Re: Construction Mitigation Description
Renton Training Center Expansion
595 Monster Road SW
Renton, WA 98055
Dear Scott:
Site Plan Review Submittal Requirements Response
Item #10:
A) Based on current information of permit turn around, client vetting, approval and funding
durations, we believe the site work would start at the beginning of May 2016 and complete by
the end of July 2016.
B) Our work would be conducted during regular daytime hours and weekday operation, We
anticipate 7am to 5pm, Monday through Friday and are flexible within that time frame to conform
to any typical Renton requirement.
C) Our proposed haul route starting from the site would be Monster Road SW, South to
Oaksdale Ave SW, East to SW Grady Way, South to Rainier Ave S to I-405. However, we also
have the option of heading north on Monster Road SW to 68th Ave S to Martin Luther King Jr
Way to I-5 if that is less impactful in the eyes of a reviewer.
D) As this site work would take place during late spring and summer, we would anticipate
standard wet weather TESC measures for protecting the storm system and at the perimeter site
or property lines, as well as dust control measures for the drier times.
This project is being performed in an already finished and functional industrial property, as such
we have access to dust control water as needed, abundant paved and striped parking areas for
the crew, traffic striping and signage and speed bumps.
The standard daytime workweek schedule means that we are working in safer daylight visibility
hours and during the same time as other normal work activities are taking place at the adjacent
industrial properties. Our added work and hauling traffic will be virtually indistinguishable in type
and frequency from the tractor trailer merchandise loads coming and going at the nearby
distribution center businesses.
Page 2 of 2
We feel fortunate to have amenable neighbors to this type of site work project, but we also will
institute necessary mitigation measures to reduce our impact to them as well as the adjacent
wetlands.
Our preliminary on site traffic control plan is attached.
Should you have any questions or need further clarification, I can be reached directly at 206-
251-7403 or via email at markm@ferris-turney.com.
Mark McGary
Project Manager
Ferris-Turney General Contractors