HomeMy WebLinkAboutSummary_Preapp_Mtg_PRE12-000036h:\ced\planning\current planning\preapps\12-036.vanessa\12-036 (r-14 iaquaponics, slope).doc
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
M E M O R A N D U M
DATE:May 17, 2012
TO:Pre-application File No. 12-036
FROM:Vanessa Dolbee, Senior Planner
SUBJECT:iAquaponics – 13043 Renton Ave. S.
General: We have completed a preliminary review of the pre-application for the above-
referenced development proposal. The following comments on development and permitting
issues are based on the pre-application submittals made to the City of Renton by the applicant
and the codes in effect on the date of review. The applicant is cautioned that information
contained in this summary may be subject to modification and/or concurrence by official
decision-makers (e.g., Hearing Examiner, Community & Economic Development Administrator,
Public Works Administrator, Planning Director, Development Services Director, and City
Council). Review comments may also need to be revised based on site planning and other
design changes required by City staff or made by the applicant. The applicant is encouraged to
review all applicable sections of the Renton Municipal Code. The Development Regulations are
available for purchase for $50.00 plus tax, from the Finance Division on the first floor of City Hall
or online at www.rentonwa.gov
Project Proposal: The subject property is located at 13043 Renton Avenue South and is
comprised of six parcels. The overall site is triangular is shape and fronts onto Renton Ave S.
and S. 132nd Street. The project site totals 4.61 acres in area and is zoned Residential-14 du/ac
(R-14). The proposal is to expand on to the existing commercial plant Nursery by adding an
aquaponics component which would include the production of fish, adding a restaurant facility,
food processing facility and agrotourism component. The proposal does not appear to expand
the size of the existing nursery, but would remodel some of the existing facilities to
accommodate the new components. The applicant has not proposed any site improvements
with the application. Under current conditions the site is accessed at four locations, two off of
Renton Ave. S and two off of S. 132nd Street.
Current Use: The site is currently be used as a nursery, which would continue to operate at this
site. The continued operation of the nursery was not include in the application material but was
identified by the current property owner whom discussed the application with City Staff at City
Hall in recent weeks.
Zoning: The project site is zoned Residential-14 (R-14) and is located within the Residential
Medium Density Land Use designation and is also subject to the Residential Design and Open
Space standards. However, because the project is not residential the applicant would be
required to demonstrate compliance with the purpose and intent of the standards. The
following would be applicable:
iAquaponics, PRE12-036
Page 2 of 6
May 17, 2012
h:\ced\planning\current planning\preapps\12-036.vanessa\12-036 (r-14 iaquaponics, slope).doc
a. Site Design: Quality neighborhoods are characterized by well landscaped, safe, pedestrian
oriented streets. These qualities are enhanced by variation in scale and massing with prominent
entries and generous fenestration facing the street.
b. Open Space: Open spaces shall be located so that a hierarchy and/or variety of open spaces
throughout the site is created.
c. Building Design: Key characteristics of attractive neighborhoods include variety architectural
styles, enhanced by attention to selection of exterior materials, colors, and architectural
detailing.
Development Standards
New components and/or buildings would be subject to RMC 4-2-110A, “Development Standards
for Residential Zoning Designations” effective at the time of complete application (noted as “R-
14 standards” herein). A copy of the current standards is included herewith. A Horticultural
Nursery, existing and an Eating and Drinking Establishment are not outright permitted In the R-
14 zone. Therefore the proposal would require an Administrative Conditional Use Permit.
Furthermore, the eating and drinking establishment is limited to 5,000 square feet.
Based on the application materials, the proposed restaurant would be 3,000 square feet, which
would be within the maximum size permitted in the zone. However, the application also
identified a 1,000 square foot food-processing component. Food processing is not an outright
permitted use within the R-14 zone, however based on a phone conversation with the project
applicant on May 10, 2012; the food processing would be accessory and ancillary to the
restaurant use. Pursuant to the applicant, the food processing would be utilizing the same
facility as the restaurant and the products would be sold out of the restaurant. Based on these
assumptions, food processing would be determined to be accessory to the restaurant
component. Furthermore, the eco-tourism activity would also be considered to be accessory to
the nursery.
The table below notes the current standards for the R-14 zone. All new structures would be
required to meet the current development standards of the zone.
Type of Standard Minimum Standard
Setbacks
Min Front Yard 10 ft
Side Yard 4 ft
Rear Yard 12 ft
Side Yard Along-A-
Street
10 ft.
Building Standards
Building Coverage
Ratio
None
Maximum Impervious
Surface Area
85 %
iAquaponics, PRE12-036
Page 3 of 6
May 17, 2012
h:\ced\planning\current planning\preapps\12-036.vanessa\12-036 (r-14 iaquaponics, slope).doc
Height 20 ft
Refuse and Recycle Recycle: 5 SF /1,000 GSF
Refuse: 10 SF / 1,000 GSF
Both of the following are required:
1. Trash and recycling containers shall be located so that
they have minimal impact on residents and their
neighbors and so that they are not visible to the general
public; and
2. A screened enclosure in which to keep containers shall
be provided or garages shall be built with adequate space
to keep containers. Screened enclosures shall not be
located within front yards.
Parking
Eating and drinking
establishments
A minimum and maximum of 10 per 1,000 square
feet of dining area.
Uncovered
commercial area
outdoor nurseries:
A minimum and maximum of 0.5 per 1,000 square
feet of retail sales area in addition to any parking
requirements for buildings.
Bicycle The number of bicycle parking spaces shall be 10% of
the number of required off-street parking spaces.
Landscaping
On-Site Street
Frontage
10 ft
*Except for walk and driveways. In those cases, 10' of
landscaping shall be required where buildings are not
located.
Tree Retention 10 % of significant trees
Setbacks –Not enough information was provided to determine if new buildings would be
constructed. All new structures would be required to meet minimum setbacks standards.
Impervious Coverage – The R-14 zone allows a maximum impervious surface area coverage of
85%. Information regarding the impervious surface area of the site was not provided with the
submittal materials, therefore staff was not able to calculate the lot coverage of the proposal. A
lot coverage analysis meeting the requirements in RMC 4-8-120D.12, shall be submitted at the
time of formal land use application.
Height – Not enough information was provided to determine if new buildings would be
constructed. All new structures would be required to comply with height restrictions.
Access/Parking – The applicant did not provided parking information with their application. A
parking analysis meeting the requirements in RMC 4-8-120D.12, shall be submitted at the time
iAquaponics, PRE12-036
Page 4 of 6
May 17, 2012
h:\ced\planning\current planning\preapps\12-036.vanessa\12-036 (r-14 iaquaponics, slope).doc
of formal land use application. If the proposal provides more or less parking than required by
code, a request for a parking modification would need to be applied for and granted. This
detailed written request should be submitted by the applicant along with the formal land use
application.
Bicycle parking stalls are required to be provided. (RMC 4-4-080F.10 and RMC 4-4-080F.11) for
further general and specific parking requirements.
ADA accessible stalls must be a minimum of 8 feet in width by 20 feet in length, with an adjacent
access aisle of 8 feet in width for van accessible spaces. The appropriate amount of ADA
accessible stalls based on the total number of spaces must be provided.
Landscaping: New development shall comply with the City of Renton Landscape
requirements. The subject development would be required to comply with this section
if the cost of the remodel/addition is equal to or greater than fifty percent (50%) of the
assessed property valuation.
Except for critical areas, all portions of the development area which are not covered by
structures, required parking, access, circulation or service areas, must be landscaped with
native, drought-resistant vegetative cover. The minimum on-site landscape width required
along street frontages is 10 feet. Please refer to landscape regulations (RMC 4-4-070 and RMC
4-4-080F.7) for further general and specific landscape requirements (enclosed). However, the
10-foot landscape strip may be reduced through the site plan review process. A conceptual
landscape plan and landscape analysis meeting the requirements in RMC 4-8-120D.12, shall be
submitted at the time of land use application.
Fences – If the applicant intends to install any fences as part of this project, the location must be
designated on the landscape plan. A fence detail should also be included on the plan as well.
Environmental Review
Remolding a structure over 4,000 square feet, adding over 20 parking spaces and the proposal
of a new restaurant/agritourism facility over 4,000 square feet triggers the requirement for
SEPA Environmental Review.
Critical Areas
Steep slopes are located on the subject site therefore; a geotechnical study may be required.
The study shall be completed by a qualified professional. The study shall demonstrate that the
proposal will not increase the threat of the geological hazard to adjacent properties beyond the
pre-development conditions, the proposal will not adversely impact other critical areas, and the
development can be safely accommodated on the site. In addition, the study shall assess soil
conditions and detail construction measures to assure building stability.
Permit Requirements: The proposal would require a SEPA Environmental Review, Hearing
Examiner Site Plan approval and a Hearing Examiner Conditional Use Permit. All permits are
would be reviewed in an estimated timeframe of 12 weeks.
The purpose of the Site Plan process is the detailed arrangement of project elements so as to be
compatible with the physical characteristics of a site and with the surrounding area. An
additional purpose of Site Plan is to ensure quality development consistent with City goals and
policies. General review criteria includes:
a. Conformance with the Comprehensive Plan;
iAquaponics, PRE12-036
Page 5 of 6
May 17, 2012
h:\ced\planning\current planning\preapps\12-036.vanessa\12-036 (r-14 iaquaponics, slope).doc
b. Conformance with existing land use regulations;
c. Mitigation of impacts to surrounding properties and uses;
d. Mitigation of impacts of the proposed site plan to the site;
e. Access and circulation;
f. Open space;
g. Views and public access;
h. Natural Systems;
i. Services and infrastructure; and
j. Phasing.
The Administrator will consider, as applicable, the following factors for all conditional use permit
applications:
1. Consistency with Plans and Regulations: The proposed use shall be compatible with the
general goals, objectives, policies and standards of the Comprehensive Plan, the zoning
regulations and any other plans, programs, maps or ordinances of the City of Renton.
2. Appropriate Location: The proposed location shall not result in the detrimental
overconcentration of a particular use within the City or within the immediate area of the
proposed use. The proposed location shall be suited for the proposed use.
3. Effect on Adjacent Properties: The proposed use at the proposed location shall not result in
substantial or undue adverse effects on adjacent property.
4. Compatibility: The proposed use shall be compatible with the scale and character of the
neighborhood.
5. Parking: Adequate parking is, or will be made, available.
6. Traffic: The use shall ensure safe movement for vehicles and pedestrians and shall mitigate
potential effects on the surrounding area.
7. Noise, Light and Glare: Potential noise, light and glare impacts from the proposed use shall be
evaluated and mitigated.
8. Landscaping: Landscaping shall be provided in all areas not occupied by buildings, paving, or
critical areas. Additional landscaping may be required to buffer adjacent properties from
potentially adverse effects of the proposed use.
The applicant shall provided justification as to why their project would meet all of the above
review criteria for the requested conditional use permit. In this case, two separate CUPs are
requested, as such the applicant shall provide justification for both CUPs. The justification shall
be provided at formal land use application.
The Site Plan Review and Conditional Use permit application fees are $2,000 each. SEPA
Environmental Review is $1,000. Please note that all land use permits have an additional 3
percent Technology Surcharge Fee. Detailed information regarding the land use application
submittal is provided in the attached handouts.
iAquaponics, PRE12-036
Page 6 of 6
May 17, 2012
h:\ced\planning\current planning\preapps\12-036.vanessa\12-036 (r-14 iaquaponics, slope).doc
In addition to the required land use permits, separate construction, building and sign permits
would be required. The review of these permits may occur concurrently with the review of the
land use permits, but cannot be issued prior to the completion of any appeal periods.
Impact Mitigation Fees: In addition to the applicable building and construction fees, mitigation
fees would be applicable to the site. Impact fees, which would replace mitigation fees, may be
adopted prior to building permit approval for which an applicant may vest to impact/mitigation
fees. Those fees have yet to be determined. Currently fees are the following:
A Transportation Mitigation Fee based on $75.00 per new daily trip attributed to the
development; and
A Fire Mitigation Fee based on $0.52 per square foot of new non-residential area
(excluding structured parking areas).
cc: Jennifer Henning
FIRE & EMERGENCY SERVICES DEPARTMENT
M E M O R A N D U M
DATE:May 3, 2012
TO:Vanessa Dolbee, Senior Planner
FROM:Corey Thomas, Plans Review Inspector
SUBJECT:iAquaponics
1. There are insufficient details in order to determine required changes in
fire flow and fire hydrant requirements for this proposed set of building
changes. Minimum fire hydrant requirements are one hydrant within 150-
feet and one fire hydrant within 300-feet. Existing hydrants can be
counted toward this requirement if they meet current code including 5-
inch storz fittings. It would appear that a requirement to install more fire
hydrants and water mains is likely.
2. Fire mitigation impact fees are currently applicable at the rate of $0.52
per square feet of building area. Credit will be granted for buildings being
removed/replaced.
3. An approved fire sprinkler system is required throughout buildings that
contain restaurant occupancies that exceed 1,500 square feet. Fire
sprinkler systems are also required for all buildings that exceed 5,000
square feet that are new, remodeled or added on to. Separate plans and
permits are required to be submitted to the Renton Fire Department for
review and permitting.
4. An approved fire alarm system is required for all buildings that exceed
3,000 square feet. Systems are required to be fully addressable and full
detection is required. Separate plans and permits are required to be
submitted to the Renton Fire Department for review and permitting.
5. Fire department apparatus access roadways are required to be
minimum 20-feet wide fully paved, with 25-feet inside and 45-feet
outside turning radius. Fire access roadways shall be constructed
to support a 30-ton vehicle with 322-psi point loading. Access is
required within 150-feet of all points on the buildings.
h:\3000 crr\3200 tech svcs\plans review-inspector\preapps\aqua.doc
6. Solar panels are currently required to be installed per the National
Electrical Code. Solar panels will be further regulated by the 2012
International Fire Code beginning on July 1st, 2013.
7. There is an existing aboveground storage tank that is required to
have an annual permit. Is this tank to be retained or others
installed?
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
M E M O R A N D U M
DATE:May 11, 2012
TO:Vanessa Dolbee, Planner
FROM:Arneta Henninger, Plan Review
SUBJECT:AQUAPONICS
13045 RENTON AVE S – Parcel 2144800285
PRE 12-036
NOTE: The applicant is cautioned that information contained in this summary is preliminary and non-
binding and may be subject to modification and/or concurrence by official city decision-makers. Review
comments may also need to be revised based on site planning and other design changes required by
City staff or made by the applicant.
I have completed a preliminary review for the above-referenced project which is the combination of
aquaculture and hydroponics where fish and plants are grown together in one integrated, soils system.
The project also includes a restaurant. The project is located adjacent to and west of Renton Ave S,
north of S 132nd St and south of S 130th St all in the NE ¼ of Sect. 13, 23 N Rng 04 E.
The following comments are based on the pre-application submittal made to the City of Renton by the
applicant.
Water
1. The subject development is within the water service area of the City of Renton and in the 495-water
pressure zone. The site is not in the Aquifer Protection Zone area.
2. There is an existing 8” DI water main in S. 132nd St. See City of Renton water drawing W-0613 for
detailed engineering plans. This 8” main can deliver a maximum of 1700 gpm.
3. The static water pressure at the street level is about 95 psi.
4. Per the City of Renton Fire Marshal, there are insufficient details in the submittal in order to
determine required changes in fire flow and fire hydrant requirements for this proposed set of building
changes. Minimum fire hydrant requirements are one hydrant within 150 feet and one fire hydrant
within 300 feet. Existing hydrants can be counted toward this requirement if they meet current code
including 5-inch storz fittings.
5. Also per the Fire Marshal, an approved fire sprinkler system is required throughout buildings that
contain restaurant occupancies that exceed 1,500 square feet. The project will be required to install a
DDCVA on the fire service line.
Aquaponics – PRE 12-036
Page 2 of 3
May 11, 2012
H:\CED\Planning\Current Planning\PREAPPS\12-036.Vanessa\Plan Review Comments PRE 12-036.doc
6. The development is subject to the City’s water system development charges per Renton Municipal
Code (RMC4-1-180C), based on the size of the meter(s) and the size of the fire sprinkler stub, and also
subject to applicable city plan review and inspection fees. This fee is triggered if the project adds a
water meter or upsizes an existing water meter.
7. Civil plans for water main improvements shall be prepared by a professional engineer registered in
the State of Washington and shall meet the City’s standards.
Sanitary Sewer
(The following comments for sanitary sewer are based on this project being considered a new use.)
1. This site is located in the City of Renton sewer service area.
2. Sanitary sewer is not available in S. 130 St, S. 132nd St, or in Renton Ave S.
3. The project will be required to design and install a sanitary sewer main extension up to and across
the full frontage of the parcel being developed on S. 132nd St, then connecting to the City of Renton
sewer system.
4. Any use in the building subject to oils or grease shall require the installation of a grease interceptor or
oil/water separator as determined at the time of plan review.
5. System Development Charges (SDC) are based on any and all domestic water meters. These fees are
collected at the time a construction permit is issued.
Storm Drainage
1. There are storm drainage conveyance facilities and structures in Renton Ave S.
2. S. 130th St and S. 132nd St appear to have some storm structures, but the City does not have any
detailed records on these.
3. A conceptual drainage plan and report is required to be submitted with the formal application for a
commercial project. The project shall comply with the City of Renton Amendments to the 2009 King
County Surface Water Design.
4. Your civil engineer will look in the manual under Section 1.2.3.1 Area-Specific Flow Control Facility
Requirement. This site is located, per the Flow Control Application Map, in the Flow Control Duration
Standard (Forested Conditions).
5. The Surface Water SDC fees are $0.405 per square foot of new impervious area. These fees are
collected at the time a construction permit is issued.
Street Improvements
1. Construction of a commercial building will trigger a separate review.
2. This project will be required to install an 8’ planter strip and an 8’ sidewalk on the parcel being
developed, along the full frontage of Renton Ave S. The existing curb can remain.
3. Street lighting, per City of Renton standards (to meet the street lighting levels for arterial streets), will
be required to be installed on the parcel being developed, along the full frontage Renton Ave S.
4. All new electrical, phone, and cable services and lines must be undergrounded.
5. Traffic Mitigation Fees may apply.
Aquaponics – PRE 12-036
Page 3 of 3
May 11, 2012
H:\CED\Planning\Current Planning\PREAPPS\12-036.Vanessa\Plan Review Comments PRE 12-036.doc
General Comments
1. All required utility, drainage, and street improvements will require separate plan submittals prepared
according to City of Renton drafting standards by a licensed Civil Engineer.
2. All plans shall be tied to a minimum of two of the City of Renton Horizontal and Vertical Control
Network.
3. Permit application must include an itemized cost estimate for these improvements. Half of the fee
must be paid upon application for building and construction permits, and the remainder when the
permits are issued. There will be additional fees for water service related expenses. See Drafting
Standards.