St crossing I-405 to NE 7th St & Sunset Blvd
CenturyLink/Lumen to Install new copper cable in existing conduit from Houser Way to MH 54 (in WSDOT R/W) to MH 55 @ NE 7th St/
Sunset BLVD. Access MH 55 for splicing & splice at pole on Houser Way. Wreck out 1500pr after splicing complete. Extend vacated conduit from pole to HH 800
on Houser Way (approx. 20ft), then place new innerduct & fiber from HH 800 to MH 55
X X X X
8/13/21Austin Sweeney
MFP21004013
RESTORATION PER CITY OF RENTON STANDARDS
Scott Warlick 9/30/2021
DEPARTMENT OF PUBLIC WORKS
Note: The Applicant is responsible for compliance with all codes and regulations, whether or not described in this document.
Page 1 of 2 | Published: 11/25/2019
Transportation Division | 1055 South Grady Way, 5th Floor | Renton, WA 98057 | 425-430-7380
Website: rentonwa.gov
TRAFFIC CONTROL PLAN (TCP) APPLICATION
Published: 11/25/2019
TRAFFIC CONTROL PLAN (TCP) MUST BE SUBMITTED TO PUBLIC WORKS TRANSPORTATION DIVISION
FOR REVIEW/APPROVAL NO LATER THAN FIVE (5) WORKING DAYS BEFORE THE DATE OF WORK.
The City of Renton requires any contractor, firm, corporation, or other public/private agency to prepare a TCP and
obtain City of Renton's approval of that plan when construction, repair, or maintenance work is to be conducted
within the city's right-of-way.
TO THE APPLICANT: Submit the TCP application form and required submittal documents to
TCP@rentonwa.gov with the subject line “TCP Application – [Project Name]” or the above address.
The following items, electronic copies preferred, are all required for submittal of the TCP Application:
1.☐ A copy of the Traffic Control Plan (TCP) Application form.
2.☐ A copy of the required TCP layout, preferred 11” X 17” paper size format, which shall:
☐Include map(s) showing the location of the project and work area.
☐Be legible lettering and clear, contrasting, symbols of viewing or printing.
☐Must indicate street names, and north arrow and scale.
☐All signs and detour routes shall conform to the MUTCD, WSDOT TCPs, and the Washington State
Traffic Control Flagger Certification handbook, by the Evergreen Safety Council.
☐Types of plans required:
☐Work hour plan – show all mobility impacts during construction hours.
☐Non-work plan - show all mobility impacts after work hours when limited or no work is
happening in the right-of-way (ROW), if applicable.
☐Changing construction phases – show construction sequence and each construction phase
change even if the traffic control is not modified, if applicable.
☐Pedestrian access/detour plan, if applicable.
Project Name: ______________________________________________ Permit #: _____________________
Project Address: ____________________________________________________________________________
Work Date: From _____________ To _____________ Work Time: Start ______________ End ______________
Description of Work, Work Schedule, Equipment Used: _____________________________________________
___________________________________________________________________________________________
___________________________________________________________________________________________
Construction Company: ________________________________________ Phone/Cell: (_____) _____-________
Applicant Name: _________________________________ Email: ______________________________________
Business Address: _________________________________ City/State: __________________ Zip: __________
Approved By: _______________________________________________ Date: ________________________
Transportation Operations Engineering
CenturyLink/Lumen to install new copper cable in existing conduit from Houser
Way to MH 54 (in WSDOT R/W) to MH 55 @ NE 7th St/Sunset BLVD. Access MH 55 for splicing & splice at pole on Houser way. Wreck out 1500pr after spilcing
1500pr after splicing complete. Extend vacated conduit from pole to HH 800 on Houser Way (approx. 20ft), then place new innerduct & fiber from HH 800 to MH 55
N.736672
Houser Way & N 8th St crossing I-405 to NE 7th St & Sunset Blvd
Monday Friday 8:00am 3:00pm
Northsky Communications LLC.425 615 7121
Austin Sweeney Austin.sweeney@centuryLink.com
23315 66th Ave S Kent 98032
MFP21004013
Scott Warlick CED 9/30/2021
Note: The Applicant is responsible for compliance with all codes and regulations, whether or not described in this document.
Page 2 of 2 | Published: 11/25/2019
APPLICANT AGREES TO ALL THE FOLLOWING:
•TCP must be approved prior to commencing the work, and all permit conditions shall be met.
•Existing pedestrian access shall be maintained. The work on pedestrian facilities shall be limited to one corner
at a time, with the least possible inconvenience or delay to pedestrians.
•Signage shall be used to warn motorcyclists/bicyclists of the potential hazards on any uneven surfaced or
slippery road conditions during work and non-work hours.
•The start of Work Time begins when any street or travel lane is fully/partially closed or impacts the follow of
traffic. This includes set up within the traveled way or immediately adjacent to the roadway.
•Emergency services (253-852-2121) shall be notified twenty-four (24) hours before any street or lane closures.
•Contractor or entity must call Renton School District (425-204-4455) or any public/private agency, including
public transit, to be affected by a temporary lane or road closure.
•TCP for all street and/or lane closures shall be implemented and performed in compliance with the Manual on
Uniform Traffic Control Devices (MUTCD) and/or State of Washington Department of Transportation (WSDOT)
and all traffic regulations of the City of Renton and Revised Code of Washington (RCW).
•Any lane or street closures not in conformance with the approved traffic control plan and/or without
notification of emergency services may result in receiving a citation for violation of RCW 47.36.200 Signs or
Flaggers at thoroughfare work sites and RCW 9A.36.050 Reckless Endangerment, and other applicable State
and City codes.
•Indemnify and hold harmless the City of Renton from any and all claims, actions, and judgments, including all
costs of defense and attorney’s fees incurred in defending against same, arising from and related to
implementation of the approved traffic control plans including claims arising from towing of private vehicles
and the acts of the Applicant’s agents and employees.
•The City of Renton shall be entitled, in its reasonable discretion, to settle claims prior to suit or judgment, and
in such event shall indemnify and hold harmless the City for any such claims paid, including the City’s
reasonable attorney’s fees and litigation costs incurred resulting from such claim.
•In the event any claim or suit is brought against the City within the scope of this Agreement, Applicant will pay
for legal counsel chosen by the City to defend against same.
•Flagger and sign placement are subject to revision by the City Inspector on site, if needed to address traffic or
pedestrian safety or travel.
•Total road closure lasting more than twenty-four (24) hours is subject to the approval by the City Council.
•Approved Temporary TCP must be at the work site during work hours.
•Complete assistance and accommodation shall be provided to all kinds of pedestrian traffic when sidewalk or
walkway is impeded to safely redirect pedestrians around a work zone.
•Any vehicle, equipment, barricade, or portable tow-away sign used within the work area must display a
company logo or any legally acceptable sign showing the company name, address, and telephone number at a
conspicuous place on the vehicle or equipment.
In the case of Temporary No Parking Zones, all the following apply in addition to previous:
•Contractor must complete form to show limits of Temporary No Parking Zone identifying barricade locations
for vacate parking or curb lane usage.
•Contractor must post notice of dates and time of Temporary No Parking Zone with at least two signs per block
seventy-two (72) hours in advance of effective date and time.
•The cover sheet of this TCP form must be attached to each Temporary No Parking Sign on the project site.
•Temporary traffic control devices must be removed immediately when work is done or no construction
activities are going on. If deemed abandoned, City crews will remove and store them at the City’s maintenance
shop (3555 NE 2nd Street; 425-430-7423).
_______________________________ _______________________________ _______________________
Applicant’s Signature Print Name Date
Austin Sweeney Austin Sweeney 8/13/2021
MFP21004013
MFP21004013
MFP21004013
Lumen Civil Base Map
I405 EXPRESS TOLL LANES - NE 8TH TO NE 7TH
W.S.D.O.T. - PROJECT No. XL5467
RENTON, WA
Cover Sheet
2 Legend
3
Civil Base Map Color Key:Existing FacilitiesConflict Mitigation Action (Proposed Facilities)Additional Information Needed/Notes
Estimated % Design Drawings: 90%
Jurisdiction File Name: 41_XL5467_PS_CENT01_UI 1601.pdf
Received file from Jurisdiction Date: 3/8/21
PROJECT LOCATION
FOR REFERENCE ONLY
NOTES:
ALL EXISTING AND PROPOSED CONDITIONS ARE BASED ON INFORMATIONPROVIDED BY OTHERS. LUMEN CANNOT BE RESPONSIBLE FOR THE ACCURACYOF INFORMATION AND/OR PLANS PROVIDED BY OUTSIDE PARTIES. FACILITYLOCATIONS, DEPTHS AND ELEVATIONS SHOULD BE FIELD VERIFIED PRIOR TOCONSTRUCTION.
PROPOSED DESIGN MODIFICATIONS ARE RECOMMENDATIONS ONLY ANDSHOULD BE VERIFIED PRIOR TO CONSTRUCTION.
INDEX OF SHEETS
Plans Prepared For:
Plans Prepared By:
LOCATION MAPNOT TO SCALE N
SHEET 1 of 4DATE: 08-02-21
REV. DATE DESCRIPTION
1 04-02-21 Initial TT Draft Issued
1
CTL JOB: N.GEO CODE:WC CLLI: RNTNWA01 (Renton)ENGINEER: Jesse PatjensPHONE: 206-733-8591EMAIL: jesse.patjens@lumen.comCPA: Paul ButlerPHONE: 206-348-0058EMAIL: paul.butler@centurylink.com
TT Eng: Chelsea LloydPhone: 208-755-3226E-mail: clloyd@terratechllc.netTT #: WACLhttp://www.terratechllc.net
TT Eng: Kelly CasteelPhone: 206-353-6847E-mail: kcasteel@terratechllc.netTT #: WACLhttp://www.terratechllc.net TT Eng: Tom BrownPhone: 206-799-2989E-mail: tbrown@terratechllc.net TT #: CL 16.7042http://www.terratechllc.net
TT Eng: Beth TanPhone: 206-660-6330E-mail: btan@terratechllc.net TT #: WACLhttp://www.terratechllc.net
TT Eng: Mike CockéPhone: 253-732-7075E-mail: mcocke@terratechllc.netTT #: WACLhttp://www.terratechllc.net
TT Eng: Kristal GreenhawPhone: 425-512-5061E-mail: kgreenhaw@terratechllc.netTT #: WACLhttp://www.terratechllc.net
Utility Plan
TT Eng: Cory CoatePhone: 503-961-5023E-mail: ccoate@terratechllc.netTT #: WACLhttp://www.terratechllc.net
TT Eng: Tim PersonettPhone: 509-570-8967E-mail: tpersonett@terratechllc.netTT #: WACLhttp://www.terratechllc.net
2 04-07-21 Revised Placement Notes
3 08-02-21 Added Profile Information
4 Utility Profile
MFP21004013
Legend
X
X XXX X
X X X
HH
HH
HHX
X
X
XX XCP
)
X
Existing CenturyLink pedestalor
or
or
New CenturyLink pedestal
Existing CenturyLink pedestal to be removed
Existing CenturyLink SAI (serving area interface)
New CenturyLink SAI (serving area interface)
Existing CenturyLink SAI to be removed orabandoned
Existing CenturyLink cable or conduit to beremoved or abandoned
Existing CenturyLink handhole
New CenturyLink handhole
Existing CenturyLink handhole to be removed
Existing CenturyLink manhole (various sizes)
New CenturyLink manhole (various sizes)
Existing CenturyLink double lidded manhole(various sizes)
New CenturyLink double lidded manhole(various sizes)
Existing CenturyLink manhole to be removedor abandoned (all sizes and types)
Existing CenturyLink repeater
New CenturyLink repeater
Existing CenturyLink repeater to be removed
CP
Existing CenturyLink cool ped. - fiber/electronics
New CenturyLink cool ped. - fiber/electronics
Existing CenturyLink RT (remote terminal)
New CenturyLink RT (remote terminal)
Existing CenturyLink pole
New CenturyLink pole
Existing CenturyLink pole
Existing CenturyLink down guy and anchor
New CenturyLink down guy and anchor
New CenturyLink sidewalk down guy and anchor
Existing power company down guy and anchor
X
X
Lumen Civil Base Map 2
of 4
btel Existing buried telephone line
tduc Existing telephone duct run
afo-exist Existing aerial fiber optic
aer-tel Existing overhead telephone line
fo-exist Existing buried fiber optic
bsw-ex Existing buried service wire
asw-ex Existing aerial service wire
New overhead telephone line
BTEL New buried telephone line
TDUC New telephone duct run
BSW-NEW New buried service wire
AFO-NEW New aerial fiber optic
AER-TEL
FO-NEW New buried fiber optic
ASW-NEW New aerial service wire
Project Details
Narrative/Special Remarks:
The CenturyLink relocation scope will include:•
Construction Sequencing Description Regarding CenturyLink Relocation Scope
and Jurisdiction Project Construction:
CenturyLink's relocation scope is planned to occur prior to Jurisdiction's
Construction Start Date.
Temporary Facilities:
There are no planned temporary facilities as part of CenturyLink's relocation
scope.
Example Narrative/Special Remarks:
This project proposes to relocate CenturyLink facilities along (insertproject route) between (insert project extents) for the Constructionof (insert Jurisdiction's Project Name and Number).
Existing buried splice
New buried splice
New leased pole
Existing leased poleL
L
Abbreviations
ct. Countpr. Pairpp Pending Placementug. Underground
Existing joint use pole
New joint use pole
New foreign owned (e.g. power)
Existing foreign owned (e.g. power)
J
J
Existing CenturyLink power pedestal
New CenturyLink power pedestal
P
P
Existing CenturyLink pole to be removed
1. ALL DUCT ELEVATIONS ARE BASED ON POTHOLE INFORMATION, UNLESS
NOTED OTHERWISE, AND HAVE BEEN PROVIDED BY OTHERS. ELEVATIONS
SHOWN ARE TOP OF DUCT. DEPTHS SHOWN ARE DISTANCE BELOW
EXISTING FINISHED GRADE.
2. PROPOSED VAULT AND DUCT LOCATIONS SHALL BE FIELD VERIFIED
AGAINST EXISTING AND PROPOSED UTILITIES. ENGINEER IN CHARGE
DURING CONSTRUCTION SHALL BE NOTIFIED OF CONFLICTS.
Notes All methods, materials, content and form contained in this
material are the intellectual property of Terra Technologies
LLC, and may not be copied, reproduced, distributed, or
displayed without the express written permission of
Terra Technologies LLC.
The technology presented in this material is protected under
various U.S. and international patents and pending patent
applications, including without limitation, U.S. Patent Nos.
7,771,140; 8,016,518; and 8,061,934.
MFP21004013
XL5467
CENT01MATCH LINE SB405 STA. 5565+00.00 MATCH LINE SB405 STA. 5550+00.00SCALE IN FEET
0 50 1001110
STA. 5550+00 TO STA. 5565+00
UI# 1601 CENTURYLINK - BURIED COMM PLAN
SEW WALL 04.52L
18" Pcssp
12" Pcssp
12" Pcssp12" Pcssp
12" Pcssp 12" Pcssp
12" Pcssp 12" Pcssp
12" PCSSP 12" PCSSP 12" PCSSP
18
" PCSSP
18
" CM
P18
" PCSSP
18" PCSSP
?
?
??
????????
??
?????????????????????????????????????????????????CV
CV ??
?????STTSTT?????
????????????STTRR??STT????MB ????
????????????STT??????MB??STT?MBMB ??????UUUUUUUUUUUUUUUUUUUUUUUUUCC CCCCCCCCCCCPPPPPPP
PP PPP
P P
PP
P
P
P
PPPPPPP
P
CV
CV SSSSSSSSSSSSPHPHPHPHCPCPCMW-201
-20 W-20
2-20 PHPHPH??
?????STTSTT?????
????????????STTRR??STT????MB ????
????????????STT??????MB??STT?MBMB ??????UUUUUUUUUUUUUUUUUUUUUUUUUCC CCCCCCCCCCCPPPPPPP
PP PPP
P P
PP
P
P
P
PPPPPPP
P
CV
CV SSSSSSSSSSSSPHPHPHPHCPCPCMW-201
-20 W-20
2-20 PHPHPHWL 4.9RBUILDINGSPACCAR PLATT ELECTRIC SUPPLY
SB I-405
NB I-405 N. 8TH STSUNSET BLVD NE
HOUSER WAY BYPASS
SUNSET BLVD NENE 7TH STWL 4.9R
SSSSSSSSSSSSSSPHPHPHPHCPCPCPHPHPHMP 4.65
MP 4.70 MP 4.75
MP 4.80
MP 4.85
MP 4.90
DESIGNED BY
ENTERED BY
CHECKED BY
PROJ. ENGR.
REGIONAL ADM.
FILE NAME
TIME
DATE 12/24/2020
c:\users\matt\documents\projectwise\workingdir\wsdot\dms09123\41_XL5467_PS_CENT01_UI 1601.dgn
REVISION BY
SHEET
OF
SHEETS
LOCATION NO.CONTRACT NO.
JOB NUMBER
REGION
NO.
STATE FED.AID PROJ.NO.
WASH10PLOTTED BY
DATE
11:12:09 AM Washington State
Department of Transportation
P.E. STAMP BOX
DATE
P.E. STAMP BOX
DATE
PLAN REF NO
TDW
MF
JMS
CALL 2 DAYS
BEFORE YOU DIG
1-800-424-5555
J. LEFOTU
MF
L. HODGSON
AND EXPRESS TOLL LANES PROJECT
I-405; RENTON TO BELLEVUE WIDENING
C9242
XL5467
TYPE 1
LOCATE AND AVOID
BURIED TELEPHONE
CENTURYLINK
UI#1601
TYPE 1
LOCATE AND AVOID
4" STW HP IN 8" CASING GAS
PSE
UI#1589
PUBLIC
RELOCATE
NEW SSMH
COR
UI#1522
CENT01A15550
75607560
7555
7550
5560
5555
5565
tduc tduc tduc
tductductductductductductductductductductdu
c
tdu
c
tdu
c
aer-tel aer-teltductductductductducHH
2-4" ducts
100 pr. buried
24 ct. ug. fiber
2-4" ducts
1500 pr. ug.
24 ct. ug. fiber
50 pr. aerial
200 pr. aerial
Pedestal
Pole
Metal Power
Pole
MH #54
8'x4'x6'
After new placement & wreck out of
1500pr is complete, remove MH 54,
split duct conduits together.
Mandrel & place mule tape
HH #800
Leave 100ft coil of fiber in HH-800
Tag & label cable with project placing #
8-4" ducts
1500 pr. ug.
Place new 200pr in existing conduit
from pole to MH 55
Place 3-1.25" innerduct & 24ct fiber
Remove DSMC-1500pr ug after
splicing complete
Pedestal w/ term
717 NE Sunset
tductduc2-4" ducts
4-4" ducts
100 pr. ug.
900 pr. ug.
Pole #A1080517
MH #55
8'x4'x6'
Leave 100ft coil of fiber in MH 55
Tag & label cable with project placing #
Pedestal w/ term
701 NE Sunset
Pole
3
of 4
To SAI X 801
Sunset BV NE
Extend spare conduits past edge
of WSDOT improvements
2-3.5" ducts
1500 pr. ug.
MFP21004013
Work and traffic control in
WSDOT ROW will require
additional approval from WSDOT
XL5467
NOTES:
2. FINAL GROUND LEVEL TO BE CONFIRMED.
1. TO BE UPDATED AS DESIGN PROGRESSES.
CENT01A
CENTURYLINK BURIED COMM SECTION
SECTION STA. 7558+88.27
UI# 1601 CENTURYLINK - BURIED COMM 10+0011+0010+5011+5012+00140
130
120
110
60
80
90
70
100
140
130
120
110
60
80
90
70
100 STA. 10+40.77DUCTBANK FOUND AT 93.2'POTHOLED. TOP OF STA. 11+67.80ELEVATION UNKNOWN.POTHOLED. TOP OF DUCTBANK OG
OGSTA: 5562+57.55
FINISHED I-405 SB
STA:7558+59.06
FINISHED I-405 NBDUCTBANK FOUND AT 90.8'POTHOLED. TOP OF STA. 10+34.06STA. 10+27.59CENTER OF 42" VAULT LIDDESIGNED BY
ENTERED BY
CHECKED BY
PROJ. ENGR.
REGIONAL ADM.
FILE NAME
TIME
DATE 12/24/2020
c:\users\matt\documents\projectwise\workingdir\wsdot\dms09123\41_XL5467_PS_CENT01A_UI 1601 PROFILE.dgn
REVISION BY
SHEET
OF
SHEETS
LOCATION NO.CONTRACT NO.
JOB NUMBER
REGION
NO.
STATE FED.AID PROJ.NO.
WASH10PLOTTED BY
DATE
12:52:28 PM Washington State
Department of Transportation
P.E. STAMP BOX
DATE
P.E. STAMP BOX
DATE
PLAN REF NO
TDW
MF
JMS
CALL 2 DAYS
BEFORE YOU DIG
1-800-424-5555
J. LEFOTU
MF
L. HODGSON
AND EXPRESS TOLL LANES PROJECT
I-405; RENTON TO BELLEVUE WIDENING
C9242
XL5467
CENT01
1
Existing Ground
Profile of
Existing Ducts
4
of 4
MH #54
To Be Removed
after new placement
is complete
MFP21004013