Loading...
HomeMy WebLinkAbout1. Response Letter - City of Renton - Skagen 5 lot short plat/ City of Renton Attention City of Renton, this letter contains all of the comments from the City of Renton regarding Skagen 5 lot short plat for final short plat. The following comments have all been corrected. See responses below as well as all attachments. Engineering Review Comments (ERC): Based on Condition 1 lot 5 is out of compliance per the approved street modification. Driveway turnaround is required Response: Done - Driveway turnaround has been added for lot 5. See Revised short plat (3 of 3) Easements need to be recorded by the City of Renton prior to final recoding of the plat. All easement documents are required to be submitted. Response: Done - Easements ready to be recorded, documented on the face of the plat. As described in the condition documentation Driveways must be installed prior to the recording of the final plat. Response: Done – We have elected to defer the driveway installation for lots 1,2,3,4. See attached deferral. Driveways shall be in a tract Response: Done - Driveways are easements and not tracts. See face of the short plat. All addresses must be shown in the address table Response: Done – All addresses are shown on the address table on the face of the short plat. Provide a blank space for the storm easement documents for the recording number to be written in by the city at time of recording. Response: Done – See attached storm easement document. As builts are required to be submitted and approved. Response: Done – As builts were provided prior to inspection of completed work. Bill of Sale is required to be submitted Response: Done – See attached Bill of Sale. 2 year maintenance bond is required to be submitted. Response: Done – Submitted to Justin on 12/14/2016. Justin to confirm that what was submitted is sufficient. Attach all approved deferrals for the project Response: Done – Submitted to Justin on 12/14/2016 deferral for driveways for lots 1,2,3,4. Justin to confirm approval. Any invoices billed to the project for inspection overtime must be paid in full. Response: N/A – no invoices for inspection overtime. Planning review comments (PRC): Provide an original revised landscaping plan to show/include the required 10 foot landscaping strip along the rear portion of Lot 5 Response: Done – See revised Landscape short plat plan. Provide an easement note on the face of the plat for the required 10 foot landscaping strip along the rear portion of Lot 5. Currently only labeled as “10’ OPEN SPACE ACCESS EASEMENT” on sheet 3. Response: Done – See note on the face of the revised short plat. Update the landscape plan plant schedule to reflect the change in street tree species from Acer saccharum ‘Bonfire’ / Bonfire Sugar Maple to Cercidiphyllum japonicum / Katsura Response: Done – See revised Landscape legend short plat plan. Add assigned addresses for each lot in address table on sheet 1. (Lot 1 19706, Lot 2 19700, Lot 3 19652, Lot 4 19646, and Lot 5 19640). Response: Done – See note on the face of the revised short plat. Technical Service Comments Review completed in electronic format. Please see redlines for comments. Response: Done – See revised short plat plan. Plan – Addressing Review – Planning Committee Add addresses to face of plat. Response: Done – See note on the face of the revised short plat. Thank you for all of your help! Matt Hughes WH Hughes Homes 14401 Issaquah-Hobart Rd SE Issaquah, WA 98027 (425) 395-5599