Re: PPUD Project Sequencing Plan:
Construction will start once all the permits are obtained. The client intends to start construction in the summer
of 2016 and it is anticipated to take approximately one year to build out the site infrastructure. Building
construction will start immediately and it is anticipated that building construction will be completed by summer
2017 with the latest anticipated
The intent is to start clearing and grading as soon as possible in 2016 followed up with site preparation which
would include utilities and any street improvements such as the installation of the new 8 inch sanitary sewer
lines and manholes needed in Grant Avenue along with rough cutting of the drive aisle all having an anticipated
construction schedule of 2‐4 months.
After site work and utilities are completed foundations for all building will start. Buildings will be constructed
starting at the back of the site and working toward Grant Avenue. Foundation excavation, plumbing, electrical
rough in and then formwork and installation of concrete will take approximately 2‐4 months.
Building Framing will start as soon as the first two buildings are ready with all framing being done simultaneously
and in conjunction with foundation work being completed. All rough framing should take approximately 1‐2
months per building and will commence simultaneously with foundation work completion for each building.
Once framing of each building is completed and building envelope has been made water tight then all rough in
plumbing and electrical will begin, insulation installed, then drywall then paint. All of this will be happening
simultaneously with exterior siding and finishes and should take approximately 1‐2 months for each building.
Upon completion of each building final finish grading along with landscaping will commence and both the site
finish work and landscaping will take approximately 1‐2 months respectively.
In all from start of the project meaning clearing and grading to final completion should of the last building
should take anywhere from 12‐18 months.