HomeMy WebLinkAboutRS_Construction_Mitigation_Plan__210902_v2SINGH 6 TH ST SHORT PLAT CONSTRUCTION MITIGATION 1. Proposed construction dates: January 3 , 2022. 2. Hours and days of operation: 8 hours per day, 5 days a week. Total 20 -30 days required. 3. Proposed hauling/transportation routes: It will be a route fully approved by City of Renton 4. Measures to be implemented to minimize dust, traffic and transportation impacts, erosion, mud, noise, and other noxious characteristics: Erosion and sediment control requirements will include the delineation of clearing limits via flagging, proper cover measures for the protection of disturbed areas, perimeter protection with silt fencing on an as -needed basis, and a stabilized construction entrance per City of Renton standards. The Erosion and Sediment Control Plan is included. See attached drawings. 5. Any special hours proposed for construction or hauling (i.e.weekends, late nights); and: None currently proposed 6. Preliminary traffic control plan: See attached traffic control plan.