Construction Mitigation Description
Mitigation Description: Please provide 5 copies of a written narrative addressing each of the
following:
· Proposed construction dates (begin and end dates)
January 2017 Start Garage Shoring and Utility Construction
April 2017 Start Garage Construction
August 2017 Start MOB Construction
September 2017 Complete Garage Construction
October 2018 Complete MOB Shell and Core Construction
· Hours and days of operation
7:00 a.m. - 8:00 p.m. Monday through Friday, 9:00 a.m. - 8:00 p.m. Saturday
· Proposed hauling/transportation routes
To be determined by contractor. We anticipate they will use I-405, Highway 167, South 43rd
Street and Talbot Road South. Early concept is that trucks will be staged onsite.
· Measures to be implemented to minimize dust, traffic and transportation impacts, erosion,
mud, noise, and other noxious characteristics
Temporary erosion control measures will be implemented to reduce this potential. A
temporary erosion and sedimentation control plan has been prepared and will be
implemented.
· Any special hours proposed for construction or hauling (i.e. weekends, late nights)
No special hours anticipated at this time.
· Preliminary traffic control plan
Contractor will provide flaggers on Talbot Road and North Campus driveway as required.
If your project requires the use of cranes, please contact the City’s Airport Manager at (425)
430-7471 to determine whether Federal Aviation Administration notification will be required.