Earth Solutions NW, LLC
LETTER OF TRANSMITTAL
15365 NE 90th Street, Suite 100 Redmond, WA 98052
(425) 449-4704 FAX (425) 449-4711
To: RJ Development Date: October 14, 2021
401 Central Street SE ESNW No.: ES- 895.06
Olympia, WA 98501 Project: Weatherly Inn
Attn: Mr. Jeff Bennett
Email: jeffb@accrete.build
No. of
Copies Date Description
1 10/11 – 10/13/21 Daily Field Report(s) # 316-318
Comments:
CC:
1: Mark Richardson ATTN: mark@accrete.build
2: Jennifer Vogele ATTN: jennifer@accrete.build
3: Jonathan Chavez ATTN: jchavez@rentonwa.gov
4: Joe W ATTN: joew@accrete.build
5: Brittany Perry ATTN: brittany@accrete.build
6: ATTN:
7: ATTN:
8: ATTN:
Transmitted By: Earth Solutions NW, LLC
PM: Scott Riegel, L.G., L.E.G.
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 316
Time On Site Time Off Site Date Day of Week
11:30 AM 12:45 PM 10/11/21 Monday
Travel Time Weather
1.00Hr. RT 60F, Rain
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Johannsen Brad LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site? Project No. Permit No.
Test Number Test Location
(Parking lot
subgrade) Elevation Reference
Compaction
Curve
Maximum Dry
Density (pcf) Fill Moisture
(%) Test
Dry Density
(pcf)
% of Maximum
Dry Density
At the client’s request, ESNW rep was onsite to observe site access roadway subgrade conditions at the Weatherly
Inn development.
Roadway Subgrade:
ESNW rep arrived onsite and observed saturated soil conditions in the site access roadway. ESNW rep used a
½-inch steel T-probe to probe site access roadway. ESNW rep marked an approximately 25-foot by 50-foot area
(shown on plans below) for over-excavation. ESNW rep recommended over-excavation up to 24-inches and
backfill with structural woven geotextile fabric and 2-inch to 4-inch quarry spalls. Contractor relayed 2-inch ATB
lift would be placed over site access roadway and parking areas. Contractor relayed steel sheets would be
placed over areas of saturated soil conditions at site access roadway entrance and over-excavation would take
place at a later date.
ESNW rep will return as requested to continue observation and testing of further earthwork activities.
Fig.1: Access roadway at the Weatherly Inn Development.
Jackson Lundgren, G.I.T.
Senior Field Technician
206-468-0991
1/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 316
Time On Site Time Off Site Date Day of Week
11:30 AM 12:45 PM 10/11/21 Monday
Travel Time Weather
1.00Hr. RT 60F, Rain
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Johannsen Brad LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site? Project No. Permit No.
Fig. 2: Area of saturated soil conditions and recommended over-excavation and backfill with woven geotextile fabric and
quarry spalls
Area of recommended over-excavation
2/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 317
Time On Site Time Off Site Date Day of Week
12:45 PM 1:45 PM 10/12/21 Tuesday
Travel Time Weather
1.00Hr. RT 60F, Rain
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Johannsen Brad LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site? Project No. Permit No.
Test Number Test Location
(Parking lot
subgrade) Elevation Reference
Compaction
Curve
Maximum Dry
Density (pcf) Fill Moisture
(%) Test
Dry Density
(pcf)
% of Maximum
Dry Density
At the client’s request, ESNW rep was onsite to observe and test ATB paving at the Weatherly Inn development.
Asphalt Treated Base Paving:
ESNW rep arrived onsite and observed Lakeside Paving was onsite and placing a 2-inch lift of asphalt treated
base (ATB) along the site parking area and access roadway. ESNW rep observed contractor compacting ATB
with a vibratory drum roller. ESNW rep observed ATB was approximately 295 oF when placed. Density tests
indicated contractor had achieved adequate compaction of 92% of the RICE value or greater for ATB in
the locations tested. Please refer to the attached plan detail for approximate testing locations.
ESNW rep will return as requested to continue observation and testing of further earthwork activities.
Fig.1: Parking area at the Weatherly Inn Development.
Jackson Lundgren, G.I.T.
Senior Field Technician
206-468-0991
1/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 317
Time On Site Time Off Site Date Day of Week
12:45 PM 1:45 PM 10/12/21 Tuesday
Travel Time Weather
1.00Hr. RT 60F, Rain
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Johannsen Brad LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site? Project No. Permit No.
Test Number Test Location
(Roadway/
Parking Area) Elevation Rice Value
(pcf) Fill Moisture % Test Wet
Density
lbs./cu.ft.
% of
Rice Value
342 See map FG 156.0 N/A 144.5 93
343 See map FG 156.0 N/A 143.8 92
344 See map FG 156.0 N/A 145.8 93
345 See map FG 156.0 N/A 146.0 94
346 See map FG 156.0 N/A 145.2 93
347 See map FG 156.0 N/A 144.2 92
348 See map FG 156.0 N/A 143.9 92
349 See map FG 156.0 N/A 144.0 92
350 See map FG 156.0 N/A 142.9 92
351 See map FG 156.0 N/A 143.9 92
352 See map FG 156.0 N/A 145.6 93
Fig. 2: Approximate location of tests 342-352 on ATB paving at the Weatherly Inn Development
2/2
342
343
344 345
346
347
348 349 350
351 352
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 318
Time On Site Time Off Site Date Day of Week
12:45 PM 1:45 PM 10/13/21 Wednesday
Travel Time Weather
1.00Hr. RT 60F, Rain
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Johannsen Brad LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Test Number Test Location
(Parking lot
subgrade) Elevation Reference
Compaction
Curve
Maximum Dry
Density (pcf) Fill Moisture
(%) Test
Dry Density
(pcf)
% of Maximum
Dry Density
At the client’s request, ESNW rep was onsite to observe sidewalk subgrade and test ATB paving at the Weatherly
Inn development.
Sidewalk Subgrade:
ESNW rep observed contractor had placed approximately 4-inches to 6-inches of 1 ¼-inch recycled crushed
concrete as sidewalk subgrade in an approximately 8-foot by 75-foot area at the southwest corner of the Weatherly
Inn development along Talbot Road South. ESNW rep observed contractor compacting sidewalk subgrade with a
vibratory sled compactor. ESNW rep used a ½-inch steel T-probe to probe locations along sidewalk subgrade
and observed subgrade conditions were very dense, firm, unyielding, and suitable for support of the
proposed sidewalk.
Asphalt Treated Base Paving:
ESNW rep arrived onsite and observed Lakeside Paving was onsite and placing a 2-inch lift of asphalt treated
base (ATB) along the site parking area and access roadway. ESNW rep observed contractor compacting ATB
with a vibratory drum roller. ESNW rep observed ATB was approximately 295 oF when placed. Density tests
indicated contractor had achieved adequate compaction of 92% of the RICE value or greater for ATB in
the locations tested. Please refer to the attached plan detail for approximate testing locations.
ESNW rep will return as requested to continue observation and testing of further earthwork activities.
Fig.1: Site access roadway at Weatherly Inn Development
Jackson Lundgren, G.I.T.
Senior Field Technician
206-468-0991
1/2
Type text here
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 318
Time On Site Time Off Site Date Day of Week
12:45 PM 1:45 PM 10/13/21 Wednesday
Travel Time Weather
1.00Hr. RT 60F, Rain
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Johannsen Brad LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Test Number Test Location
(Roadway/
Parking Area) Elevation Rice Value
(pcf) Fill Moisture % Test Wet
Density
lbs./cu.ft.
% of
Rice Value
353 See map FG 156.0 N/A 146.5 94
354 See map FG 156.0 N/A 144.6 93
355 See map FG 156.0 N/A 143.7 92
356 See map FG 156.0 N/A 145.7 93
357 See map FG 156.0 N/A 146.9 94
358 See map FG 156.0 N/A 144.2 92
359 See map FG 156.0 N/A 143.9 92
360 See map FG 156.0 N/A 144.0 92
361 See map FG 156.0 N/A 145.8 93
362 See map FG 156.0 N/A 147.1 94
363 See map FG 156.0 N/A 144.2 92
364 See map FG 156.0 N/A 146.2 94
365 See map FG 156.0 N/A 145.9 94
366 See map FG 156.0 N/A 143.9 92
367 See map FG 156.0 N/A 144.2 92
Fig. 2: Approximate location of tests 353-367 on ATB paving at the Weatherly Inn Development
2/2
363
364
360
361
356
359
355
358
354 357
353
365
366
367