HomeMy WebLinkAboutTIR-4085coterra
321 3rd Avenue South, Suite 406
Seattle, Washington 98104
206.596.7115
TECHNICAL INFORMATION REPORT
Project: Homestead
Willowcrest Townhomes
Edmonds Ave NE
Renton, WA 98056
Prepared For: Homestead
412 Maynard Ave S #201
Seattle, WA 98104
Prepared By: Max Berde, PE
Reviewed By: Peter Apostol, PE
Date: December 19, 2019
ENGINEERING PLLC
DEVELOPMENT ENGINEERING
Nathan Janders 01/03/2020
SURFACE WATER UTILITY
jfarah 01/03/2020
TABLE OF CONTENTS
Section No. Subject Page No.
SECTION I PROJECT OVERVIEW.....................................................................1
SECTION II CONDITIONS AND REQUIREMENTS SUMMARY...................15
SECTION III OFFSITE ANALYSIS......................................................................19
SECTION IV FLOW CONTROL AND WATER QUALITY
FACILITY ANALYSIS AND DESIGN..........................................23
SECTION V CONVEYANCE SYSTEM ANALYSIS AND DESIGN................27
SECTION VI SPECIAL REPORTS AND STUDIES.............................................27
SECTION VII OTHER PERMITS ...........................................................................27
SECTION VIII EROSION AND SEDIMENT CONTROL ......................................27
SECTION IX BOND QUANTITIES AND
DECLARATION OF COVENANTS...............................................28
SECTION X OPERATIONS AND MAINTENANCE MANUAL.......................28
LIST OF FIGURES
FIGURE 1 VICINITY MAP.................................................................................4
FIGURE 2 TIR WORKSHEET ............................................................................5
FIGURE 3 EXISTING SITE SOILS...................................................................12
FIGURE 4 EXISTING LAND COVER .............................................................13
FIGURE 5 DEVELOPED LAND COVER ........................................................14
FIGURE 6 OFF-SITE DRAINAGE SYSTEM...................................................21
FIGURE 7 WATER QUALITY TREATMENT AREA ....................................27
FIGURE 8 UPSTREAM DRAINAGE AREAS…………….…….APPENDIX G
LIST OF APPENDICIES
APPENDIX A CIVIL PLANS
APPENDIX B FLOW CONTROL/DETENTION CALCULATIONS
APPENDIX C WATER QUALITY CALCULATIONS
APPENDIX D GEOTECHNICAL REPORT
APPENDIX E OPERATIONS AND MAINTENANCE
APPENDIX F BOND QUANTITIES WORKSHEET
APPENDIX G CONVEYANCE CALCULATIONS
APPENDIX H DRAINAGE REVIEW FLOWCHART
Willowcrest Townhomes Project Page 1 Project No. 18011
Renton, WA Coterra Engineering PLLC
SECTION I – PROJECT OVERVIEW
General Description:
The proposed Homestead Willowcrest Townhomes Project includes the construction of
three townhome buildings, consisting of four townhomes each, on a proposed 0.76 acre
lot located off of Edmonds Ave NE in the City of Renton (see Figure 1 for vicinity map).
The site is bordered by developed parcels to the east (RHA Glennwood Townhomes),
Edmonds Ave NE to the west, and developed parcels to the north and south. The site is
proposed to be subdivided for this townhomes project and later developed in Phase 2 by
Renton Housing Authority which would include a new commercial/apartment structure,
extension of the emergency access driveway, and Edmonds Ave NE frontage
improvements. The total area of the project site: the Willow Crest Townhomes
comprising Phase 1; the future RHA Phase 2 lot; and the front improvements total 1.76
acres. The future Phase 2 frontage improvements will include construction of new curb,
gutter, and sidewalk. 270 feet of right-of-way will be dedicated along the site’s frontage
on Edmonds Ave NE. In addition, a City of Renton high pressure 12” water main will be
extended to the project to loops it to Edmonds Ave NE.
The proposed project has been designed to meet the requirements of the 2017 City of
Renton Surface Water Design Manual (SWDM). A summary of the project data is
provided in the TIR worksheet (see Figure 2).
Site Soils:
The NRCS map (see Figure 3) of the site shows “Ragnar-Indianola” soils located within
the project area. Additional information on the site’s soils is provided in a geotechnical
report prepared by GeoEngineers, Inc., and dated Nov 15, 2018. The findings of the
report are based on soil samples taken from test pits that were excavated on-site. In
general, the results of the test pit data uncovered about one foot of topsoil mixed with
loose fill underlain by a 2-3.5 foot thick layer of silty sand that was underlain by
impermeable glacial till soil. For more information, see the geotechnical report included
in Appendix D.
Predeveloped Conditions:
The existing site is undeveloped with vegetation consisting of areas of tall grasses; brush;
and portions of trees covering most of the site and sloping from east to west towards
Edmonds Ave NE. The future Phase 2 development lot consists of vegetation sloping to
the west towards Edmonds Ave NE as well, though historic aerials indicate there was a
single-family home on the lot previously. A steep asphalt driveway accessing Edmonds
Ave NE as well as an existing rockery wall ranging from 5’ to 15’ is still present onsite in
the future Phase 2 property. The limit of work in the current phase as well as the future
Phase 2 lot is located within one Threshold Discharge Area which is defined by the City
of Renton Surface Water Design Manual as:“an onsite area draining to a single natural
discharge location, or multiple natural discharge locations that combine within one-
quarter –mile downstream.”
Willowcrest Townhomes Project Page 2 Project No. 18011
Renton, WA Coterra Engineering PLLC
Existing grades on the project site are generally 3% - 10% with stormwater runoff
draining overland from east to west towards Edmonds Ave NE. On the west margin of
the site, the previously improved street, Edmonds Ave NE, slopes from north to south at
approximately 7% slope along the frontage of the project site.
The existing land coverage of each section of the project site is presented in the table
below. The existing site is presented graphically in Figure 4 which follows this section.
The downstream path of stormwater runoff is described in the offsite analysis in Section
III.
Table 1 – Existing Site Land Coverage (Acres)
Rooftop
(Acres)
Cem.
Conc.
(Acres)
Gravel
(Acres)
ACP
(Acres)
Pervious
(Acres)
Total
(Acres)
Basin A – Project
Site - - - - 0.716 0.716
Developed Conditions:
The area of proposed improvements in Phase 1 include three townhouse buildings –
consisting of four connected townhomes in each building; an access drive with
hammerhead turnaround; residential parking stalls; pedestrian walkways; and associated
storm drainage, utility, and landscape improvements. The following table quantifies the
areas of the proposed land coverage. The proposed site is presented graphically in Figure
5 which follows this section.
Table 2 – Developed Site Land Coverage (Acres)
Rooftop
(Acres)
Cem.
Conc.
(Acres)
Gravel
(Acres)
ACP
(Acres)
Grass/
Landscape
(Acres)
Total
(Acres)
Basin A – Project
Site 0.165 0.045 - 0.242 0.264 0.716
The existing site topography will not be dramatically altered in the proposed condition.
In general, the site will continue to drain from east to west towards the Edmonds Ave NE
right-of-way as it currently does in the existing condition.
Willowcrest Townhomes Project Page 3 Project No. 18011
Renton, WA Coterra Engineering PLLC
The proposed improvements within the project site (Basin A) described above and
delineated in Table 2 trigger both flow control and water quality mitigation per the City
of Renton Surface Water Design Manual.
Stormwater runoff will be collected by roof drains, catch basins, and area drains. Per
Core Requirement #4 of the 2017 City of Renton Surface Water Design Manual, the
proposed conveyance system will be designed to convey runoff resulting from the peak
rates resulting from the 25-year storm event. The proposed flow control facility is a
detention tank located at the west edge of the project site within a Tract, which will
discharge to the existing storm drainage main in Edmonds Ave NE to the west. An
Oldcastle BioPod media filtration vault is proposed to provide water quality treatment for
the proposed improvements in Basin A and will be located downstream of the detention
tank. See Section IV for a detailed description of the design of the flow control and water
quality facilities.
Willowcrest Townhomes Project Page 4 Project No. 18011
Renton, WA Coterra Engineering PLLC
FIGURE 1 – VICINITY MAP
Willowcrest Townhomes Project Page 5 Project No. 18011
Renton, WA Coterra Engineering PLLC
FIGURE 2
CITY OF RENTON
TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
CITY OF RENTON SURFACE WATER DESIGN MANUAL
2017 City of Renton Surface Water Design Manual 12/12/2016 8-A-1
REFERENCE 8-A
TECHNICAL INFORMATION REPORT (TIR)
WORKSHEET
Part 1 PROJECT OWNER AND
PROJECT ENGINEER Part 2 PROJECT LOCATION AND
DESCRIPTION
Project Owner _____________________________
Phone ___________________________________
Address __________________________________
_________________________________________
Project Engineer ___________________________
Company _________________________________
Phone ___________________________________
Project Name __________________________
CED Permit # ________________________
Location Township ________________
Range __________________
Section _________________
Site Address __________________________
_____________________________________
Part 3 TYPE OF PERMIT APPLICATION Part 4 OTHER REVIEWS AND PERMITS
Land Use (e.g., Subdivision / Short Subd.)
Building (e.g., M/F / Commercial / SFR)
Grading
Right-of-Way Use
Other _______________________
DFW HPA
COE 404
DOE Dam Safety
FEMA Floodplain
COE Wetlands
Other ________
Shoreline Management
Structural Rockery/Vault/_____
ESA Section 7
Part 5 PLAN AND REPORT INFORMATION
Technical Information Report Site Improvement Plan (Engr. Plans)
Type of Drainage Review
(check one):
Date (include revision
dates):
Date of Final:
Full
Targeted
Simplified
Large Project
Directed
____________________________________
__________________
Plan Type (check
one):
Date (include revision
dates):
Date of Final:
Full
Modified
Simplified
____________________________________
__________________
HOMESTEAD COMMUNITY LAND TRUST
206-323-1227
412 MAYNARD AVE SOUTH #201
SEATTLE,WA 98104
PETER APOSTOL,PE
COTERRA ENGINEERING,PLLC
206-596-7115
WILLOWCREST TOWNHOMES
23N
5E
9
1132 EDMONDS AVE NE
RENTON,WA 98056
X PPUD
X
X NPDES CONSTRUCTION STORMWATER
X
X
X
X
X
7/29/2019
REFERENCE 8: PLAN REVIEW FORMS AND WORKSHEET
TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
12/12/2016 2017 City of Renton Surface Water Design Manual 8-A-2
Part 6 SWDM ADJUSTMENT APPROVALS
Type (circle one): Standard / Blanket
Description: (include conditions in TIR Section 2)
____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
Approved Adjustment No. ______________________ Date of Approval: _______________________
Part 7 MONITORING REQUIREMENTS
Monitoring Required: Yes / No
Start Date: _______________________
Completion Date: _______________________
Describe: _________________________________
_________________________________________
_________________________________________
Re: SWDM Adjustment No. ________________
Part 8 SITE COMMUNITY AND DRAINAGE BASIN
Community Plan: ____________________________________________________________________
Special District Overlays: ______________________________________________________________
Drainage Basin: _____________________________________________________________________
Stormwater Requirements: _____________________________________________________________
Part 9 ONSITE AND ADJACENT SENSITIVE AREAS
River/Stream ________________________
Lake ______________________________
Wetlands ____________________________
Closed Depression ____________________
Floodplain ___________________________
Other _______________________________
_______________________________
Steep Slope __________________________
Erosion Hazard _______________________
Landslide Hazard ______________________
Coal Mine Hazard ______________________
Seismic Hazard _______________________
Habitat Protection ______________________
_____________________________________
EAST LAKE WASINGTON -RENTON SUB BASIN:JOHNS CREEK
MIN REQUIREMENTS #1 -#9;ENHANCED BASIN WQ TREATMENT
RENTON
MANUFACTURER (OLDCASTLE)IS APPLYING FOR BLANKET ADJUSTMENT REQUEST FOR USE OF OLDCASTLE
BIOPOD FOR ENHANCED WATER QUALITY TREATMENT.
REFERENCE 8-A: TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
2017 City of Renton Surface Water Design Manual 12/12/2016 Ref 8-A-3
Part 10 SOILS
Soil Type
______________________
______________________
______________________
______________________
Slopes
________________________
________________________
________________________
________________________
Erosion Potential
_________________________
_________________________
_________________________
_________________________
High Groundwater Table (within 5 feet)
Other ________________________________
Sole Source Aquifer
Seeps/Springs
Additional Sheets Attached
Part 11 DRAINAGE DESIGN LIMITATIONS
REFERENCE
Core 2 – Offsite Analysis_________________
Sensitive/Critical Areas__________________
SEPA________________________________
LID Infeasibility________________________
Other________________________________
_____________________________________
LIMITATION / SITE CONSTRAINT
_______________________________________
_______________________________________
_______________________________________
_______________________________________
_______________________________________
_______________________________________
Additional Sheets Attached
Part 12 TIR SUMMARY SHEET (provide one TIR Summary Sheet
per Threshold Discharge Area)
Threshold Discharge Area:
(name or description)
Core Requirements (all 8 apply):
Discharge at Natural Location Number of Natural Discharge Locations:
Offsite Analysis Level: 1 / 2 / 3 dated:__________________
Flow Control (include facility
summary sheet)
Standard: _______________________________
or Exemption Number: ____________
On-site BMPs: _______________________________
Conveyance System Spill containment located at: _____________________________
Erosion and Sediment Control /
Construction Stormwater Pollution
Prevention
CSWPP/CESCL/ESC Site Supervisor: _____________________
Contact Phone: _________________________
After Hours Phone: _________________________
RdC -RAGNAR-INDIANOLA 2%-15%LOW
EDMONDS AVE NE (ALL ONSITE AREAS INCLUDING EX GLENNWOOD
TOWNHOMES AND PROPOSED ROW IMPROVEMENTS)
CORE REQUIREMENTS #1 -#9
1
PEAK RATE FLOW CONTROL STANDARD
REQUIRED MEF PER CORE REQUIREMENT #9
TBD
TBD
X STEEP SLOPE
REFERENCE 8: PLAN REVIEW FORMS AND WORKSHEET
TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
12/12/2016 2017 City of Renton Surface Water Design Manual 8-A-4
Part 12 TIR SUMMARY SHEET (provide one TIR Summary Sheet
per Threshold Discharge Area)
Maintenance and Operation Responsibility (circle one): Private / Public
If Private, Maintenance Log Required: Yes / No
Financial Guarantees and Liability Provided: Yes / No
Water Quality (include facility
summary sheet)
Type (circle one): Basic / Sens. Lake / Enhanced Basic / Bog
or Exemption No. _______________________
Special Requirements (as applicable):
Area Specific Drainage
Requirements
Type: SDO / MDP / BP / Shared Fac. / None
Name: ________________________
Floodplain/Floodway Delineation Type (circle one): Major / Minor / Exemption / None
100-year Base Flood Elevation (or range): _______________
Datum:
Flood Protection Facilities Describe:
Source Control
(commercial / industrial land use)
Describe land use:
Describe any structural controls:
Oil Control High-Use Site: Yes / No
Treatment BMP: _________________________________
Maintenance Agreement: Yes / No
with whom? _____________________________________
Other Drainage Structures
Describe:
MULTI-FAMILY
STORMWATER DETENTION VAULT
DETENTION FACILITY
REFERENCE 8-A: TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
2017 City of Renton Surface Water Design Manual 12/12/2016 Ref 8-A-5
Part 13 EROSION AND SEDIMENT CONTROL REQUIREMENTS
MINIMUM ESC REQUIREMENTS
DURING CONSTRUCTION
Clearing Limits
Cover Measures
Perimeter Protection
Traffic Area Stabilization
Sediment Retention
Surface Water Collection
Dewatering Control
Dust Control
Flow Control
Control Pollutants
Protect Existing and Proposed BMPs/Facilities
Maintain Protective BMPs / Manage Project
MINIMUM ESC REQUIREMENTS
AFTER CONSTRUCTION
Stabilize exposed surfaces
Remove and restore Temporary ESC Facilities
Clean and remove all silt and debris, ensure operation of Permanent BMPs/Facilities, restore
operation of BMPs/Facilities as necessary
Flag limits of sensitive areas and open space
preservation areas
Other _______________________
Part 14 STORMWATER FACILITY DESCRIPTIONS (Note: Include Facility Summary and Sketch)
Flow Control Type/Description Water Quality Type/Description
Detention
Infiltration
Regional Facility
Shared Facility
On-site BMPs
Other
________________
________________
________________
________________
________________
________________
Vegetated Flowpath
Wetpool
Filtration
Oil Control
Spill Control
On-site BMPs
Other
________________
________________
________________
________________
________________
________________
________________
Part 15 EASEMENTS/TRACTS Part 16 STRUCTURAL ANALYSIS
Drainage Easement
Covenant
Native Growth Protection Covenant
Tract
Other ____________________________
Cast in Place Vault
Retaining Wall
Rockery > 4′ High
Structural on Steep Slope
Other _______________________________
X
X
X
X
XX
X
X
X
X
X
X
X DETENTION TANK
X
X BIOPOD
X
X
REFERENCE 8: PLAN REVIEW FORMS AND WORKSHEET
TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
12/12/2016 2017 City of Renton Surface Water Design Manual 8-A-6
Part 17 SIGNATURE OF PROFESSIONAL ENGINEER
I, or a civil engineer under my supervision, have visited the site. Actual site conditions as observed were incorporated into this worksheet and the attached Technical Information Report. To the best of my
knowledge the information provided here is accurate.
____________________________________________________________________________________ Signed/Date
12/18/2019
Willowcrest Townhomes Project Page 12 Project No. 18011
Renton, WA Coterra Engineering PLLC
FIGURE 3 – EXISTING SITE SOIL CONDITIONS
coterra
321 3rd Avenue South, Suite 406Seattle, Washington 98104206.596.7115 coterraengineering.com
ENGINEERING PLLC
coterra321 3rd Avenue South, Suite 406Seattle, Washington 98104206.596.7115 coterraengineering.comENGINEERING PLLC
Willowcrest Townhomes Project Page 15 Project No. 18011
Renton, WA Coterra Engineering PLLC
SECTION II – CONDITIONS AND REQUIREMENTS SUMMARY
The proposed project is subject to a Full Drainage Review per the 2017 City of Renton
Surface Water Design Manual and is therefore subject to all nine core requirements and
all six special requirements. These requirements are listed below along with a discussion
of their applicability to this project. See Appendix H for drainage review type flow chart.
Core Requirements:
Req. #1 Discharge at Natural Location:
Existing discharge locations will be maintained.
Req. #2 Offsite Analysis:
See Section III below.
Req. #3 Flow Control:
The project is required to meet the Peak Rate Flow Control Standard.
The proposed improvements within Phase 1 exceed the threshold of 5,000 sf of
new and replaced impervious surface, therefore triggering the requirement of a
flow control facility and on-site flow control BMPs.
A detention tank is proposed to meet the Peak Rate Flow Control Standard
requirement. Onsite BMPs are also required as part of the project and are
discussed below in Core Requirement #9.
For further details see Section IV.
Req. #4 Conveyance System:
The new conveyance system has been designed to meet and exceed the
requirement to convey the 25-year peak flow from the developed site conditions.
Req. #5 Erosion and Sediment Control:
Construction erosion and sediment control systems shall be implemented per the
Temporary Erosion and Sediment Control plan.
Willowcrest Townhomes Project Page 16 Project No. 18011
Renton, WA Coterra Engineering PLLC
Req. #6 Maintenance and Operations:
A Declaration of Covenant is required for this project and will be submitted for
review by City of Renton staff before recording. The proposed facilities will be
owned and maintained by Homestead.
Req. #7 Financial Guarantees:
A financial guarantee will be necessary for this project. Bonding will be required
for the construction of improvements and will be obtained prior to construction.
Req. #8 Water Quality:
The proposed improvements located on the project site exceed 5,000 sf of new
and replaced Pollution-Generating Impervious Surface (PGIS), therefore
triggering the requirement of a water quality facility.
Based on the proposed site usage, multi-family housing, Enhanced Basic Water
Quality treatment is required per Core Requirement #8 of the 2017 City of Renton
Surface Water Design Manual for targeted PGIS.
An Oldcastle BioPod media filtration vault is proposed to meet the requirements
of the Enhanced Basic Water Quality requirement within the SWDM.
For further details see Section IV.
Req. #9 On-Site BMPs:
The proposed improvements exceed the threshold of 5,000 sf of new and replaced
impervious surface, therefore triggering the requirements of Core Requirement #9
to implement on-site flow control facilities to the maximum extent feasible.
Following the City of Renton SWDM required list method for implementing on-
site BMPs to comply with Core Requirement #9, all listed BMPs were determined
to be infeasibly for Phase 1 of the proposed project site.
Despite infeasibility determinations for listed on-site BMP facilities, the proposed
project plans to implement perforated pipe on all roof drain connections from the
three proposed townhouse buildings per the recommendation of the City of
Renton SWDM.
Willowcrest Townhomes Project Page 17 Project No. 18011
Renton, WA Coterra Engineering PLLC
Additionally, the project will implement compost-amended topsoil per SWDM
requirement for all new and replaced landscape areas to aid surface water
drainage.
For further details see Section IV.
Special Requirements:
Req. #1 Area Specific Requirements:
No area specific requirements are applicable to this project.
Req. #2: Floodplain/Floodway Delineation
This project is not adjacent to any floodplains or floodways. Therefore no
delineation is necessary.
Req. #3 Flood Protection Facilities:
This project is not adjacent to any applicable areas and will not affect any
applicable facility.
Req. #4 Source Controls:
This project is a multi-family project and will provide appropriate source controls.
Req. #5 Oil Control:
No oil control requirements are applicable to this project.
Req. #6 Aquifer Protection Area
The proposed project is within Zone 2 of the APA. The contractor will be
required to obtain imported fill material from a Washington Department of
Transportation approved source. There are no open flow control or water quality
facilities which will introduce stormwater to ground water given the project soil
conditions.
Willowcrest Townhomes Project Page 18 Project No. 18011
Renton, WA Coterra Engineering PLLC
SECTION III – OFFSITE ANALYSIS
Task 1 – Study Area Definition and Maps
Maps of the project site and surrounding area were obtained from the King County GIS
website. Topographical site information is from the topographical survey for the project.
Storm drainage system maps were compiled from City of Renton GIS maps and as-built
plans. Aerial images were obtained from Google Earth.
Task 2 – Resource Review
The City of Renton Public Works Department was contacted regarding the resources
listed in section 2.3.1.1 of the 2017 City of Renton Surface Water Design Manual. The
following is a summary of the resource review:
Adopted Basin Plans
o King County Basin Name: East Lake Washington (per King County
iMap)
Basin Reconnaissance Summary Reports
o None completed to our knowledge.
Floodplain/Floodway (FEMA) Maps
o The site is not within a floodplain or floodway per FEMA mapping.
Other Offsite Analysis Reports
o Other Offsite Analysis Reports were not available.
Environmentally Sensitive Areas Map
o There are no Environmentally Sensitive areas mapped within the vicinity
of the site.
USDA Soils Survey
o A geotech report has been completed and site soils are primarily silty sand
that was underlain by impermeable glacial till soil.
Wetlands Inventory Maps
o There are no Wetlands mapped within the vicinity of the site.
Downstream Water Quality Problems Requiring Special Attention
o Per Section 1.2.2.1.2 of the SWDM, possible downstream water quality
issues that have been identified by the local, state, or federal jurisdiction
must be reviewed as part of the Downstream Analysis.
Per the EPA’s Clean Water Act, states must identify impaired waterways
and identify the pollutants causing impairment. These waterways or
waterbodies are listed on what is known as the 303(d) list. The eventual
downstream conveyance system for the proposed project site is John’s
Willowcrest Townhomes Project Page 19 Project No. 18011
Renton, WA Coterra Engineering PLLC
Creek, which outfalls into Lake Washington. The last reaches of John’s
Creek are identified by the Washington State Department of Ecology as
303(d) impacted based on the following parameters which are identified as
Category 5, which lists the waterbody on the 303(d) list:
-Bacteria
-Temperature
-Dissolved Oxygen
The portions of John’s Creek which are identified as 303(d) impacted
waterways at the final reaches of John’s Creek as it outfalls to Lake
Washington. These sections are beyond ¼ mile from the piped-
conveyance system which the proposed project site discharges to in
Edmonds Ave NE.
o Per Section 1.2.2.3 of the SWDM, based on the criteria listed above for
the 303(d) listed waterway(s) for the downstream conveyance from the
project site, the following mitigation measures must be considered as part
of the proposed project:
-Bacteria
The proposed project does not drain to a bacteria problem
located within one quarter mile/15% distance downstream
from the site discharge point; therefore no further
mitigation measures are required beyond Core
Requirements #1 - #9 and Special Requirements #1 - #6
from the 2017 City of Renton Surface Water Design
Manual. The location of the impacted 303(d) waterway was
determined from Washington State DOE’s online Water
Quality Atlas Mapping system.
-Temperature
The proposed project does not drain to a temperature
problem located within one quarter mile/15% distance
downstream from the site discharge point; therefore no
further mitigation measures are required beyond Core
Requirements #1 - #9 and Special Requirements #1 - #6
from the 2017 City of Renton Surface Water Design
Manual. The location of the impacted 303(d) waterway was
determined from Washington State DOE’s online Water
Quality Atlas Mapping system.
-Dissolved Oxygen
The proposed project does not drain to a Dissolved Oxygen
problem located within one quarter mile/15% distance
downstream from the site discharge point; therefore no
further mitigation measures are required beyond Core
Willowcrest Townhomes Project Page 20 Project No. 18011
Renton, WA Coterra Engineering PLLC
Requirements #1 - #9 and Special Requirements #1 - #6
from the 2017 City of Renton Surface Water Design
Manual. The location of the impacted 303(d) waterway was
determined from Washington State DOE’s online Water
Quality Atlas Mapping system.
Task 3 – Field Inspection
A Level 1 downstream analysis was performed on 12/18/2018. Weather conditions
during the downstream analysis consisted of overcast skies. Periodic rainfall occurred in
the week prior to the analysis.
On-site landuse and topography was confirmed, and the downstream conveyance was
identified. This section is complemented by the information found in Figure 6 and the
Off-site Analysis Drainage System Table which follow this section.
Stormwater runoff originating from the project site sheet flows to the west across the
adjacent undeveloped parcel which is primarily vacant and heavily vegetated. Grades
within this parcel slope to the west at approximately 10%-15%. Sheet flow patterns
persist in a westerly direction until flowing onto Edmonds Ave NE. A piped conveyance
system in Edmonds Ave NE collects runoff from the project site and conveys flows to the
south. Due to heavy traffic conditions, the piped conveyance system was not inspected.
Based on review of City of Renton GIS Utility Mapping, the piped conveyance continues
to the south in Edmonds Ave NE to NE Sunset Blvd, where larger diameter conveyance
piping flows west towards Lake Washington beyond ¼ mile downstream from the site.
No open drainage complaints are associated with the downstream conveyance system.
Task 4 – Drainage System Description and Problem Description
There are no known problems with the downstream system.
Task 5 – Mitigation of Existing or Potential Problems
Based on the observations made during the field inspection and the requirements for the
design of the proposed drainage systems, no negative impacts to the systems downstream
of the project site are anticipated.
Existing Upslope Drainage Areas
Portions of the adjacent property to the east – the previously developed Glennwood
Townhomes drain to the west based on topography to the proposed Phase 1 project site.
The areas of the adjacent off-site, upstream area that drains to the Willowcrest site are
fully-established pervious landscape areas or previously undeveloped pervious areas.
Based on on-site observations during the Offsite Analysis, no upstream run-on was
observed. Based on current landcover, site layout, and grading, minimal offsite run-on is
expected onto the Willowcrest site.
Willowcrest Townhomes Project Page 21 Project No. 18011
Renton, WA Coterra Engineering PLLC
To mitigate any upstream overland or subsurface run-on, a perforated interreceptor storm
drain line is proposed at the eastern project margin of the Phase 1 property to collect any
upstream flows from the Glennwood Townhomes site and route it around the proposed
project improvements on the Willowcrest site. The proposed upstream drainage
collection system – consisting of a French drain – and tightline routing is intended to
maintain the existing drainage patterns of any upstream runoff from the adjacent property
and convey it to the existing municipal storm drainage system in Edmonds Ave NE.
18"SD18"SD24"SD24"SD24"SD30"SD30"SD36"SD36"SD36"SD36"SD36"SD36"SDCB(TYP)PROJECTSITESHALLOWCONCENTRATEDSURFACEFLOWPIPEDCONVEYANCECATCHBASINDIRECTIONOFFLOWINDICATEDBYARROWSHEETFLOWcoterra
321 3rd Avenue South, Suite 406Seattle, Washington 98104206.596.7115 coterraengineering.com
ENGINEERING PLLC
1/1/05 OFF-SITE ANALYSIS DRAINAGE SYSTEM TABLE SURFACE WATER DESIGN MANUAL, CORE REQUIREMENT #2 Basin: Subbasin Name: Subbasin Number: Symbol Drainage Component Type, Name, and Size Drainage Component Description Slope Distance from site discharge Existing Problems Potential Problems Observations of field inspector, resource reviewer, or resident see map Type: sheet flow, swale, stream, channel, pipe, pond; Size: diameter, surface area drainage basin, vegetation, cover, depth, type of sensitive area, volume % ¼ ml = 1,320 ft. constrictions, under capacity, ponding, overtopping, flooding, habitat or organism destruction, scouring, bank sloughing, sedimentation, incision, other erosion tributary area, likelihood of problem, overflow pathways, potential impacts East Lake Washington 2.12.2SheetFlowPipedConveyanceRunofffromSite10%-15%2%-10%0ft-325ft325ft-1/4miNoneobservedorreportedNoneobservedNoneobservedPipedconveyancesystemwasnotabletobeobservedduetoheavytrafficconditions.Observationwouldrequireimplementationoftrafficcontrol.PipedconveyanceandstructuresshownonFigure6arebasedonCityofRentonGISUtilityMapping.Therearenodrainagecomplaintsassociatedwiththisconveyanceline.RunofffromSiteNoneobservedorreported
Willowcrest Townhomes Project Page 24 Project No. 18011
Renton, WA Coterra Engineering PLLC
SECTION IV – FLOW CONTROL AND WATER QUALITY FACILITY
ANALYSIS AND DESIGN
Flow Control
The project site is located in a Peak Flow Control Standard area per the 2017 City of
Renton Surface Water Design Manual. This standard requires that the developed site
discharge rates match the existing site conditions discharge rates for the 2-, 10-, and 100-
year return periods. The proposed improvements will create more than 2,000 SF of new
plus replaced imperious surfaces, therefore the project is required to meet the flow
control standard and implement on-site flow control BMPs. Based on the engineer’s on-
site visits to the proposed property and analysis of current aerial photography, the
existing site conditions within the Phase 1 project site (Basin A) is assumed to be 25%
forested land cover and 75% pasture land cover.
MGS Flood stormwater modeling program – utilizing a continuous hydrologic model –
was implemented to size a detention facility which matched the existing site discharge
rates for the 2-, 10-, and 100-year return events. At this preliminary stage of design, a
detention vault was sized in MGS Flood to meet the flow control requirement. As the
project stormwater design is refined, the type of detention structure on the project may be
revised.
Based on the MGS Flood analysis, a detention tank was sized to detain Basin A of the
proposed project. The proposed detention volume is 3,731 cubic feet. The MGS Flood
calculations are included in Appendix B of this report. The proposed detention tank was
designed per the City of Renton SWDM requirements including 0.5’ sediment storage
(dead storage). Sizing details are shown on the Storm Drainage Plan, sheet 4.0 of the civil
plan set, as well as the civil details.
On-Site Flow Control BMPs
The proposed site is classified as a Small Subdivision Project. Implementation of On-
Site Flow Control BMPs is therefore required per Core Requirement #9.
On-site BMPs are evaluated for targeted surfaces, per the list from section 1.2.9.3.1 for
Small Subdivision Projects in the 2017 City of Renton Surface Water Design Manual.
Analysis of feasibility of the on-site BMPs from the SWDM list follow in order per
SWDM feasibility determination instructions.
Full Dispersion: Infeasible. Per on-site BMP infeasibility criteria in section C.2.1.1,
the total area of impervious surfaces plus non-native pervious surfaces on the project
site exceed 35% of the total site area.
Full Infiltration: Infeasible. Per criteria outlined in section 5.2 of the SWDM, in order
for infiltration to be implemented on a site, “The applicant must demonstrate through
infiltration testing, soil logs, and the written opinion of a geotechnical professional
that sufficient permeable soil exists at the proposed facility location to allow
construction of a properly functioning infiltration facility.” Per the SWDM, the
Willowcrest Townhomes Project Page 25 Project No. 18011
Renton, WA Coterra Engineering PLLC
geotechnical engineer shall obtain soil logs for possible infiltration system locations
on the proposed site. Soils collected in on-site test pits per Geotechnical Engineering
Services report prepared by GeoEngineers, Inc., dated 11/15/2018, are classified as
“SM” or “silty sands, sand – silt mixtures” at the depth of typical on-site infiltration
facilities or infiltration BMPs. The report continues, “Based on our analysis, it is our
opinion that the on-site native glacial till soils have a very low infiltration capacity.”
And finally they conclude, “Due to the density, high fines content, and relative
impermeability of the glacial till, infiltration should be assumed to be very low when
designing infiltration systems.” Based on the geotechnical engineer analysis of the
existing site soils, full infiltration is not feasible.
Bioretention: Infeasible. Bioretention is considered infeasible for projects that cannot
meet the minimum design requirements for bioretention. Per section C2.6,
bioretention facilities receiving runoff from impervious areas over 10,000 square feet
must follow setback requirements of Infiltration Ponds as outlined in section 5.2.2.1.
Per section 5.2.2.1, “The toe of the exterior slope of an infiltration pond berm
embankment shall be set back 5 feet from the tract, easement, or property line.”
Based on the currently proposed site design, a bioretention facility cannot be feasibly
located on the proposed Willow Crest Townhomes property with the required setback
requirements from both proposed structures and tract, easement, and property lines.
Additionally, per section C2.6, bioretention facilities are infeasible on slopes greater
than 8%. Based on the proposed grading of the project site and the adjacent RHA site,
it is infeasible to locate bioretention facilities on the proposed site.
Permeable Pavement: Infeasible. Per section C2.7, permeable pavement shall not be
installed on slopes steeper than 5% for porous asphaltic concrete. Project proposes
asphalt paving for access drives. Based on existing topography and proposed site
layout, majority of access drive grades exceed 5%. Proposed areas of grading less
than 5% in access drive would exceed maximum run-on limit ratio for PGIS of 2:1.
Limited Infiltration: Per SWDM section 1.2.9.2.2, which then references section
C.2.3 for feasibility of Limited Infiltration, “Where geotechnical evaluation and
approval is required for limited infiltration that proposes to discharge towards or is
within described setbacks of a steep slope hazard area, erosion hazard area, landslide
hazard, or slopes greater than 15%, limited infiltration is considered infeasible and
not required.” Existing and proposed grades down gradient from proposed project site
exceed 15% grade; therefore, limited infiltration is infeasible.
Basic Dispersion:
o Splash blocks: Infeasible. Required 50’ vegetated flow path is infeasible
based on proposed site design.
o Rock pads: Infeasible. Required 50’ vegetated flow path is infeasible
based on proposed site design.
o Gravel-filled trenches: Infeasible. Per section C.2.4.4, setbacks of at least
10’ from buildings and 5’ from property line are required. Proposed site
layout cannot accommodate 25’ flowpath with required setbacks.
o Sheet flow: Infeasible. Required 10’ vegetated flow path located on the
project property is infeasible based on proposed site design.
Willowcrest Townhomes Project Page 26 Project No. 18011
Renton, WA Coterra Engineering PLLC
Other BMPs: Per criteria set forth in section 1.2.9.2.2 of the SWDM, for projects that
will result in an impervious surface coverage 45-65% on the buildable portion of the
site/lot, on-site BMPs must be applied to 50% of target impervious surfaces reduced
by 1.5% for each 1% of impervious surface coverage above 45%.
The proposed project site developed condition consists of 63% impervious surfaces.
Based on the above formula, 23% of the site’s targeted impervious surfaces must be
mitigated by onsite BMPs (63%-45%=18%; 18*1.5=27; 50%-27%=23%). Of the
19,689 SF of new impervious surfaces, 4,528 SF are required by the SWDM to be
mitigated by onsite BMPs.
When the previously listed onsite stormwater BMPs are not feasible, projects shall
evaluate the implementation of the following BMPs:
o Reduced Impervious Surface Credit: Currently proposed townhome
footprints total 20% of proposed Phase I lot. Townhomes have been
designed to maximize building lot area for the benefit of providing
maximum number of housing units allowed by zoning on this site.
Reduced Impervious Surface Credit would decrease size of proposed
townhomes and limit the project goals of providing as much low-income
housing as possible with the highest site density. To meet BMP area
target, proposed townhomes would need to decrease by over 50% of
proposed footprint. This is infeasible for this project.
o Native Growth Retention Credit: This BMP credit requires retention of
existing forested portions of the site at a 3.5 to 1 ratio for credit. To meet
BMP target goal, 15,850 SF of site area would need to be retained as
native growth. That is over one third of proposed site area and would not
make development of site possible to the desired density to meet project
goal of providing maximum number of low-incoming housing units.
Additionally, this BMP is feasible due to, “The donor area must not slope
more than 15%.” – existing and proposed onsite grades exceed 15%.
o Tree Retention Credit: 4 Significant Trees are proposed to be retained as
part of the proposed project to meet land use code requirements. These
trees are shown on the Tree Retention Plan within the landscape plans. To
meet the onsite BMP area target (tree retention credit can only account for
up to 25% of required target mitigation area), 11,320 SF of deciduous tree
canopy or 5,660 SF of evergreen tree canopy would need to be retained on
the project site and within 20’ of ground-level hardscape. Based on
proposed site layout to maximize housing units, it is infeasible to meet the
onsite BMP target mitigation area requirement with tree retention.
Soil Amendment: Feasible. New and replaced pervious surfaces within the project
limits will implement soil amendment per the soil quality and depth requirements of
section C2.13. Soil amendment will be implemented in all onsite disturbed areas
Willowcrest Townhomes Project Page 27 Project No. 18011
Renton, WA Coterra Engineering PLLC
which will be landscape area in the developed condition. See Landscape sheet 3.01
for additional details.
Despite infeasibility for listed on-site BMPs per the SWDM criteria, perforated pipe
connections from roof drain leaders from each of the three proposed buildings, upstream
of detention, are proposed. These perforated pipe connections are shown on the current
Utility Plan.
From the initial geotechnical investigation, it was determined that the subsurface soils on
the project site are composed of several feet of fill soil laying over glacial till which
inhibits any practical infiltration potential for possible stormwater mitigation on the
project site. Therefore, the use of large-scale infiltrative flow control facilities and on-site
BMPs are not shown on the current preliminary plans.
Willowcrest Townhomes Project Page 28 Project No. 18011
Renton, WA Coterra Engineering PLLC
Water Quality
The proposed new and replaced pollution-generating impervious surfaces (PGIS) on the
project site trigger the requirement for water quality treatment of targeted surfaces. Per
the City of Renton SWDM, the project site is within the Basin Water Quality Area; but
the proposed site land use of multi-family housing triggers the Enhanced Basic Water
Quality Menu.
The proposed project will provide treatment of targeted PGIS as outlined by the
Enhanced Basic Water Quality Menu. This will be provided by an Oldcastle BioPod
media filtration vault, sized using MGS Flood software to treat the full 2 year release rate
from the detention tank. The detention tank and onsite storm drainage system has been
designed to capture all new proposed impervious surfaces for the project. As a result, all
targeted PGIS and non-targeted new impervious surfaces are routed through the water
quality facility – including building roofs. No stormwater covenants are required for
roofing materials as water quality treatment is provided for these surfaces by the
proposed facility. Sizing calculations are provided in Appendix C.
Willowcrest Townhomes Project Page 29 Project No. 18011
Renton, WA Coterra Engineering PLLC
SECTION V – CONVEYANCE SYSTEM DESIGN AND ANALYSIS
The new conveyance system has been designed to convey, per SWDM requirements, at
least the 25-year peak flow rate from the developed site. Conveyance capacity
calculations are included in Appendix G which show that onsite conveyance can
accommodate the 100-year peak flow for the full developed site in addition to upstream
tributary area.
SECTION VI – SPECIAL REPORTS AND STUDIES
A geotechnical analysis of the project site was performed and is included in Appendix D.
Additionally, specifications are provided by manufacturer to show that the proposed
detention tank can accommodate at least H-20 loading per City of Renton comments.
SECTION VII – OTHER PERMITS
In addition to the PPUD permit, a Civil Construction Permit from the City of Renton is
required, as well as an NPDES permit from the Washington State DOE for the discharge
of construction stormwater from the project site.
SECTION VIII – EROSION AND SEDIMENT CONTROL
ESC Measures are being addressed as follows:
Clearing Limits: Clearing limits are being delineated by perimeter silt fencing and
chain link fencing.
Cover Measures: Temporary cover shall be installed if an area is to remain
unworked for more than seven days during the dry season (May 1 to September
30) or for more than two consecutive working days during the wet season
(October 1 to April 30). Any area to remain unworked for more than 30 days shall
be seeded or sodded, unless the City of Renton determines that winter weather
makes vegetation establishment infeasible.
Perimeter Protection: Perimeter protection will be implemented by silt fencing
around the site perimeter where drainage paths require.
Traffic Area Stabilization: A stabilized construction entrance will be built for
construction traffic.
Sediment Retention: Catch basin protection has been provided and is shown on
the projects TESC plans.
Surface Water Control: Surface water will be collected and conveyed via swales
with check dams as necessary.
Willowcrest Townhomes Project Page 30 Project No. 18011
Renton, WA Coterra Engineering PLLC
Dust Control: Dust control, if required, will be provided through the limited use
of water trucks.
Willowcrest Townhomes Project Page 31 Project No. 18011
Renton, WA Coterra Engineering PLLC
SECTION IX – BOND QUANTITIES AND DECLARATION OF COVENANTS
A bond quantity worksheet for the proposed improvements is included with this
submittal.
There are two Declaration of Covenants which are required for the proposed project; one
for inspection and maintenance of proposed stormwater facilities; and one for the
inspection and maintenance of the proposed on-site BMPs. A draft version of these
required covenants are provided as one document as allowed by the City of Renton.
Covenant be signed and notarized prior to recording. Covenant provided under separate
cover.
SECTION X – OPERATIONS AND MAINTENANCE MANUAL
Operation and maintenance of the proposed BioPod system is provided in this submittal.
The maintenance of the stormwater facilities will by be performed by Homestead.
Appendix A
Civil Plans
Appendix B
Flow Control/Detention Calculations
Detention Pipe Volume Calculator
Blue Indicates Data Entry Cells, the rest are calculated.
Storage Volume Provided by Horizontal Pipe of Diameter d
Pipe Diameter (d)5.0 ft
Pipe Length 190 ft
Overflow Elevation:325.00 ft
Pond Volume at Overflow (cu ft):3731
Target Volume from MGSFlood: 700
Note: Volume is increased by 1 for Elevations Greater than Pipe Diameter
Pond Volume Table Because Routing Routine Requires Increasing Pond Volume
Circular Section Geometry Read from CircularSections Tab *** Copy Table below to MGSFlood Program Elevation Volume Input Screen
elev. Wetted Area storage storage DON'T INCLUDE THE COLUMN HEADINGS!
ft y/d s.f. cu.ft. (ac.ft) ELEV (FT) Top Area (Dummy) VOLUME (CU FT)
320.00 0.000 0.000 0 0 320.00 10.0 0.0.
320.20 0.040 0.263 50 0.001 320.20 10.1 49.9.
320.40 0.080 0.735 140 0.003 320.40 10.2 139.7.
320.60 0.120 1.335 254 0.006 320.60 10.3 253.7.
320.80 0.160 2.028 385 0.009 320.80 10.4 385.2.
321.00 0.200 2.795 531 0.012 321.00 10.5 531.1.
321.20 0.240 3.623 688 0.016 321.20 10.6 688.3.
321.40 0.280 4.500 855 0.020 321.40 10.7 855.0.
321.60 0.320 5.418 1029 0.024 321.60 10.8 1029.3.
321.80 0.360 6.365 1209 0.028 321.80 10.9 1209.4.
322.00 0.400 7.335 1394 0.032 322.00 11.0 1393.7.
322.20 0.440 8.320 1581 0.036 322.20 11.1 1580.8.
322.40 0.480 9.318 1770 0.041 322.40 11.2 1770.3.
322.60 0.520 10.318 1960 0.045 322.60 11.3 1960.3.
322.80 0.560 11.315 2150 0.049 322.80 11.4 2149.9.
323.00 0.600 12.300 2337 0.054 323.00 11.5 2337.0.
323.20 0.640 13.270 2521 0.058 323.20 11.6 2521.3.
323.40 0.680 14.218 2701 0.062 323.40 11.7 2701.3.
323.60 0.720 15.135 2876 0.066 323.60 11.8 2875.7.
323.80 0.760 16.010 3042 0.070 323.80 11.9 3041.9.
324.00 0.800 16.840 3200 0.073 324.00 12.0 3199.6.
324.20 0.840 17.608 3345 0.077 324.20 12.1 3345.4.
324.40 0.880 18.300 3477 0.080 324.40 12.2 3477.0.
324.60 0.920 18.900 3591 0.082 324.60 12.3 3591.0.
324.80 0.960 19.373 3681 0.084 324.80 12.4 3680.8.
325.00 1.000 19.635 3731 0.086 325.00 12.5 3730.7.
325.20 1.040 19.635 3731 0.086 325.20 12.6 3731.7.
325.40 1.080 19.635 3731 0.086 325.40 12.7 3732.7.
325.60 1.120 19.635 3731 0.086 325.60 12.8 3733.7.
325.80 1.160 19.635 3731 0.086 325.80 12.9 3734.7.
326.00 1.200 19.635 3731 0.086 326.00 13.0 3735.7.
7/29/2019 PondPipe.xls
—————————————————————————————————
MGS FLOOD
PROJECT REPORT
Program Version: MGSFlood 4.38
Program License Number: 201510001
Project Simulation Performed on: 06/14/2019 10:01 AM
Report Generation Date: 06/20/2019 12:36 PM
—————————————————————————————————
Input File Name: Willowcrest - Civil Permit Sizing - Basin A - Tank.fld
Project Name: Renton Homestead
Analysis Title: Peak Flow - Detention
Comments:
———————————————— PRECIPITATION INPUT ————————————————
Computational Time Step (Minutes): 15
Extended Precipitation Time Series Selected
Climatic Region Number: 13
Full Period of Record Available used for Routing
Precipitation Station : 96004005 Puget East 40 in_5min 10/01/1939-10/01/2097
Evaporation Station : 961040 Puget East 40 in MAP
Evaporation Scale Factor : 0.750
HSPF Parameter Region Number: 1
HSPF Parameter Region Name : USGS Default
********** Default HSPF Parameters Used (Not Modified by User) ***************
********************** WATERSHED DEFINITION ***********************
Predevelopment/Post Development Tributary Area Summary
Predeveloped Post Developed
Total Subbasin Area (acres) 0.716 0.716
Area of Links that Include Precip/Evap (acres) 0.000 0.000
Total (acres) 0.716 0.716
----------------------SCENARIO: PREDEVELOPED
Number of Subbasins: 1
---------- Subbasin : Basin A - Existing ----------
-------Area(Acres) --------
Till Forest 0.179
Till Pasture 0.537
Till Grass 0.000
Outwash Forest 0.000
Outwash Pasture 0.000
Outwash Grass 0.000
Wetland 0.000
Green Roof 0.000
User 2 0.000
Impervious 0.000
----------------------------------------------
Subbasin Total 0.716
----------------------SCENARIO: POSTDEVELOPED
Number of Subbasins: 1
---------- Subbasin : Basin A - Proposed ----------
-------Area(Acres) --------
Till Forest 0.000
Till Pasture 0.000
Till Grass 0.274
Outwash Forest 0.000
Outwash Pasture 0.000
Outwash Grass 0.000
Wetland 0.000
Green Roof 0.000
User 2 0.000
Impervious 0.442
----------------------------------------------
Subbasin Total 0.716
************************* LINK DATA *******************************
----------------------SCENARIO: PREDEVELOPED
Number of Links: 0
************************* LINK DATA *******************************
----------------------SCENARIO: POSTDEVELOPED
Number of Links: 1
------------------------------------------
Link Name: Basin A - Detention Tank
Link Type: Structure
Downstream Link: None
User Specified Elevation Volume Table Used
Elevation (ft) Pond Volume (cu-ft)
320.00 0.
320.20 50.
320.40 140.
320.60 254.
320.80 385.
321.00 531.
321.20 688.
321.40 855.
321.60 1029.
321.80 1209.
322.00 1394.
322.20 1581.
322.40 1770.
322.60 1960.
322.80 2150.
323.00 2337.
323.20 2521.
323.40 2701.
323.60 2876.
323.80 3042.
324.00 3200.
324.20 3345.
324.40 3477.
324.60 3591.
324.80 3681.
325.00 3731.
Massmann Infiltration Option Used
Hydraulic Conductivity (in/hr) : 0.00
Depth to Water Table (ft) : 100.00
Bio-Fouling Potential : Low
Maintenance : Average or Better
Riser Geometry
Riser Structure Type : Circular
Riser Diameter (in) : 24.00
Common Length (ft) : 0.000
Riser Crest Elevation : 325.00 ft
Hydraulic Structure Geometry
Number of Devices: 3
---Device Number 1 ---
Device Type : Circular Orifice
Control Elevation (ft) : 320.50
Diameter (in) : 0.71
Orientation : Horizontal
Elbow : No
---Device Number 2 ---
Device Type : Circular Orifice
Control Elevation (ft) : 323.00
Diameter (in) : 1.24
Orientation : Horizontal
Elbow : Yes
---Device Number 3 ---
Device Type : Circular Orifice
Control Elevation (ft) : 324.50
Diameter (in) : 1.80
Orientation : Horizontal
Elbow : Yes
**********************FLOOD FREQUENCY AND DURATION STATISTICS*******************
----------------------SCENARIO: PREDEVELOPED
Number of Subbasins: 1
Number of Links: 0
----------------------SCENARIO: POSTDEVELOPED
Number of Subbasins: 1
Number of Links: 1
********** Subbasin: Basin A - Proposed **********
Flood Frequency Data(cfs)
(Recurrence Interval Computed Using Gringorten Plotting Position)
Tr (yrs) Flood Peak (cfs)
======================================
2-Year 0.188
5-Year 0.241
10-Year 0.301
25-Year 0.406
50-Year 0.484
100-Year 0.603
200-Year 0.606
********** Link: Basin A - Detention Tank ********** Link Inflow
Frequency Stats
Flood Frequency Data(cfs)
(Recurrence Interval Computed Using Gringorten Plotting Position)
Tr (yrs) Flood Peak (cfs)
======================================
2-Year 0.188
5-Year 0.241
10-Year 0.301
25-Year 0.406
50-Year 0.484
100-Year 0.603
200-Year 0.606
********** Link: Basin A - Detention Tank ********** Link WSEL
Stats
WSEL Frequency Data(ft)
(Recurrence Interval Computed Using Gringorten Plotting Position)
Tr (yrs) WSEL Peak (ft)
======================================
1.05-Year 321.968
1.11-Year 322.216
1.25-Year 322.568
2.00-Year 322.992
3.33-Year 323.288
5-Year 323.601
10-Year 323.924
25-Year 324.571
50-Year 324.960
100-Year 325.017
***********Groundwater Recharge Summary *************
Recharge is computed as input to Perlnd Groundwater Plus Infiltration in Structures
Total Predeveloped Recharge During Simulation
Model Element Recharge Amount (ac-ft)
-----------------------------------------------------------------------------------------------
Subbasin: Basin A - Existing 125.440
_____________________________________
Total: 125.440
Total Post Developed Recharge During Simulation
Model Element Recharge Amount (ac-ft)
-----------------------------------------------------------------------------------------------
Subbasin: Basin A - Proposed 33.486
Link: Basin A - Detention 0.000
_____________________________________
Total: 33.486
Total Predevelopment Recharge is Greater than Post Developed
Average Recharge Per Year, (Number of Years= 158)
Predeveloped: 0.794 ac-ft/year, Post Developed: 0.212 ac-ft/year
***********Water Quality Facility Data *************
----------------------SCENARIO: PREDEVELOPED
Number of Links: 0
----------------------SCENARIO: POSTDEVELOPED
Number of Links: 1
********** Link: Basin A - Detention Tank **********
Basic Wet Pond Volume (91% Exceedance): 2241. cu-ft
Computed Large Wet Pond Volume, 1.5*Basic Volume: 3362. cu-ft
15-Minute Timestep, Water Quality Treatment Design Discharge
On-line Design Discharge Rate (91% Exceedance): 0.06 cfs
Off-line Design Discharge Rate (91% Exceedance): 0.04 cfs
Infiltration/Filtration Statistics--------------------
Inflow Volume (ac-ft): 253.27
Inflow Volume Including PPT-Evap (ac-ft): 253.27
Total Runoff Infiltrated (ac-ft): 0.00, 0.00%
Total Runoff Filtered (ac-ft): 0.00, 0.00%
Primary Outflow To Downstream System (ac-ft): 253.43
Secondary Outflow To Downstream System (ac-ft): 0.00
Percent Treated (Infiltrated+Filtered)/Total Volume: 0.00%
***********Compliance Point Results *************
Scenario Predeveloped Compliance Subbasin: Basin A - Existing
Scenario Postdeveloped Compliance Link: Basin A - Detention Tank
*** Point of Compliance Flow Frequency Data ***
Recurrence Interval Computed Using Gringorten Plotting Position
Predevelopment Runoff Postdevelopment Runoff
Tr (Years) Discharge (cfs) Tr (Years) Discharge (cfs)
----------------------------------------------------------------------------------------------------------------------
2-Year 2.181E-02 2-Year 2.123E-02
5-Year 4.164E-02 5-Year 5.385E-02
10-Year 6.246E-02 10-Year 6.237E-02
25-Year 0.105 25-Year 9.791E-02
50-Year 0.154 50-Year 0.139
100-Year 0.194 100-Year 0.193
200-Year 0.204 200-Year 0.220
** Record too Short to Compute Peak Discharge for These Recurrence Intervals
Appendix C
Water Quality Calculation
Detention Pipe Volume Calculator
Blue Indicates Data Entry Cells, the rest are calculated.
Storage Volume Provided by Horizontal Pipe of Diameter d
Pipe Diameter (d)5.0 ft
Pipe Length 190 ft
Overflow Elevation:325.00 ft
Pond Volume at Overflow (cu ft):3731
Target Volume from MGSFlood: 700
Note: Volume is increased by 1 for Elevations Greater than Pipe Diameter
Pond Volume Table Because Routing Routine Requires Increasing Pond Volume
Circular Section Geometry Read from CircularSections Tab *** Copy Table below to MGSFlood Program Elevation Volume Input Screen
elev. Wetted Area storage storage DON'T INCLUDE THE COLUMN HEADINGS!
ft y/d s.f. cu.ft. (ac.ft) ELEV (FT) Top Area (Dummy) VOLUME (CU FT)
320.00 0.000 0.000 0 0 320.00 10.0 0.0.
320.20 0.040 0.263 50 0.001 320.20 10.1 49.9.
320.40 0.080 0.735 140 0.003 320.40 10.2 139.7.
320.60 0.120 1.335 254 0.006 320.60 10.3 253.7.
320.80 0.160 2.028 385 0.009 320.80 10.4 385.2.
321.00 0.200 2.795 531 0.012 321.00 10.5 531.1.
321.20 0.240 3.623 688 0.016 321.20 10.6 688.3.
321.40 0.280 4.500 855 0.020 321.40 10.7 855.0.
321.60 0.320 5.418 1029 0.024 321.60 10.8 1029.3.
321.80 0.360 6.365 1209 0.028 321.80 10.9 1209.4.
322.00 0.400 7.335 1394 0.032 322.00 11.0 1393.7.
322.20 0.440 8.320 1581 0.036 322.20 11.1 1580.8.
322.40 0.480 9.318 1770 0.041 322.40 11.2 1770.3.
322.60 0.520 10.318 1960 0.045 322.60 11.3 1960.3.
322.80 0.560 11.315 2150 0.049 322.80 11.4 2149.9.
323.00 0.600 12.300 2337 0.054 323.00 11.5 2337.0.
323.20 0.640 13.270 2521 0.058 323.20 11.6 2521.3.
323.40 0.680 14.218 2701 0.062 323.40 11.7 2701.3.
323.60 0.720 15.135 2876 0.066 323.60 11.8 2875.7.
323.80 0.760 16.010 3042 0.070 323.80 11.9 3041.9.
324.00 0.800 16.840 3200 0.073 324.00 12.0 3199.6.
324.20 0.840 17.608 3345 0.077 324.20 12.1 3345.4.
324.40 0.880 18.300 3477 0.080 324.40 12.2 3477.0.
324.60 0.920 18.900 3591 0.082 324.60 12.3 3591.0.
324.80 0.960 19.373 3681 0.084 324.80 12.4 3680.8.
325.00 1.000 19.635 3731 0.086 325.00 12.5 3730.7.
325.20 1.040 19.635 3731 0.086 325.20 12.6 3731.7.
325.40 1.080 19.635 3731 0.086 325.40 12.7 3732.7.
325.60 1.120 19.635 3731 0.086 325.60 12.8 3733.7.
325.80 1.160 19.635 3731 0.086 325.80 12.9 3734.7.
326.00 1.200 19.635 3731 0.086 326.00 13.0 3735.7.
7/29/2019 PondPipe.xls
—————————————————————————————————
MGS FLOOD
PROJECT REPORT
Program Version: MGSFlood 4.38
Program License Number: 201510001
Project Simulation Performed on: 06/14/2019 10:01 AM
Report Generation Date: 06/20/2019 12:36 PM
—————————————————————————————————
Input File Name: Willowcrest - Civil Permit Sizing - Basin A - Tank.fld
Project Name: Renton Homestead
Analysis Title: Peak Flow - Detention
Comments:
———————————————— PRECIPITATION INPUT ————————————————
Computational Time Step (Minutes): 15
Extended Precipitation Time Series Selected
Climatic Region Number: 13
Full Period of Record Available used for Routing
Precipitation Station : 96004005 Puget East 40 in_5min 10/01/1939-10/01/2097
Evaporation Station : 961040 Puget East 40 in MAP
Evaporation Scale Factor : 0.750
HSPF Parameter Region Number: 1
HSPF Parameter Region Name : USGS Default
********** Default HSPF Parameters Used (Not Modified by User) ***************
********************** WATERSHED DEFINITION ***********************
Predevelopment/Post Development Tributary Area Summary
Predeveloped Post Developed
Total Subbasin Area (acres) 0.716 0.716
Area of Links that Include Precip/Evap (acres) 0.000 0.000
Total (acres) 0.716 0.716
----------------------SCENARIO: PREDEVELOPED
Number of Subbasins: 1
---------- Subbasin : Basin A - Existing ----------
-------Area(Acres) --------
Till Forest 0.179
Till Pasture 0.537
Till Grass 0.000
Outwash Forest 0.000
Outwash Pasture 0.000
Outwash Grass 0.000
Wetland 0.000
Green Roof 0.000
User 2 0.000
Impervious 0.000
----------------------------------------------
Subbasin Total 0.716
----------------------SCENARIO: POSTDEVELOPED
Number of Subbasins: 1
---------- Subbasin : Basin A - Proposed ----------
-------Area(Acres) --------
Till Forest 0.000
Till Pasture 0.000
Till Grass 0.274
Outwash Forest 0.000
Outwash Pasture 0.000
Outwash Grass 0.000
Wetland 0.000
Green Roof 0.000
User 2 0.000
Impervious 0.442
----------------------------------------------
Subbasin Total 0.716
************************* LINK DATA *******************************
----------------------SCENARIO: PREDEVELOPED
Number of Links: 0
************************* LINK DATA *******************************
----------------------SCENARIO: POSTDEVELOPED
Number of Links: 1
------------------------------------------
Link Name: Basin A - Detention Tank
Link Type: Structure
Downstream Link: None
User Specified Elevation Volume Table Used
Elevation (ft) Pond Volume (cu-ft)
320.00 0.
320.20 50.
320.40 140.
320.60 254.
320.80 385.
321.00 531.
321.20 688.
321.40 855.
321.60 1029.
321.80 1209.
322.00 1394.
322.20 1581.
322.40 1770.
322.60 1960.
322.80 2150.
323.00 2337.
323.20 2521.
323.40 2701.
323.60 2876.
323.80 3042.
324.00 3200.
324.20 3345.
324.40 3477.
324.60 3591.
324.80 3681.
325.00 3731.
Massmann Infiltration Option Used
Hydraulic Conductivity (in/hr) : 0.00
Depth to Water Table (ft) : 100.00
Bio-Fouling Potential : Low
Maintenance : Average or Better
Riser Geometry
Riser Structure Type : Circular
Riser Diameter (in) : 24.00
Common Length (ft) : 0.000
Riser Crest Elevation : 325.00 ft
Hydraulic Structure Geometry
Number of Devices: 3
---Device Number 1 ---
Device Type : Circular Orifice
Control Elevation (ft) : 320.50
Diameter (in) : 0.71
Orientation : Horizontal
Elbow : No
---Device Number 2 ---
Device Type : Circular Orifice
Control Elevation (ft) : 323.00
Diameter (in) : 1.24
Orientation : Horizontal
Elbow : Yes
---Device Number 3 ---
Device Type : Circular Orifice
Control Elevation (ft) : 324.50
Diameter (in) : 1.80
Orientation : Horizontal
Elbow : Yes
**********************FLOOD FREQUENCY AND DURATION STATISTICS*******************
----------------------SCENARIO: PREDEVELOPED
Number of Subbasins: 1
Number of Links: 0
----------------------SCENARIO: POSTDEVELOPED
Number of Subbasins: 1
Number of Links: 1
********** Subbasin: Basin A - Proposed **********
Flood Frequency Data(cfs)
(Recurrence Interval Computed Using Gringorten Plotting Position)
Tr (yrs) Flood Peak (cfs)
======================================
2-Year 0.188
5-Year 0.241
10-Year 0.301
25-Year 0.406
50-Year 0.484
100-Year 0.603
200-Year 0.606
********** Link: Basin A - Detention Tank ********** Link Inflow
Frequency Stats
Flood Frequency Data(cfs)
(Recurrence Interval Computed Using Gringorten Plotting Position)
Tr (yrs) Flood Peak (cfs)
======================================
2-Year 0.188
5-Year 0.241
10-Year 0.301
25-Year 0.406
50-Year 0.484
100-Year 0.603
200-Year 0.606
********** Link: Basin A - Detention Tank ********** Link WSEL
Stats
WSEL Frequency Data(ft)
(Recurrence Interval Computed Using Gringorten Plotting Position)
Tr (yrs) WSEL Peak (ft)
======================================
1.05-Year 321.968
1.11-Year 322.216
1.25-Year 322.568
2.00-Year 322.992
3.33-Year 323.288
5-Year 323.601
10-Year 323.924
25-Year 324.571
50-Year 324.960
100-Year 325.017
***********Groundwater Recharge Summary *************
Recharge is computed as input to Perlnd Groundwater Plus Infiltration in Structures
Total Predeveloped Recharge During Simulation
Model Element Recharge Amount (ac-ft)
-----------------------------------------------------------------------------------------------
Subbasin: Basin A - Existing 125.440
_____________________________________
Total: 125.440
Total Post Developed Recharge During Simulation
Model Element Recharge Amount (ac-ft)
-----------------------------------------------------------------------------------------------
Subbasin: Basin A - Proposed 33.486
Link: Basin A - Detention 0.000
_____________________________________
Total: 33.486
Total Predevelopment Recharge is Greater than Post Developed
Average Recharge Per Year, (Number of Years= 158)
Predeveloped: 0.794 ac-ft/year, Post Developed: 0.212 ac-ft/year
***********Water Quality Facility Data *************
----------------------SCENARIO: PREDEVELOPED
Number of Links: 0
----------------------SCENARIO: POSTDEVELOPED
Number of Links: 1
********** Link: Basin A - Detention Tank **********
Basic Wet Pond Volume (91% Exceedance): 2241. cu-ft
Computed Large Wet Pond Volume, 1.5*Basic Volume: 3362. cu-ft
15-Minute Timestep, Water Quality Treatment Design Discharge
On-line Design Discharge Rate (91% Exceedance): 0.06 cfs
Off-line Design Discharge Rate (91% Exceedance): 0.04 cfs
Infiltration/Filtration Statistics--------------------
Inflow Volume (ac-ft): 253.27
Inflow Volume Including PPT-Evap (ac-ft): 253.27
Total Runoff Infiltrated (ac-ft): 0.00, 0.00%
Total Runoff Filtered (ac-ft): 0.00, 0.00%
Primary Outflow To Downstream System (ac-ft): 253.43
Secondary Outflow To Downstream System (ac-ft): 0.00
Percent Treated (Infiltrated+Filtered)/Total Volume: 0.00%
***********Compliance Point Results *************
Scenario Predeveloped Compliance Subbasin: Basin A - Existing
Scenario Postdeveloped Compliance Link: Basin A - Detention Tank
*** Point of Compliance Flow Frequency Data ***
Recurrence Interval Computed Using Gringorten Plotting Position
Predevelopment Runoff Postdevelopment Runoff
Tr (Years) Discharge (cfs) Tr (Years) Discharge (cfs)
----------------------------------------------------------------------------------------------------------------------
2-Year 2.181E-02 2-Year 2.123E-02
5-Year 4.164E-02 5-Year 5.385E-02
10-Year 6.246E-02 10-Year 6.237E-02
25-Year 0.105 25-Year 9.791E-02
50-Year 0.154 50-Year 0.139
100-Year 0.194 100-Year 0.193
200-Year 0.204 200-Year 0.220
** Record too Short to Compute Peak Discharge for These Recurrence Intervals
WQ FACILITY SIZED
TO ACCOMODATE
FULL 2-YEAR
RELEASE RATE
FROM DETENTION
FACILITY.
Appendix D
Geotechnical Report
Geotechnical Engineering Services
Willow Crest Townhomes
Renton, Washington
for
Homestead Community Land Trust
c/o Third Place Design Co-operative
November 15, 2018
Geotechnical Engineering Services
Willow Crest Townhomes
Renton, Washington
for
Homestead Community Land Trust
c/o Third Place Design Co-operative
November 15, 2018
17425 NE Union Hill Road, Suite 250
Redmond, Washington 98052
425.861.6000
Prepared for:
Homestead Community Land Trust
c/o Third Place Design Co-operative
177 Western Avenue West, Suite 266
Seattle, Washington 98119
Geotechnical Engineering Services
Willow Crest Townhomes
Renton, Washington
File No. 23656-001-00
November 15, 2018
Attention: Suzanne Davis, LEED AP, NCARB
Prepared by:
GeoEngineers, Inc.
17 425 NE Union Hill Road, Suite 250
Redmond, Washington 98052
425.861.6000
Michael A. Gray, PE
Geotechnical Engineer
R��
Principal
MAG:RCM:nld
Disclaimer: Any electronic form, facsimile or hard copy of the original document (email, text, table, and/or figure), if provided, and any attachments are only a copy of the original document. The original document is stored by Geo Engineers, Inc. and will serve as the official document of record.
GEoENGINEER�
November 15, 2018 | Page i File No. 23656-001-00
Table of Contents
INTRODUCTION ..................................................................................................................................................... 1
Project Description ........................................................................................................................................... 1
Purpose and Scope .......................................................................................................................................... 1
FIELD EXPLORATIONS AND LABORATORY TESTING ......................................................................................... 1
Field Explorations ............................................................................................................................................. 1
Laboratory Testing ........................................................................................................................................... 1
Previous Studies .............................................................................................................................................. 2
SITE DESCRIPTIONS............................................................................................................................................. 2
Site Geology ..................................................................................................................................................... 2
Surface Conditions........................................................................................................................................... 2
Subsurface Conditions .................................................................................................................................... 2
Groundwater Conditions .................................................................................................................................. 3
CONCLUSIONS AND RECOMMENDATIONS ........................................................................................................ 3
Summary .......................................................................................................................................................... 3
Earthquake Engineering .................................................................................................................................. 4
2015 IBC Seismic Design Information .................................................................................................... 4
Liquefaction Potential ............................................................................................................................... 4
Ground Rupture ......................................................................................................................................... 4
Landslides ................................................................................................................................................. 5
Foundations ..................................................................................................................................................... 5
Foundation Design .................................................................................................................................... 5
Foundation Settlement ............................................................................................................................. 5
Lateral Resistance .................................................................................................................................... 6
Construction Considerations .................................................................................................................... 6
Footing Drains ........................................................................................................................................... 6
Slab-on-Grade Floors ....................................................................................................................................... 6
Pavement Recommendations ......................................................................................................................... 7
Subgrade Preparation ............................................................................................................................... 7
New Hot Mix Asphalt Pavement ............................................................................................................... 7
Portland Cement Concrete Pavement ..................................................................................................... 8
Asphalt-Treated Base ................................................................................................................................ 8
Earthwork ......................................................................................................................................................... 8
Clearing and Site Preparation .................................................................................................................. 9
Subgrade Preparation ............................................................................................................................... 9
Structural Fill ........................................................................................................................................... 10
Permanent Cut and Fill Slopes ............................................................................................................... 12
Utility Trenches ........................................................................................................................................ 12
Sedimentation and Erosion Control ....................................................................................................... 13
Excavations .................................................................................................................................................... 13
Temporary Cut Slopes ............................................................................................................................. 13
Drainage Considerations ............................................................................................................................... 14
November 15, 2018 | Page ii File No. 23656-001-00
Infiltration Considerations ............................................................................................................................. 14
RECOMMENDED ADDITIONAL GEOTECHNICAL SERVICES ............................................................................. 15
LIMITATIONS ....................................................................................................................................................... 15
REFERENCES ..................................................................................................................................................... 15
LIST OF FIGURES
Figure 1. Vicinity Map
Figure 2. Site Plan – Proposed Development
Figure 3. Compaction Criteria for Trench Backfill
APPENDICES
Appendix A. Field Explorations
Figure A-1. Key to Exploration Logs
Figures A-2 through A-7. Logs of Test Pits
Appendix B. Laboratory Testing
Figures B-1 and B-2. Sieve Analysis Results
Figure B-3. Compaction Test Results (TP-3)
Appendix C. Boring and Test Pit Logs from Previous Studies
Appendix D. Report Limitations and Guidelines for Use
November 15, 2018 | Page 1
File No. 23656-001-00
INTRODUCTION
This report presents the results of GeoEngineers, Inc.’s (GeoEngineers) geotechnical engineering services
for the Willow Crest Townhomes project located in Renton, Washington. The site is shown relative to
surrounding physical features on Figure 1, Vicinity Map and Figure 2, Site Plan.
Project Description
We understand that the proposed development will consist of three four-unit wood-frame townhomes
(12 total townhomes) constructed at existing grade. The development will also include new underground
utilities, access drive, sidewalks, and landscaping. Minor site grading is anticipated and no underground
structures are planned for the project.
Purpose and Scope
The purpose of our geotechnical engineering services is to evaluate soil and groundwater conditions as a
basis for developing design criteria for the geotechnical aspects of the proposed development. Field
explorations and laboratory testing were performed to identify and evaluate subsurface conditions at the
sites to develop engineering recommendations for use in design of the project. Our services were performed
in general accordance with our scope of services outlined in our Proposal dated October 2, 2018.
FIELD EXPLORATIONS AND LABORATORY TESTING
Field Explorations
The subsurface soil and groundwater conditions were evaluated by reviewing existing geotechnical
information and completing six test pits (GEI-TP-1 through GEI-TP-6) across the planned building locations.
The test pits were completed to depths of approximately 8 feet below the ground surface (bgs). The test
pits were completed on October 22, 2018 using a rubber-tracked backhoe. The approximate locations of
the explorations are shown on Figure 2. Descriptions of the field exploration program and the explorations
logs are presented in Appendix A.
Laboratory Testing
Soil samples were obtained during the exploration program and taken to our laboratory for further
evaluation. Selected samples were tested for the determination of moisture content, fines content, grain
size distribution (sieve analysis), and modified Proctor compaction tests. A description of the laboratory
testing and the test results are presented in Appendix B.
November 15, 2018 | Page 2 File No. 23656-001-00
Previous Studies
The exploration logs (borings and test pits) of selected explorations from previous subsurface studies in
vicinity of the proposed project were reviewed. Logs of relevant explorations reviewed for this study are
presented in Appendix C and approximate locations are shown on Figure 2. The existing subsurface
information includes:
■ “Report of Geotechnical Investigation, Proposed Residential Development, Edmonds and
Glennwood Ave NE, Renton, Washington,” prepared by Soil and Environmental Engineers, Inc., dated
January 10, 2011.
SITE DESCRIPTIONS
Site Geology
Our review of the geologic map for the area (Mullineaux 1965) and previous geotechnical reports completed
in the vicinity of the project site indicate that the proposed development is underlain by dense to very dense
glacial till at relatively shallow depths. Dense to very dense native glacial till was observed in all the test
pits completed at the site. Glacial till commonly consists of a very compact, poorly sorted, non-stratified
mixture of clay, silt, sand, gravel and cobbles. Glacial till commonly appears gray or blue on a fresh surface,
while weathered glacial till may be brown to yellow in color. The till was observed to contain cobbles in some
areas and commonly also includes large boulders. Additionally, test pit GEI-TP-4 encountered a boulder at
approximately 3.5 feet.
Surface Conditions
The location of the proposed townhomes consists of an undeveloped lot covered with vegetation. The lot is
relatively flat and slopes down from approximate Elevation 343 feet in the northeast corner to about
Elevation 330 feet in the southwest corner. Vegetation generally consists of blackberry brambles with
various deciduous trees spread across the site. An existing storm drain outfall is present in the southeast
corner of the site.
Subsurface Conditions
Shallow fill overlying loose to medium dense weathered glacial till and dense to very dense relatively
unweathered native glacial till was observed in all of our test pits completed at the planned townhome
locations. In general, the soils encountered in the test pits consisted of the following:
Fill: Fill consisting of loose to medium dense sand with silt and gravel exists across the site. The fill is
relatively thin and is typically less than 1 foot deep in the test pits completed at the project site.
Till: Glacial till was observed to the depths explored in all of the test pits. The glacial till is relatively
unweathered at a depth ranging from about 2.5 to 3.5 feet bgs and consists of gray dense to very dense
silty fine to medium sand with variable gravel content and occasional cobbles. Weathered glacial till exists
near the ground surface below the fill and above the relatively unweathered parent material and is typically
brown and loose to medium dense. The weathered till may be 1 to 3 feet thick across the site.
November 15, 2018 | Page 3 File No. 23656-001-00
Groundwater Conditions
No groundwater seepage was observed in the test pits completed on site. Additionally, previous
explorations completed to depths of 30 feet below site grades did not encounter groundwater.
Groundwater observations represent conditions observed during exploration and may not represent the
groundwater conditions throughout the year. We anticipate that perched groundwater will exist at the
contact between the glacial till and the overlying looser fill and weathered till, and within more permeable
layers within the native glacial till. Groundwater seepage is expected to fluctuate as a result of season,
precipitation, and other factors.
CONCLUSIONS AND RECOMMENDATIONS
Based on the results of our field exploration program, laboratory testing, and engineering analysis, we
conclude that development of the proposed development can be accomplished as planned. A summary of
primary geotechnical considerations for the site development and design of the proposed development is
provided in the subsequent sections.
Summary
■ The planned townhomes site is classified as Site Class C, in accordance with the 2015 International
Building Code (IBC).
■ The planned townhomes may be supported on conventional spread footings bearing on dense to very
dense undisturbed glacial till or on structural fill placed over these soils. Footings bearing on dense to
very dense undisturbed glacial till may be designed using an allowable soil bearing value of
6,000 pounds per square foot (psf). Footings bearing on structural fill placed over undisturbed dense
to very dense glacial till may be designed using an allowable bearing value of 3,000 psf. All existing fill,
highly weathered glacial till or otherwise unsuitable soils should be removed from below foundations
prior to constructing foundations or placing structural fill. The allowable bearing value may be increased
by one-third for short duration loads such as wind or seismic events.
■ Lateral foundation loads may be resisted by passive resistance on the sides of the footings and by
friction on the base of the footings. For footings supported and surrounded by either dense native soils
or compacted structural fill, a coefficient of friction of 0.35 and a passive resistance of 350 pounds per
cubic foot (pcf) may be used.
■ A subgrade modulus of 100 pounds per cubic inch (pci) may be used for design of the slabs-on-grade
for the townhomes. Concrete slabs-on-grade should be supported on a 4-inch-thick capillary break layer
overlain by a vapor retarder (in conditioned spaces or enclosed rooms, such as mechanical or storage
space).
■ The pavement section extending to the west and north from the southeast corner of the project site
may be supported on existing fill soils provided that the upper 2 feet of the fill is placed and compacted
as structural fill. A proof roll test can also be conducted to reduce excavation costs if native soils are
encountered within the upper 2 feet and to check that the soils can perform adequately under planned
loads. If any soft spots are observed, the upper 2 feet of subgrade soils should be removed and
replaced with at least 2 feet of structural fill compacted to at least 95 percent of the maximum dry
density (MDD) per ASTM International (ASTM) D 1557. Suitable on-site soils may be used as structural
November 15, 2018 | Page 4 File No. 23656-001-00
fill under the planned road and associated hardscape provided that earthwork is accomplished during
dry weather conditions in the summer months.
Earthquake Engineering
We evaluated the site for seismic hazards including liquefaction, lateral spreading, fault rupture and
earthquake-induced landsliding. Our evaluation indicates that the site does not have liquefiable soils
present and, therefore, also has no risk of liquefaction-induced lateral spreading. In addition, the site has
a low risk of fault rupture and earthquake-induced landsliding.
2015 IBC Seismic Design Information
For the planned townhomes, we recommend the IBC 2015 parameters for average field standard
penetration resistance, site class, short period spectral response acceleration (SS), 1-second period
spectral response acceleration (S1), and seismic coefficients FA and FV presented in Table 1.
TABLE 1. 2015 IBC SEISMIC PARAMETERS
2015 IBC Parameter Recommended Value
Average Field Standard Penetration Resistance >50
Site Class C
Short Period Spectral Response Acceleration, SS (percent g) 143.2
1-Second Period Spectral Response Acceleration, S1 (percent g) 53.8
Seismic Coefficient, FA 1.000
Seismic Coefficient, FV 1.300
Liquefaction Potential
Liquefaction is a phenomenon where soils experience a rapid loss of internal strength as a consequence
of strong ground shaking. Ground settlement, lateral spreading and/or sand boils may result from soil
liquefaction. Structures supported on liquefied soils could suffer foundation settlement or lateral
movement that could be severely damaging to the structures.
Conditions favorable to liquefaction occur in loose to medium dense, clean to moderately silty sand, which
is below the groundwater level. Based on our evaluation of the subsurface conditions observed in the
explorations, it is our opinion that potentially liquefiable soils are not present at the project site.
Ground Rupture
Ground rupture from lateral spreading is associated with liquefaction. Lateral spreading involves lateral
displacements of large volumes of liquefied soil, and can occur on near-level ground as blocks of surface
soils displace relative to adjacent blocks. In our opinion, ground rupture resulting from lateral spreading at
the site is unlikely because potentially liquefiable soils are not present at the site as discussed above.
Because of the thickness of the Quaternary sediments below the site, which are commonly more than
1,000 feet thick, the potential for surface fault rupture is considered low.
November 15, 2018 | Page 5 File No. 23656-001-00
Landslides
Because site topography is relatively flat and dense to very dense glacial till deposits occur at shallow
depths, it is our opinion that landsliding as a result of strong ground shaking is unlikely at the site.
Foundations
We recommend that the buildings be supported on shallow spread footings founded on the dense to very
dense native glacial till soil encountered in the explorations, or on properly compacted structural fill
extending down to medium dense to dense glacial till. The following recommendations for the buildings are
based on the subsurface conditions observed in the explorations and the site survey.
Foundation Design
For shallow foundation support, we recommend widths of at least 18 and 24 inches, respectively, for
continuous wall and isolated column footings supporting the proposed townhomes. The design frost depth
in the Puget Sound area is 12 inches, therefore, we recommend that the footings be founded at least
18 inches below lowest adjacent finished grade.
Unsuitable soils consisting of fill, topsoil, and/or highly weathered glacial soils will vary across the site and
must be removed from below planned footings. Based on our explorations, up to 3½ feet of fill and/or
looser weathered native soils exist under the proposed north building unit (GEI-TP-1 and GEI-TP-2),
approximately 3 feet under the central building unit (GEI-TP-3 and GEI-TP-4) and 2½ feet under the south
building unit (GEI-TP-5 and GEI-TP-6). Therefore, depending on the foundation locations and depths,
overexcavation under the footings may be necessary. For foundations supported on medium dense native
glacial till or structural fill extending down to medium dense to dense native glacial till, we recommend
footings be designed using a maximum allowable bearing pressure of 3,000 psf. A maximum allowable
bearing pressure of 6,000 psf may be used in design where foundations are bearing on dense to very dense
relatively unweathered glacial till or on controlled density fill (CDF) extending down to the dense to very
dense native till. All existing fill and looser native soils should be removed from below planned footings.
These allowable bearing pressures apply to the total dead and long-term live loads and may be increased
up to one-third for short-term live loads such as wind or seismic forces.
The overexcavated areas should be backfilled with: (1) CDF having a design strength of at least 200 pounds
per square inch (psi) where 6,000 psf bearing pressures are used or, (2) imported gravel borrow where
3,000 psf is used. Where structural fill is placed below footings, the fill should extend beyond the edges of
the foundations by the depth of the overexcavation, while the CDF should extend beyond the edges of the
foundations by half the depth of the excavation.
Foundation Settlement
We estimate that the post-construction settlement of footings founded on the very dense glacial till or
structural fill extending to the medium dense to very dense till, as recommended above, will be between
½ and 1 inch. Differential settlement between comparably loaded column footings or along a 25-foot
section of continuous wall footing should be less than ½ inch. We expect most of the footing settlements
will occur as loads are applied. Loose or disturbed soils not removed from footing excavations prior to
placing concrete will result in additional settlement.
November 15, 2018 | Page 6 File No. 23656-001-00
Lateral Resistance
Lateral loads can be resisted by passive resistance on the sides of the footings and by friction on the base
of the footings. Passive resistance should be evaluated using an equivalent fluid density of 350 pcf where
footings are poured neat against native soil or are surrounded by structural fill compacted to at least
95 percent of MDD, as recommended. Resistance to passive pressure should be calculated from the
bottom of adjacent floor slabs and paving or below a depth of 1 foot where the adjacent area is unpaved,
as appropriate. Frictional resistance can be evaluated using 0.35 for the coefficient of base friction against
footings. The above values incorporate a factor of safety of about 1.5.
If soils adjacent to footings are disturbed during construction, the disturbed soils must be recompacted,
otherwise the lateral passive resistance value must be reduced.
Construction Considerations
Immediately prior to placing concrete, all debris and loose soils that accumulated in the footing excavations
during forming and steel placement must be removed. Debris or loose soils not removed from the footing
excavations will result in increased settlement.
If wet weather construction is planned, we recommend that all footing subgrades be protected using a lean
concrete mud mat or 3 inches of compacted crushed base course. The mud mat or base course should be
placed the same day that the footing subgrade is excavated and approved for foundation support.
We recommend that all completed footing excavations be observed by a representative of our firm prior to
placing mud mat, reinforcing steel, and structural concrete. Our representative will confirm that the bearing
surface has been prepared in a manner consistent with our recommendations and that the subsurface
conditions are as expected.
Footing Drains
We recommend that perimeter footing drains be installed around each building. The perimeter drains
should be installed at the base of the exterior footings. The perimeter drains should be provided with
cleanouts and should consist of at least 4-inch-diameter perforated pipe placed on a 3-inch bed of drainage
material, and surrounded by 6 inches of drainage material enclosed in a non-woven geotextile fabric such
as TenCate Mirafi 140N (or approved equivalent) to prevent fine soil from migrating into the drain material.
We recommend against using flexible tubing for footing drainpipes. The perimeter drains should be sloped
to drain by gravity, if practicable, to a suitable discharge point, preferably a storm drain. We recommend
that the cleanouts be covered, and be placed in flush-mounted utility boxes. Water collected in roof
downspout lines must not be routed to the footing drain lines.
Slab-on-Grade Floors
We expect that the lower level concrete slab-on-grade can be supported on the medium dense to very dense
native soil encountered in our explorations or on properly compacted structural fill. A subgrade modulus of
100 pci may be used for design of the slabs-on-grade at the site. We recommend that an appropriate
capillary break and vapor retarder be installed below concrete slabs to reduce the risk of moisture migration
through the floor slab. This is especially important since zones of groundwater seepage may be present at
the planned floor slab level in more permeable layers above the dense native glacial till or in looser soils
on top of the dense glacial till.
November 15, 2018 | Page 7 File No. 23656-001-00
Prior to placing the gravel layer, the subgrade should be proofrolled as described previously in the
“Earthwork” section of this report. If necessary, the building slab subgrades should be recompacted to a
firm and unyielding condition.
We recommend that concrete slabs-on-grade be constructed on a gravel layer to provide uniform support
and drainage and to act as a capillary break. The gravel layer below slabs-on-grade should consist of at
least 4 inches of clean crushed gravel with a maximum particle size of 1 inch and negligible sand or silt in
accordance with Washington State Department of Transportation (WSDOT) Standard Specification
9-03.1(4)C American Association of State Highway and Transportation Officials (AASHTO) Grading No. 67.
If prevention of moisture migration through the slab is essential, a vapor retarder such as heavy plastic
sheeting should be installed between the slab and the gravel layer. It may also be prudent to apply a sealer
to the slab to further retard the migration of moisture through the floor. We recommend that the plastic
sheet be placed over the capillary break layer.
Pavement Recommendations
Recommendations for typical pavements (asphalt and concrete) are provided in the following sections. The
City of Renton may have standard pavement sections that could apply to the site, therefore the project civil
engineer should review the City’s standards, if applicable.
Subgrade Preparation
We recommend the subgrade soils in new pavement areas be prepared and evaluated as described in the
“Earthwork” section of this report. All new pavement and hardscape areas should be supported on
subgrade soils that have been proof rolled or probed as described in the “Clearing and Site Preparation”
section of this report. If the exposed subgrade soils are loose or soft, it may be necessary to excavate
localized areas and replace them with structural fill or gravel base course. Pavement subgrade conditions
should be observed during construction and prior to placing the subbase materials in order to evaluate the
presence of zones of unsuitable subgrade soils and the need for overexcavation and replacement of these
zones.
New Hot Mix Asphalt Pavement
In light-duty pavement areas (e.g., automobile parking), we recommend a pavement section consisting of
at least a 2½ -inch thickness of ½-inch hot-mix asphalt (HMA) per WSDOT Sections 5-04 and 9-03,
over a 4-inch thickness of densely compacted crushed surfacing base course (CSBC) per WSDOT Section
9-03.9(3). In heavy-duty pavement areas (such as the driveway), we recommend a pavement section
consisting of at least a 3-inch thickness of ½-inch HMA over a 6-inch thickness of densely compacted CSBC.
The base course should be compacted to at least 95 percent of the MDD obtained using ASTM D 1557.
We recommend that proof rolling of the subgrade and compacted base course be observed by a
representative from our firm prior to paving. Soft or yielding zones observed during proof rolling may require
overexcavation and replacement with compacted structural fill.
The pavement sections recommended above are based on our experience. Thicker asphalt sections may
be needed in accordance with the City of Renton or based on the actual traffic data, truck loads, and
intended use. All paved and landscaped areas should be graded so that surface drainage is directed to
appropriate catch basins.
November 15, 2018 | Page 8 File No. 23656-001-00
Portland Cement Concrete Pavement
Portland cement concrete (PCC) sections may be considered for areas where concentrated heavy loads
may occur. We recommend that these pavements consist of at least 6 inches of PCC over 6 inches of CSBC.
A thicker concrete section may be needed based on the actual load data for use of the area. If the concrete
pavement will have doweled joints, we recommend that the concrete thickness be increased by an amount
equal to the diameter of the dowels. The base course should be compacted to at least 95 percent of the
MDD.
We recommend PCC pavements incorporate construction joints and/or crack control joints spaced at
maximum distances of 12 feet apart, center-to-center, in both the longitudinal and transverse directions.
Crack control joints may be created by placing an insert or groove into the fresh concrete surface during
finishing, or by saw cutting the concrete after it has initially set up. We recommend the depth of the crack
control joints be approximately one fourth the thickness of the concrete; or about 1½ inches deep for the
recommended concrete thickness of 6 inches. We also recommend the crack control joints be sealed with
an appropriate sealant to help restrict water infiltration into the joints.
Asphalt-Treated Base
If pavements are constructed during the wet seasons, consideration may be given to covering the areas to
be paved with asphalt-treated base (ATB) for protection. Light-duty pavement areas should be surfaced with
3 inches of ATB, and heavy-duty pavement areas should be surfaced with 6 inches of ATB. Thicker ATB
sections may be needed based on construction equipment loads. Prior to placement of the final pavement
sections, we recommend the ATB surface be evaluated and areas of ATB pavement failure be removed and
the subgrade repaired. If ATB is used and is serviceable when final pavements are constructed, the CSBC
can be eliminated, and the design PCC or asphalt concrete pavement thickness can be placed directly over
the ATB.
Earthwork
Based on the subsurface soil conditions encountered in the explorations, we expect that the soils at the
site may be excavated using conventional heavy-duty construction equipment. Very dense glacial till was
encountered at relatively shallow depths at the planned building locations; therefore, glacial till soils within
deeper portions of excavations may require a large excavator to accomplish the excavations. Cobbles were
observed in most of the test pits and glacial till deposits in the area commonly contain boulders that may
be encountered during excavation. Accordingly, the contractor should be prepared to deal with boulders, if
encountered.
The glacial till contains sufficient fines (material passing the U.S. standard No. 200 sieve) to be highly
moisture-sensitive and susceptible to disturbance, especially when wet. Ideally, earthwork should be
undertaken during extended periods of dry weather when the surficial soils will be less susceptible to
disturbance and provide better support for construction equipment. Dry weather construction will help
reduce earthwork costs and increase the potential for using the native soils as structural fill.
Trafficability on the site is not expected to be difficult during dry weather conditions. However, the fill and
native soils will be susceptible to disturbance from construction equipment during wet weather conditions
and pumping and rutting of the exposed soils under equipment loads may occur.
November 15, 2018 | Page 9 File No. 23656-001-00
Clearing and Site Preparation
Areas to be developed or graded should be cleared of surface and subsurface deleterious matter including
any debris, shrubs, trees and associated stumps and roots. Graded areas should be stripped of organic
soils.
The organic soils can be stockpiled and used later for landscaping purposes or may be spread over
disturbed areas following completion of grading. If spread out, the organic strippings should be in a layer
less than 1-foot thick, should not be placed on slopes greater than 3H:1V (horizontal to vertical) and should
be track-rolled to a uniformly compacted condition. Materials that cannot be used for landscaping or
protection of disturbed areas should be removed from the project site.
Undocumented fill may be present in various areas of the site and will be required to be removed under
building foundations and within the upper two feet of pavement, hardscape and slab subgrade levels.
Where existing fill and looser native soils are removed, they may be reused and recompacted as structural
fill, if conditions allow. If medium dense to dense native soils are encountered below slab subgrade,
additional excavation is not required. If old fill is encountered below slab subgrade, the fill should be
evaluated and possibly removed up to 2 feet below slab subgrade or until medium dense to dense native
soils are encountered (less than 2 feet below slab subgrade). Excavations for slab subgrade preparation
likely do not need to extend more than 2 feet below slab subgrade. The upper two feet below pavement
subgrade should also be removed and replaced as structural fill; however, if existing fill soils are suitable
and adequately compacted based on evaluations after the pavement is removed, the contractor can
perform a proof roll on the exposed surface at or below slab subgrade level, and if approved by the
geotechnical engineer, the fill may be left in place.
Subgrade Preparation
Prior to placing new fills, pavement base course materials or gravel below on-grade floor slabs, subgrade
areas should be proof rolled to locate any soft or pumping soils. Prior to proof rolling, all unsuitable soils
should be removed from below the building footprints. Proof rolling can be completed using a piece of heavy
tire-mounted equipment such as a loaded dump truck. During wet weather, the exposed subgrade areas
should be probed to determine the extent of soft soils. If soft or pumping soils are observed, they should
be removed and replaced with compacted structural fill.
If deep pockets of soft or pumping soils are encountered outside the building areas, it may be possible to
limit the depth of overexcavation by placing a non-woven geotextile fabric such as TenCate Mirafi 500X (or
equivalent) on the overexcavated subgrade prior to placing structural fill. The geotextile will provide
additional support by bridging over the soft material and will help reduce fines contamination into the
structural fill.
After completing the proof rolling, the subgrade areas should be recompacted to a firm and unyielding
condition, if possible. The degree of compaction that can be achieved will depend on when the construction
is performed. If the work is performed during dry weather conditions, we recommend that all subgrade
areas be recompacted to at least 95 percent of the MDD in accordance with the ASTM D 1557 test
procedure (modified Proctor). If the work is performed during wet weather conditions, it may not be possible
to recompact the subgrade to 95 percent of the MDD. In this case, we recommend that the subgrade be
compacted to the extent possible without causing undue heaving or pumping of the subgrade soils.
November 15, 2018 | Page 10 File No. 23656-001-00
Subgrade disturbance or deterioration could occur if the subgrade is wet and cannot be dried. If the
subgrade deteriorates during proof rolling or compaction, it may become necessary to modify the proof
rolling, compaction criteria, or methods.
Structural Fill
All fill, whether existing on-site glacial till soil or imported soil, that will support building foundations and
floor slabs, pavement and hardscape areas, or be placed in utility trenches should generally meet the
criteria for structural fill presented below. The suitability of soil for use as structural fill depends on its
gradation and moisture content.
Materials
Materials used on the project site, under buildings, pavement, hardscape areas, and to backfill utility
trenches are classified as structural fill for the purpose of this report. Structural fill material quality varies
depending upon its use as described below:
1. Structural fill placed below all building elements (except footing designed for greater than 3,000 psf
bearing pressure) and during wet weather conditions should consist of imported Gravel Borrow, as
described in Section 9-03.14(1) of the 2018 WSDOT Standard Specifications, with the additional
restriction that the fines content be limited to no more than 5 percent. On-site soils may be used as
structural fil provided it is placed during the summer months, is properly moisture conditioned to within
2 percent of the optimum moisture content, and can be compacted to at least 95 percent of the MDD.
2. CDF having a design strength of at least 200 psi should be used under all foundations designed for
greater than 3,000 psf bearing pressure.
3. Structural fill placed to construct embankment and parking areas and to backfill utility trenches may
consist of on-site fill and glacial till provided that the soils are moisture conditioned for the required
compaction. On-site till soils may be suitable for use as structural fill during dry weather conditions in
areas needing 95 percent compaction. If structural fill is placed during wet weather, the structural fill
should consist of imported gravel borrow.
4. Structural fill placed as CSBC below pavements should conform to Section 9-03.9(3) of the 2018
WSDOT Standard Specifications.
5. Structural fill placed as capillary break below slabs should consist of 1-inch minus clean crushed gravel
with negligible sand or silt in conformance with Section 9-03.1(4)C, grading No. 67 of the 2018 WSDOT
Standard Specifications.
Reuse of On-site Native Soils
The existing fill and till soils contain a high percentage of fines and will be sensitive to changes in moisture
content and difficult to handle and compact during wet weather.
The existing fill (free of organic debris) and till deposits are expected to be suitable for structural fill in areas
requiring compaction to at least 95 percent of MDD (per ASTM D 1557), provided the work is accomplished
during the normally dry season (June through September) and that the soil can be properly moisture
conditioned to within 2 percent of the optimum moisture content. Imported structural fill consisting of sand
and gravel (WSDOT gravel borrow) should be planned under all building foundation elements, especially if
construction occurs during wet weather.
November 15, 2018 | Page 11 File No. 23656-001-00
The use of existing on-site fill and till soils as structural fill during wet weather should be planned only for
areas requiring compaction to 90 percent of MDD, as long as the soils are properly protected from wet
weather, not placed during periods of precipitation, and that they can be dried if needed to achieve proper
compaction. The contractor should plan to cover and maintain all fill stockpiles with plastic sheeting if it
will be used as structural fill. The reuse of on-site soils is highly dependent on the skill of the contractor and
schedule, and we will work with the design team and contractor to maximize the reuse of on-site till soils
during the wet and dry seasons.
Fill Placement and Compaction Criteria
Structural fill should be mechanically compacted to a firm, non-yielding condition. Structural fill should be
placed in loose lifts not exceeding 12 inches in thickness when using heavy compaction equipment and
not more than 6 inches when using hand-operated compaction equipment. The actual thickness will be
dependent on the structural fill material used and the type and size of compaction equipment. Each lift
should be moisture conditioned to within about 2 percent of the optimum moisture content to achieve
proper compaction to the specified density before placing subsequent lifts. Compaction of all structural fill
at the site should be in accordance with the ASTM D 1557 (modified Proctor) test method. Structural fill
should be compacted to the following criteria:
1. Structural fill placed below floor slabs and foundations should be compacted to 95 percent of the MDD.
2. Structural fill in new pavement and hardscape areas, including utility trench backfill, should be
compacted to at least 90 percent of the MDD, except that the upper 2 feet of fill below final subgrade
should be compacted to at least 95 percent of the MDD, see Figure 3, Compaction Criteria for Trench
Backfill.
3. Structural fill placed as CSBC below pavements should be compacted to 95 percent of the MDD.
4. Non-structural fill, such as fill placed in landscape areas, should be compacted to at least 90 percent
of the MDD.
Weather Considerations
Disturbance of near-surface soils should be expected if earthwork is completed during periods of wet
weather. During dry weather, the soils will: (1) be less susceptible to disturbance, (2) provide better support
for construction equipment, and (3) be more likely to meet the required compaction criteria.
The wet weather season generally begins in October and continues through May in western Washington;
however, periods of wet weather may occur during any month of the year. For earthwork activities during
wet weather, we recommend that the following steps be taken:
■ The ground surface in and around the work area should be sloped so that surface water is directed
away from the work area. The ground surface should be graded so that areas of ponded water do not
develop. Measures should be taken by the contractor to prevent surface water from collecting in
excavations and trenches. Measures should be implemented to remove surface water from the work
area.
■ Earthwork activities should not take place during periods of moderate to heavy precipitation.
■ Slopes with exposed soils should be covered with plastic sheeting.
November 15, 2018 | Page 12 File No. 23656-001-00
■ The contractor should take necessary measures to prevent on-site soils and soils to be used as fill from
becoming wet or unstable. These measures may include the use of plastic sheeting, sumps with pumps,
and grading. The site soils should not be left uncompacted and exposed to moisture. Sealing the
surficial soils by rolling with a smooth-drum roller prior to periods of precipitation will help reduce the
extent that these soils become wet or unstable.
■ The contractor should cover all soil stockpiles that will be used as structural fill with plastic sheeting.
■ Construction traffic should be restricted to specific areas of the site, preferably areas that are surfaced
with the existing asphalt or working pad materials not susceptible to wet weather disturbance.
■ Construction activities should be scheduled so that the length of time that soils are left exposed to
moisture is reduced to the extent practical.
Routing of equipment on the existing fill and native till subgrade soils during the wet weather months will
be difficult and the subgrade will likely become highly disturbed and rutted. In addition, a significant amount
of mud can be produced by routing equipment directly on the glacial soils in wet weather. Therefore, to
protect the subgrade soils and to provide an adequate wet weather working surface for the contractor’s
equipment and labor, we recommend that the contractor protect exposed subgrade soils with sand and
gravel, crushed gravel, or ATB.
Permanent Cut and Fill Slopes
We recommend that permanent cut or fill slopes be constructed at inclinations of 2H:1V or flatter, and be
blended into existing slopes with smooth transitions. To achieve uniform compaction, we recommend that
fill slopes be overbuilt slightly and subsequently cut back to expose well compacted fill. It is our experience
that permanent cut slopes made in dense to very dense glacial till are difficult to establish vegetation on
and difficult to place and maintain topsoil on. Therefore, 3H:1V or flatter permanent cut slopes should be
considered for landscape purposes if site conditions allow for their use.
To reduce erosion, newly constructed slopes should be planted or hydroseeded shortly after completion of
grading. Until the vegetation is established, some sloughing and raveling of the slopes should be expected.
This may necessitate localized repairs and reseeding. Temporary covering, such as clear heavy plastic
sheeting, jute fabric, or erosion control blankets (such as American Excelsior Curlex 1 or North American
Green SC150) could be used to protect the slopes during periods of rainfall.
Utility Trenches
Trench excavation, pipe bedding, and trench backfilling should be completed using the general procedures
described in the 2018 WSDOT Standard Specifications or other suitable procedures specified by the project
civil engineer. The native glacial deposits and fill soils encountered at the site are generally of low corrosivity
based on our experience in the Puget Sound area.
Utility trench backfill should consist of structural fill and should be placed in loose lifts not exceeding
12 inches in thickness when using heavy compaction equipment and not more than 6 inches when using
hand-operated compaction equipment such that adequate compaction can be achieved throughout the lift.
Each lift must be compacted prior to placing the subsequent lift. The backfill should be compacted in
accordance with the criteria discussed above. Figure 3 illustrates recommended trench compaction criteria
under pavement and non-structural areas.
November 15, 2018 | Page 13 File No. 23656-001-00
Sedimentation and Erosion Control
In our opinion, the erosion potential of the on-site soils is low to moderate. Construction activities including
stripping and grading will expose soils to the erosional effects of wind and water. The amount and potential
impacts of erosion are partly related to the time of year that construction actually occurs. Wet weather
construction will increase the amount and extent of erosion and potential sedimentation.
Erosion and sedimentation control measures may be implemented by using a combination of interceptor
swales, straw bale barriers, silt fences and straw mulch for temporary erosion protection of exposed soils.
All disturbed areas should be finish graded and seeded as soon as practicable to reduce the risk of erosion.
Erosion and sedimentation control measures should be installed and maintained in accordance with the
requirements of the City of Renton.
Excavations
We anticipate that excavations are limited and will be primarily associated with footing excavations and
underground utilities. These cuts can likely be made as temporary open cut slopes depending on site
constraints. The stability of open cut slopes is a function of soil type, groundwater seepage, slope
inclination, slope height and nearby surface loads. The use of inadequately designed open cuts could
impact the stability of adjacent work areas, existing utilities, and endanger personnel.
The contractor performing the work has the primary responsibility for protection of workmen and adjacent
improvements. In our opinion, the contractor will be in the best position to observe subsurface conditions
continuously throughout the construction process and to respond to variable soil and groundwater
conditions. Therefore, the contractor should have the primary responsibility for deciding whether or not to
use open cut slopes for much of the excavations rather than some form of temporary excavation support,
and for establishing the safe inclination of the cut slope. Acceptable slope inclinations for utilities and
ancillary excavations should be determined during construction. Because of the diversity of construction
techniques and available shoring systems, the design of temporary shoring is most appropriately left up to
the contractor proposing to complete the installation. Temporary cut slopes and shoring must comply with
the provisions of Title 296 WAC, Part N, “Excavation, Trenching and Shoring.”
The excavations for the buildings and utilities will be completed primarily in loose to medium dense fill and
dense to very dense glacial till deposits. The following sections summarize the general excavation
recommendations.
Temporary Cut Slopes
For planning purposes, temporary unsupported cut slopes more than 4 feet high may be inclined at 1H:1V
maximum steepness within the dense to very dense glacial till (below a depth of about 3 feet) and 1½H:IV
maximum steepness in the overlying fill (upper 3 feet). If significant seepage is present on the cut face then
the cut slopes may have to be flattened. However, temporary cuts should be discussed with the
geotechnical engineer during final design development to evaluate suitable cut slope inclinations for the
various portions of the excavation. The contractor should scale slopes cut at 1H:1V to remove loose
materials and cobbles.
The above guidelines assume that surface loads such as traffic, construction equipment, stockpiles or
building supplies will be kept away from the top of the cut slopes a sufficient distance so that the stability
November 15, 2018 | Page 14 File No. 23656-001-00
of the excavation is not affected. We recommend that this distance be at least 5 feet from the top of the
cut for temporary cuts made at 1H:1V or flatter, and no closer than a distance equal to one-half the height
of the slope for cuts made steeper than 1H:IV.
Water that enters the excavation must be collected and routed away from prepared subgrade areas. We
expect that this may be accomplished by installing a system of drainage ditches and sumps along the toe
of the cut slopes. Some sloughing and raveling of the cut slopes should be expected. Temporary covering,
such as heavy plastic sheeting with appropriate ballast, should be used to protect these slopes during
periods of wet weather. Surface water runoff from above cut slopes should be prevented from flowing over
the slope face by using berms, drainage ditches, swales or other appropriate methods.
If temporary cut slopes experience excessive sloughing or raveling during construction, it may become
necessary to modify the cut slopes to maintain safe working conditions. Slopes experiencing problems can
be flattened, regraded to add intermediate slope benches, or additional dewatering can be provided if the
poor slope performance is related to groundwater seepage.
Drainage Considerations
We anticipate shallow groundwater seepage may enter excavations for utilities depending on the time of
year construction takes place, especially in the winter months. However, we expect that this seepage water
can be handled by digging interceptor trenches in the excavations and pumping from sumps. The seepage
water, if not intercepted and removed from the excavations, will make it difficult to place and compact
structural fill and may destabilize cut slopes.
All paved and landscaped areas should be graded so that surface drainage is directed away from the
buildings to appropriate catch basins.
Water collected in roof downspout lines must not be routed to the footing drain lines. Collected downspout
water should be routed to appropriate discharge points in separate pipe systems.
Infiltration Considerations
Sieve analyses were performed on selected soil samples collected from the test pits that were completed
as part of this study. The soil samples typically consisted of native weathered or relatively unweathered
glacial till. The design infiltration value described below is based on the results of the grain size analyses,
the United States Department of Agriculture (USDA) Textural Triangle, and the Washington State
Department of Ecology Storm Water Management Manual (2005). The grain size analyses are presented
in Appendix B.
Based on our analysis, it is our opinion that the on-site native glacial till soils have a very low infiltration
capacity. The majority of the soils across the site contain significant fines, which limits the infiltration
capacity. The results of the sieve analyses indicated that the fines content (material passing the U.S.
No. 200 sieve) typically ranges from 30 to 35 percent. Due to the density, high fines content, and relative
impermeability of the glacial till, infiltration should be assumed to be very low when designing infiltration
systems. We recommend a preliminary infiltration rate of not more than 0.2 inches per hour be used for
design of the infiltration facilities. Depending on the depth of proposed infiltration facilities, the infiltration
rate will vary; however, we recommend site specific pilot infiltration testing be performed to determine the
design infiltration rate if specific infiltration facilities are being considered.
November 15, 2018 | Page 15 File No. 23656-001-00
RECOMMENDED ADDITIONAL GEOTECHNICAL SERVICES
Throughout this report, recommendations are provided where we consider additional geotechnical services
to be appropriate. These additional services are summarized below:
■ GeoEngineers should be retained to review the project plans and specifications when complete to
confirm that our design recommendations have been implemented as intended.
■ During construction, GeoEngineers should observe and evaluate the suitability of the foundation
subgrades, evaluate the suitability of floor slab and pavement subgrades, observe installation of
subsurface drainage measures including footing drains, observe and test structural backfill, and
provide a summary letter of our construction observation services. The purposes of GeoEngineers
construction phase services are to confirm that the subsurface conditions are consistent with those
observed in the explorations and other reasons described in Appendix D, Report Limitations and
Guidelines for Use.
LIMITATIONS
We have prepared this report for use by Homestead Community Land Trust and members of the project
team for use in design of this project.
Within the limitations of scope, schedule and budget, our services have been executed in accordance with
generally accepted practices in the field of geotechnical engineering in this area at the time this report was
prepared. No warranty or other conditions, express or implied, should be understood.
Please refer to Appendix D for additional information pertaining to use of this report.
REFERENCES
International Code Council, 2015, “International Building Code.”
Mullineaux, D. R., 1965, “Geologic Map of the Renton Quadrangle, King County, Washington.”
Soil & Environmental Engineers, Inc., 2011, “Report of Geotechnical Investigation, Proposed Residential
Development, Edmonds and Glennwood Ave NE, Renton, Washington.”
United States Geological Survey – Earthquake Hazards Program Software, “U.S. Seismic Design Maps,”
2008 data, 2012/2015 IBC, https://earthquake.usgs.gov/designmaps/us/application.php.
Washington State Department of Transportation, 2018, “Standard Specifications for Road, Bridge and
Municipal Construction.”
FIGURES
µ
SITE
Vicinity Map
Figure 1
Willow Crest Townhomes Renton, Washington
2,000 2,0000
Feet
Data Source: Mapbox Open Street Map, 2018
Notes:1. The locations of all features shown are approximate.2. This drawing is for information purposes. It is intended to assist inshowing features discussed in an attached document. GeoEngineers, Inc.cannot guarantee the accuracy and content of electronic files. The masterfile is stored by GeoEngineers, Inc. and will serve as the official record ofthis communication.
Projection: NAD 1983 UTM Zone 10N
P:\23\23656001\GIS\2365600100_F01_VicinityMap.mxd Date Exported: 10/17/18 by cchelf
310315320325 33
0 335340 345308309311312313314316317318319321322
323324326
32
7 3283293313323
3
3 33433633733833934134234
3
3
4
4 34630531031532032533033534
0
34534530
1
3
0
230
3 304306307308309311312313314316317 3183193213223233243263
2
7
3
2
8
32
9 3313323333
3
4 336337338339341342343344345344346
3
4
3 3443
2
0
325 330335340318
319 321322
323
324 32632732832933133233333433433433
6 33733733
7
33
8 33934
1
34
2342342
343
295
300
30
5
3
1
0
292
293
29429
6
297
298
299
301
302
30
3
30
4
30
63073
0
8
30
9
311
312
310
31
5 3203253303353
4
0
3
4
5
30931131
2313
31
4
31
6 31731831932132232332432632
7 3283293313323333343363373
3
8
3
3
9
3413423433
4
4
34
6
347
34034134234334534334434534634534234
3 34434634
7
34
7347
347347346347347
3
4
7
Edmonds Ave NEGlenwood Ave NEGEI-TP-1
GEI-TP-2
GEI-TP-3
GEI-TP-4
GEI-TP-5
GEI-TP-6
B-1
B-2
TP-1
TP-2
TP-3
TP-4 TP-5
TP-6
Figure 2
Site Plan - Proposed Development
Willow Crest Townhomes Renton,
Washington
W E
N
S
P:\23\23656001\CAD\00\GeoTech\2365600100_F02_Site Plan.dwg TAB:F02 Date Exported: 10/31/18 - 10:19 by hmaraLegendNotes:
1. The locations of all features shown are approximate.
2. This drawing is for information purposes. It is intended to
assist in showing features discussed in an attached document.
GeoEngineers, Inc. cannot guarantee the accuracy and content
of electronic files. The master file is stored by GeoEngineers,
Inc. and will serve as the official record of this communication.
Data Source: Base survey by Lank Tree Land Surveying dated
10/17/18. Proposed site features from Third Place Design
Co-Operative dated 10/7/18.
Projection: WA State Plane, North Zone, NAD83, US Foot Feet
040 40
Test Pit by GeoEngineers, 2018 (Current Study)GEI-TP-1
Boring by Soil & Environmental Engineers, 2011B-1
Test Pit by Soil & Environmental Engineers, 2011TP-1
Site Boundary
4 Unit
Town Homes
4 Unit
Town Homes
4 Unit
Town Homes
Figure 3
P:\23\23656001\CAD\00\GeoTech\2365600100_F03_Compaction Criteria.dwg TAB:F03 Date Exported: 10/19/18 - 13:02 by hmara95
90 90
9590
Pipe
Varies
Varies
(See Note 1)
2 Feet
Varies
(Modified Proctor)
Pipe Bedding
Trench Backfill
Base Course
Concrete or Asphalt Pavement
Maximum Dry Density, by Test Method ASTM D1557
Recommended Compaction as a Percentage of
Legend
95
Notes:
1. All backfill under building areas should be compacted to at
least 95 percent per ASTM D1557.
Non-structural
Areas
Hardscape Or
Pavement
Areas
Ground Surface
Not To Scale
Compaction Criteria
for Trench Backfill
Willow Crest Townhomes
Renton, Washington
APPENDICES
APPENDIX A Field Explorations
November 15, 2018 | Page A-1 File No. 23656-001-00
APPENDIX A
FIELD EXPLORATIONS
Subsurface soil and groundwater conditions were evaluated by completing six test pits (GEI-TP-1 through
GEI-TP-6) at the approximate locations shown on Figure 2, Site Plan. Locations of the test pits were
determined in the field by pacing and tape measuring distances from the test pit locations to existing site
features. Ground surface elevations were interpolated from a site topographic map.
Test pits (GEI-TP-1 through GEI-TP-6) were completed on October 22, 2018 at the approximate locations
shown on Figure 2. The test pits were excavated to depths of about 8 feet below the existing ground surface
(bgs). The test pits were completed using a mini rubber track mounted Takeuchi TB138BFR excavator
owned and operated by Kelly’s Excavating.
The test pits were continuously monitored by a geotechnical engineer from our firm who evaluated and
classified the soils encountered, obtained representative soil samples, and observed groundwater
conditions (if present). Our representative maintained a detailed log of each test pit. Disturbed samples of
representative soil types were obtained from the excavator bucket at representative depths.
Soils encountered in the test pits were classified in the field in general accordance with ASTM D 2488, the
Standard Practice for Classification of Soils, Visual-Manual Procedure, which is summarized in Figure A-1.
Logs of the test pits are provided in Figures A-2 through A-7.
Measured groundwater level in exploration,well, or piezometer
Measured free product in well or piezometer
Distinct contact between soil strata
Approximate contact between soil strata
Contact between geologic units
SYMBOLS TYPICAL
DESCRIPTIONS
GW
GP
SW
SP
SM
FINEGRAINED
SOILS
SILTS ANDCLAYS
NOTE: Multiple symbols are used to indicate borderline or dual soil classifications
MORE THAN 50%RETAINED ONNO. 200 SIEVE
MORE THAN 50%PASSINGNO. 200 SIEVE
GRAVEL
ANDGRAVELLYSOILS
SC
LIQUID LIMITLESS THAN 50
(APPRECIABLE AMOUNTOF FINES)
(APPRECIABLE AMOUNTOF FINES)
COARSEGRAINEDSOILS
MAJOR DIVISIONS GRAPH LETTER
GM
GC
ML
CL
OL
SILTS AND
CLAYS
SANDS WITHFINES
SANDANDSANDY
SOILS
MH
CH
OH
PT
(LITTLE OR NO FINES)
CLEAN SANDS
GRAVELS WITHFINES
CLEAN GRAVELS
(LITTLE OR NO FINES)
WELL-GRADED GRAVELS, GRAVEL -SAND MIXTURES
CLAYEY GRAVELS, GRAVEL - SAND -CLAY MIXTURES
WELL-GRADED SANDS, GRAVELLYSANDS
POORLY-GRADED SANDS, GRAVELLYSAND
SILTY SANDS, SAND - SILT MIXTURES
CLAYEY SANDS, SAND - CLAYMIXTURES
INORGANIC SILTS, ROCK FLOUR,CLAYEY SILTS WITH SLIGHTPLASTICITY
INORGANIC CLAYS OF LOW TOMEDIUM PLASTICITY, GRAVELLYCLAYS, SANDY CLAYS, SILTY CLAYS,LEAN CLAYS
ORGANIC SILTS AND ORGANIC SILTYCLAYS OF LOW PLASTICITY
INORGANIC SILTS, MICACEOUS ORDIATOMACEOUS SILTY SOILS
INORGANIC CLAYS OF HIGHPLASTICITY
ORGANIC CLAYS AND SILTS OFMEDIUM TO HIGH PLASTICITY
PEAT, HUMUS, SWAMP SOILS WITHHIGH ORGANIC CONTENTSHIGHLY ORGANIC SOILS
SOIL CLASSIFICATION CHART
MORE THAN 50%OF COARSEFRACTION RETAINEDON NO. 4 SIEVE
MORE THAN 50%OF COARSEFRACTION PASSINGON NO. 4 SIEVE
SILTY GRAVELS, GRAVEL - SAND -SILT MIXTURES
POORLY-GRADED GRAVELS,GRAVEL - SAND MIXTURES
LIQUID LIMIT GREATERTHAN 50
Continuous Coring
Bulk or grab
Direct-Push
Piston
Shelby tube
Standard Penetration Test (SPT)
2.4-inch I.D. split barrel
Contact between soil of the same geologicunit
Material Description Contact
Graphic Log Contact
NOTE: The reader must refer to the discussion in the report text and the logs of explorations for a proper understanding of subsurface conditions.Descriptions on the logs apply only at the specific exploration locations and at the time the explorations were made; they are not warranted to berepresentative of subsurface conditions at other locations or times.
Groundwater Contact
Blow count is recorded for driven samplers as the number of blows required to advance sampler 12 inches (or distance noted). See exploration log for hammer weight and drop.
"P" indicates sampler pushed using the weight of the drill rig.
"WOH" indicates sampler pushed using the weight of the hammer.
Key to Exploration Logs
Figure A-1
Sampler Symbol Descriptions
ADDITIONAL MATERIAL SYMBOLS
NSSSMSHS
No Visible SheenSlight SheenModerate SheenHeavy Sheen
Sheen Classification
SYMBOLS
Asphalt Concrete
Cement Concrete
Crushed Rock/Quarry Spalls
Topsoil
GRAPH LETTER
AC
CC
SOD Sod/Forest Duff
CR
DESCRIPTIONS
TYPICAL
TS
Laboratory / Field Tests
%F%GALCACPCSDDDSHAMCMDMohsOCPMPIPPSATXUCVS
Percent finesPercent gravelAtterberg limitsChemical analysisLaboratory compaction testConsolidation testDry densityDirect shearHydrometer analysisMoisture contentMoisture content and dry densityMohs hardness scaleOrganic contentPermeability or hydraulic conductivityPlasticity indexPocket penetrometerSieve analysisTriaxial compressionUnconfined compressionVane shear
Rev 06/2017
Blackberry brambles
Dark brown fine to medium sand with silt, occasional gravel, roots(loose, moist) (fill)
Light brown silty fine to medium sand with gravel, occasional cobbles,trace roots (medium dense, moist) (weathered glacial till)
Gray silty fine to medium sand with gravel (very dense, moist) (glacialtill)
WD
SP-SM
SM
SM
1SA
2%F
3
4
4
3
Pocket Pen / Probe Penetration
0.0 kg/cm2 / 6 inches
0.5 kg/cm2 / 4 inches
>4.5 kg/cm2 / ½ inch
>4.5 kg/cm2 / <½ inch
21
30
Notes: See Figure A-1 for explanation of symbols.The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to ½ foot.Coordinates Data Source: Horizontal approximated based on Aerial Imagery. Vertical approximated based on Google Earth.Date:11/5/18 Path:W:\PROJECTS\23\23656001\GINT\2365600100.GPJ DBLibrary/Library:GEOENGINEERS_DF_STD_US_JUNE_2017.GLB/GEI8_TESTPIT_1P_GEOTEC_%FSheet 1 of 1Project Number:
Project Location:
Project:
Renton, Washington
23656-001-00
Log of Test Pit GEI-TP-1
Willow Crest Townhomes
Figure A-2Elevation (feet)339338337336335334333332Depth (feet)1
2
3
4
5
6
7
8 Testing SampleGraphic LogSAMPLE
MATERIAL
DESCRIPTION
GroupClassificationSample NameTestingMoistureContent (%)REMARKS
FinesContent (%)DateExcavated
Surface Elevation (ft)Vertical Datum Coordinate SystemHorizontal DatumEasting (X)Northing (Y)
TotalDepth (ft)10/22/2018 8
340NAVD88 1306462186084 WA State Plane NorthNAD83 (feet)
AJF
Checked By MAG
Groundwater not observed
Caving not observedEquipment Takeuchi TB138FR
Logged By Excavator Kelly's Excavating, Inc.
Blackberry brambles
Dark brown fine to medium sand with silt, roots (loose, moist) (fill)
Brown silty coarse gravel with sand and occasional cobbles, roots(medium dense to dense, moist) (weathered glacial till)
No roots below 2 feet
Gray silty fine sand with occasional gravel and cobbles (very dense,moist) (glacial till)
WD
SP-SM
GM
SM
1SA
2
3
4
3
Pocket Pen / Probe Penetration
0.0 kg/cm2 / 8 inches
1.0 kg/cm2 / 3 inches
>4.5 kg/cm2 / 1 inch
>4.5 kg/cm2 / ¼ inch
17
Notes: See Figure A-1 for explanation of symbols.The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to ½ foot.Coordinates Data Source: Horizontal approximated based on Aerial Imagery. Vertical approximated based on Google Earth.Date:11/5/18 Path:W:\PROJECTS\23\23656001\GINT\2365600100.GPJ DBLibrary/Library:GEOENGINEERS_DF_STD_US_JUNE_2017.GLB/GEI8_TESTPIT_1P_GEOTEC_%FSheet 1 of 1Project Number:
Project Location:
Project:
Renton, Washington
23656-001-00
Log of Test Pit TEI-TP-2
Willow Crest Townhomes
Figure A-3Elevation (feet)339338337336335334333332Depth (feet)1
2
3
4
5
6
7
8 Testing SampleGraphic LogSAMPLE
MATERIAL
DESCRIPTION
GroupClassificationSample NameTestingMoistureContent (%)REMARKS
FinesContent (%)DateExcavated
Surface Elevation (ft)Vertical Datum Coordinate SystemHorizontal DatumEasting (X)Northing (Y)
TotalDepth (ft)10/22/2018 8
340NAVD88 1306453186046 WA State Plane NorthNAD83 (feet)
AJF
Checked By MAG
Groundwater not observed
Caving not observedEquipment Takeuchi TB138FR
Logged By Excavator Kelly's Excavating, Inc.
Blackberry brambles
Dark brown fine to medium sand with silt and occasional gravel, roots(loose, moist) (fill)
Light brown silty fine sand with gravel and occasional cobbles, roots(loose to medium dense, moist) (weathered glacial till)
No roots below 2 feet
Light gray silty fine to medium sand with occasional gravel and cobbles(very dense, moist) (glacial till)
Gray fine to medium sand with silt, gravel and occasional cobbles (verydense, moist)
WD
SP-SM
SM
SM
SP-SM
1SA
2
3
4
5
Pocket Pen / Probe Penetration
0.0 kg/cm2 / 12 inches
2.0 kg/cm2 / 3 inches
>4.5 kg/cm2 / ½ inch
>4.5 kg/cm2 / ¼ inch
32
Notes: See Figure A-1 for explanation of symbols.The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to ½ foot.Coordinates Data Source: Horizontal approximated based on Aerial Imagery. Vertical approximated based on Google Earth.Date:11/5/18 Path:W:\PROJECTS\23\23656001\GINT\2365600100.GPJ DBLibrary/Library:GEOENGINEERS_DF_STD_US_JUNE_2017.GLB/GEI8_TESTPIT_1P_GEOTEC_%FSheet 1 of 1Project Number:
Project Location:
Project:
Renton, Washington
23656-001-00
Log of Test Pit GEI-TP-3
Willow Crest Townhomes
Figure A-4Elevation (feet)339338337336335334333332Depth (feet)1
2
3
4
5
6
7
8 Testing SampleGraphic LogSAMPLE
MATERIAL
DESCRIPTION
GroupClassificationSample NameTestingMoistureContent (%)REMARKS
FinesContent (%)DateExcavated
Surface Elevation (ft)Vertical Datum Coordinate SystemHorizontal DatumEasting (X)Northing (Y)
TotalDepth (ft)10/22/2018 8
340NAVD88 1306422185979 WA State Plane NorthNAD83 (feet)
AJF
Checked By MAG
Groundwater not observed
Caving not observedEquipment Takeuchi TB138FR
Logged By Excavator Kelly's Excavating, Inc.
Blackberry brambles
Dark brown fine to medium sand with silt and occasional gravel, roots(loose, moist) (fill)
Light brown silty fine sand with gravel and occasional cobbles (loose tomedium dense, moist) (weathered glacial till)
Light gray silty fine to medium sand with gravel and occasionalcobbles; partially cemented (very dense, moist) (glacial till)
Boulder encountered at 3½ feet
WD
SP-SM
SM
SM
1
2SA
3
4
6
Pocket Pen / Probe Penetration
0.0 kg/cm2 / 12 inches
2.25 kg/cm2 / 4 inches
>4.5 kg/cm2 / 1 inch
>4.5 kg/cm2 / ¼ inch
35
Notes: See Figure A-1 for explanation of symbols.The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to ½ foot.Coordinates Data Source: Horizontal approximated based on Aerial Imagery. Vertical approximated based on Google Earth.Date:11/5/18 Path:W:\PROJECTS\23\23656001\GINT\2365600100.GPJ DBLibrary/Library:GEOENGINEERS_DF_STD_US_JUNE_2017.GLB/GEI8_TESTPIT_1P_GEOTEC_%FSheet 1 of 1Project Number:
Project Location:
Project:
Renton, Washington
23656-001-00
Log of Test Pit GEI-TP-4
Willow Crest Townhomes
Figure A-5Elevation (feet)339338337336335334333332Depth (feet)1
2
3
4
5
6
7
8 Testing SampleGraphic LogSAMPLE
MATERIAL
DESCRIPTION
GroupClassificationSample NameTestingMoistureContent (%)REMARKS
FinesContent (%)DateExcavated
Surface Elevation (ft)Vertical Datum Coordinate SystemHorizontal DatumEasting (X)Northing (Y)
TotalDepth (ft)10/22/2018 8
340NAVD88 1306466185974 WA State Plane NorthNAD83 (feet)
AJF
Checked By MAG
Groundwater not observed
Caving not observedEquipment Takeuchi TB138FR
Logged By Excavator Kelly's Excavating, Inc.
Blackberry brambles
Brown fine to medium sand with silt and occasional gravel (loose,moist) (fill)
Light brown silty fine sand with gravel and cobbles, roots (loose tomedium dense, moist) (weathered glacial till)
Gray silty fine sand with gravel and occasional cobbles; partiallycemented (dense to very dense, moist) (glacial till)
WD
SP-SM
SM
SM
1%F
2
3
4
8
Pocket Pen / Probe Penetration
0.0 kg/cm2 / 12 inches
1.5 kg/cm2 / 5 inches
2.5 kg/cm2 / 2 inches
>4.5 kg/cm2 / ¼ inch
26
Notes: See Figure A-1 for explanation of symbols.The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to ½ foot.Coordinates Data Source: Horizontal approximated based on Aerial Imagery. Vertical approximated based on Google Earth.Date:11/5/18 Path:W:\PROJECTS\23\23656001\GINT\2365600100.GPJ DBLibrary/Library:GEOENGINEERS_DF_STD_US_JUNE_2017.GLB/GEI8_TESTPIT_1P_GEOTEC_%FSheet 1 of 1Project Number:
Project Location:
Project:
Renton, Washington
23656-001-00
Log of Test Pit GEI-TP-5
Willow Crest Townhomes
Figure A-6Elevation (feet)339338337336335334333332Depth (feet)1
2
3
4
5
6
7
8 Testing SampleGraphic LogSAMPLE
MATERIAL
DESCRIPTION
GroupClassificationSample NameTestingMoistureContent (%)REMARKS
FinesContent (%)DateExcavated
Surface Elevation (ft)Vertical Datum Coordinate SystemHorizontal DatumEasting (X)Northing (Y)
TotalDepth (ft)10/22/2018 8
340NAVD88 1306422185911 WA State Plane NorthNAD83 (feet)
AJF
Checked By MAG
Groundwater not observed
Caving not observedEquipment Takeuchi TB138FR
Logged By Excavator Kelly's Excavating, Inc.
Blackberry brambles
Brown fine to medium sand with silt and occasional gravel (loose,moist) (fill)
Light brown silty fine to medium sand with gravel and cobbles, roots(loose to medium dense, moist) (weathered till)
Gray silty fine to medium sand with gravel and occasional cobbles(dense to very dense, moist) (glacial till)
WD
SP-SM
SM
SM
1
2SA
3
4
5
Pocket Pen / Probe Penetration
0.0 kg/cm2 / 12 inches
1.5 kg/cm2 / 5 inches
4.0 kg/cm2 / 1½ inches
>4.5 kg/cm2 / ¼ inch
33
Notes: See Figure A-1 for explanation of symbols.The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to ½ foot.Coordinates Data Source: Horizontal approximated based on Aerial Imagery. Vertical approximated based on Google Earth.Date:11/5/18 Path:W:\PROJECTS\23\23656001\GINT\2365600100.GPJ DBLibrary/Library:GEOENGINEERS_DF_STD_US_JUNE_2017.GLB/GEI8_TESTPIT_1P_GEOTEC_%FSheet 1 of 1Project Number:
Project Location:
Project:
Renton, Washington
23656-001-00
Log of Test Pit GEI-TP-6
Willow Crest Townhomes
Figure A-7Elevation (feet)339338337336335334333332Depth (feet)1
2
3
4
5
6
7
8 Testing SampleGraphic LogSAMPLE
MATERIAL
DESCRIPTION
GroupClassificationSample NameTestingMoistureContent (%)REMARKS
FinesContent (%)DateExcavated
Surface Elevation (ft)Vertical Datum Coordinate SystemHorizontal DatumEasting (X)Northing (Y)
TotalDepth (ft)10/22/2018 8
340NAVD88 1306474185878 WA State Plane NorthNAD83 (feet)
AJF
Checked By MAG
Groundwater not observed
Caving not observedEquipment Takeuchi TB138FR
Logged By Excavator Kelly's Excavating, Inc.
APPENDIX B Laboratory Testing
November 15, 2018 | Page B-1 File No. 23656-001-00
APPENDIX B
LABORATORY TESTING
Soil samples obtained from the test pits were transported to our laboratory and examined to confirm or
modify field classifications, as well as to evaluate engineering properties of the soil. Representative
samples were selected for laboratory testing consisting of moisture content, percent fines (material passing
the U.S. No. 200 sieve), grain size determinations (sieve analysis), and modified Proctor testing. The tests
were performed in general accordance with test methods of the ASTM International (ASTM) or other
applicable procedures.
Soil Classifications
Soil samples obtained from the test pits were visually classified in the field and/or in our laboratory using
a system based on the Unified Soil Classification System (USCS) and ASTM classification methods. ASTM
test method D 2488 was used to visually classify the soil samples, while ASTM D 2487 was used to classify
the soils based on laboratory tests results. These classification procedures are incorporated in the test pit
logs shown in Figures A-2 through A-7 in Appendix A.
Moisture Content Determinations
Moisture contents tests were completed in general accordance with ASTM D 2216 for representative
samples obtained from the test pits. The test results are presented on the test pit logs in Appendix A at the
respective sample depth.
Percent Fines Tests
Tests to evaluate the percent fines (particles passing the No. 200 sieve) were completed using
ASTM D 1140. The wet sieve method was used to determine the percentage of soil particles larger than
the U.S. No. 200 sieve opening. The results of the percent fines tests are presented on the test pit logs at
the depths at which the samples were obtained.
Sieve Analysis
Sieve analyses were performed on selected samples in general accordance with ASTM D 422. The wet
sieve analysis method was used to estimate the percentage of soil greater than the U.S. No. 200 mesh
sieve. The results of the sieve analyses were plotted, classified in general accordance with the USCS, and
presented on Figures B-1 and B-2.
Modified Proctor
The modified Proctor tests were completed in general accordance with ASTM D1557. The results of the
modified Proctor testing are presented on Figure B-3.
0
10
20
30
40
50
60
70
80
90
100
0.0010.010.11101001000PERCENT PASSING BY WEIGHT GRAIN SIZE IN MILLIMETERS
U.S. STANDARD SIEVE SIZE
SAND SILT OR CLAYCOBBLESGRAVEL
COARSE MEDIUM FINECOARSEFINE
Boring Number
Depth
(feet)Soil Description
TP-1
TP-2
TP-3
TP-4
2
2
1.5
4
Silty fine to medium sand with gravel (SM)
Silty coarse gravel with sand (GM)
Silty fine sand with gravel (SM)
Silty fine to medium sand with gravel (SM)
Symbol
Moisture
(%)
4
3
5
6
3/8”3”1.5”#4 #10 #20 #40 #60 #1003/4”Figure B-1Sieve Analysis ResultsWillow Crest Townhomes Renton, Washington23656-001-00 Date Exported: 10/31/18
Note:This report may not be reproduced,except in full,without written approval of GeoEngineers,Inc.Test results are applicable only to the specific sample on which they were
performed,and should not be interpretedas representativeof any other samples obtainedat othertimes,depths or locations,or generatedby separate operations orprocesses.
Thegrain size analysis results wereobtainedingeneral accordancewith ASTM D 6913.GeoEngineers 17425 NE Union Hill Road Ste 250,Redmond,WA 98052
#200
0
10
20
30
40
50
60
70
80
90
100
0.0010.010.11101001000PERCENT PASSING BY WEIGHT GRAIN SIZE IN MILLIMETERS
U.S. STANDARD SIEVE SIZE
SAND SILT OR CLAYCOBBLESGRAVEL
COARSE MEDIUM FINECOARSEFINE
Boring Number
Depth
(feet)Soil Description
TP-6 4 Silty fine to medium sand with gravel (SM)
Symbol
Moisture
(%)
5
3/8”3”1.5”#4 #10 #20 #40 #60 #1003/4”Figure B-2Sieve Analysis ResultsWillow Crest Townhomes Renton, Washington23656-001-00 Date Exported: 10/31/18
Note:This report may not be reproduced,except in full,without written approval of GeoEngineers,Inc.Test results are applicable only to the specific sample on which they were
performed,and should not be interpretedas representativeof any other samples obtainedat othertimes,depths or locations,or generatedby separate operations orprocesses.
Thegrain size analysis results wereobtainedingeneral accordancewith ASTM D 6913.GeoEngineers 17425 NE Union Hill Road Ste 250,Redmond,WA 98052
#200
Figure B-3
Compaction Test Results (TP-3)
Willow Crest Townhomes
Renton, Washington
23656-001-00 Date Exported: 10/30/18Note:This report may not be reproduced,except in full,without written approval
of GeoEngineers,Inc.Test results are applicable only to the specific
sample on which they were performed,and should not be interpreted as
representative of any other samples obtained at other times,depths or
locations,or generatedby separate operations orprocesses.
The Proctor results were obtained in general accordance with
ASTMD 1557.
Boring
Number Soil Description
Optimum
Moisture
(%)
Maximum
Dry Density
(pcf)
Uncorrected TP-3 Silty fine sand with gravel (SM)11.8 120.0
Symbol
100
105
110
115
120
125
130
135
140
0 5 10 15 20
MOISTURE CONTENT (%)DRY DENSITY (pcf)100%
Saturation
(Gs=2.65)
Depth
(feet)
1.5
APPENDIX C Boring and Test Pit Logs from Previous Studies
November 15, 2018 | Page C-1 File No. 23656-001-00
APPENDIX C
BORING AND TEST PIT LOGS FROM PREVIOUS STUDIES
Included in Appendix C are the boring and test pit logs from available previous studies completed in the
immediate vicinity of the project site.
■ The logs of two borings (B-1 and B-2) and six test pits (TP-1 through TP-6) completed by Soil and
Environmental Engineers, Inc., in 2010 for the Proposed Development at Edmonds Avenue NE and
Glennwood Avenue NE project.
APPENDIX D Report Limitations and Guidelines for Use
November 15, 2018 | Page D-1
File No. 23656-001-00
APPENDIX D
REPORT LIMITATIONS AND GUIDELINES FOR USE1
This appendix provides information to help you manage your risks with respect to the use of this report.
Geotechnical Services Are Performed for Specific Purposes, Persons and Projects
This report has been prepared for the exclusive use of Homestead Community Land Trust and other
project team members for the Willow Crest Townhomes project. This report is not intended for use by
others, and the information contained herein is not applicable to other sites.
GeoEngineers structures our services to meet the specific needs of our clients. For example, a geotechnical
or geologic study conducted for a civil engineer or architect may not fulfill the needs of a construction
contractor or even another civil engineer or architect that are involved in the same project. Because each
geotechnical or geologic study is unique, each geotechnical engineering or geologic report is unique,
prepared solely for the specific client and project site. Our report is prepared for the exclusive use of our
Client. No other party may rely on the product of our services unless we agree in advance to such reliance
in writing. This is to provide our firm with reasonable protection against open-ended liability claims by third
parties with whom there would otherwise be no contractual limits to their actions. Within the limitations of
scope, schedule and budget, our services have been executed in accordance with our Agreement with the
Client and generally accepted geotechnical practices in this area at the time this report was prepared. This
report should not be applied for any purpose or project except the one originally contemplated.
A Geotechnical Engineering or Geologic Report Is Based on a Unique Set of Project-specific
Factors
This report has been prepared for the Willow Crest Townhomes project in Renton, Washington.
GeoEngineers considered a number of unique, project-specific factors when establishing the scope of
services for this project and report. Unless GeoEngineers specifically indicates otherwise, do not rely on
this report if it was:
■not prepared for you,
■not prepared for your project,
■not prepared for the specific site explored, or
■completed before important project changes were made.
For example, changes that can affect the applicability of this report include those that affect:
■the function of the proposed structure;
■elevation, configuration, location, orientation or weight of the proposed structure;
1 Developed based on material provided by ASFE, Professional Firms Practicing in the Geosciences; www.asfe.org .
November 15, 2018 | Page D-2 File No. 23656-001-00
■ composition of the design team; or
■ project ownership.
If important changes are made after the date of this report, GeoEngineers should be given the opportunity
to review our interpretations and recommendations and provide written modifications or confirmation, as
appropriate.
Subsurface Conditions Can Change
This geotechnical or geologic report is based on conditions that existed at the time the study was performed.
The findings and conclusions of this report may be affected by the passage of time, by manmade events
such as construction on or adjacent to the site, or by natural events such as floods, earthquakes, slope
instability or groundwater fluctuations. Always contact GeoEngineers before applying a report to determine
if it remains applicable.
Most Geotechnical and Geologic Findings Are Professional Opinions
Our interpretations of subsurface conditions are based on field observations from widely spaced sampling
locations at the site. Site exploration identifies subsurface conditions only at those points where subsurface
tests are conducted or samples are taken. GeoEngineers reviewed field and laboratory data and then
applied our professional judgment to render an opinion about subsurface conditions throughout the site.
Actual subsurface conditions may differ, sometimes significantly, from those indicated in this report. Our
report, conclusions and interpretations should not be construed as a warranty of the subsurface conditions.
Geotechnical Engineering Report Recommendations Are Not Final
Do not over-rely on the preliminary construction recommendations included in this report. These
recommendations are not final, because they were developed principally from GeoEngineers’ professional
judgment and opinion. GeoEngineers’ recommendations can be finalized only by observing actual
subsurface conditions revealed during construction. GeoEngineers cannot assume responsibility or liability
for this report's recommendations if we do not perform construction observation.
Sufficient monitoring, testing and consultation by GeoEngineers should be provided during construction to
confirm that the conditions encountered are consistent with those indicated by the explorations, to provide
recommendations for design changes should the conditions revealed during the work differ from those
anticipated, and to evaluate whether or not earthwork activities are completed in accordance with our
recommendations. Retaining GeoEngineers for construction observation for this project is the most
effective method of managing the risks associated with unanticipated conditions.
A Geotechnical Engineering or Geologic Report Could Be Subject to Misinterpretation
Misinterpretation of this report by other design team members can result in costly problems. You could
lower that risk by having GeoEngineers confer with appropriate members of the design team after
submitting the report. Also retain GeoEngineers to review pertinent elements of the design team's plans
and specifications. Contractors can also misinterpret a geotechnical engineering or geologic report. Reduce
that risk by having GeoEngineers participate in pre-bid and preconstruction conferences, and by providing
construction observation.
November 15, 2018 | Page D-3 File No. 23656-001-00
Do Not Redraw the Exploration Logs
Geotechnical engineers and geologists prepare final boring and testing logs based upon their interpretation
of field logs and laboratory data. To prevent errors or omissions, the logs included in a geotechnical
engineering or geologic report should never be redrawn for inclusion in architectural or other design
drawings. Only photographic or electronic reproduction is acceptable, but recognize that separating logs
from the report can elevate risk.
Give Contractors a Complete Report and Guidance
Some owners and design professionals believe they can make contractors liable for unanticipated
subsurface conditions by limiting what they provide for bid preparation. To help prevent costly problems,
give contractors the complete geotechnical engineering or geologic report, but preface it with a clearly
written letter of transmittal. In that letter, advise contractors that the report was not prepared for purposes
of bid development and that the report's accuracy is limited; encourage them to confer with GeoEngineers
and/or to conduct additional study to obtain the specific types of information they need or prefer. A pre-bid
conference can also be valuable. Be sure contractors have sufficient time to perform additional study. Only
then might an owner be in a position to give contractors the best information available, while requiring them
to at least share the financial responsibilities stemming from unanticipated conditions. Further, a
contingency for unanticipated conditions should be included in your project budget and schedule.
Contractors Are Responsible for Site Safety on Their Own Construction Projects
Our geotechnical recommendations are not intended to direct the contractor’s procedures, methods,
schedule or management of the work site. The contractor is solely responsible for job site safety and for
managing construction operations to minimize risks to on-site personnel and to adjacent properties.
Read These Provisions Closely
Some clients, design professionals and contractors may not recognize that the geoscience practices
(geotechnical engineering or geology) are far less exact than other engineering and natural science
disciplines. This lack of understanding can create unrealistic expectations that could lead to
disappointments, claims and disputes. GeoEngineers includes these explanatory “limitations” provisions in
our reports to help reduce such risks. Please confer with GeoEngineers if you are unclear how these “Report
Limitations and Guidelines for Use” apply to your project or site.
Geotechnical, Geologic and Environmental Reports Should Not Be Interchanged
The equipment, techniques and personnel used to perform an environmental study differ significantly from
those used to perform a geotechnical or geologic study and vice versa. For that reason, a geotechnical
engineering or geologic report does not usually relate any environmental findings, conclusions or
recommendations; e.g., about the likelihood of encountering underground storage tanks or regulated
contaminants. Similarly, environmental reports are not used to address geotechnical or geologic concerns
regarding a specific project.
November 15, 2018 | Page D-4 File No. 23656-001-00
Biological Pollutants
GeoEngineers’ Scope of Work specifically excludes the investigation, detection, prevention or assessment
of the presence of Biological Pollutants. Accordingly, this report does not include any interpretations,
recommendations, findings, or conclusions regarding the detecting, assessing, preventing or abating of
Biological Pollutants and no conclusions or inferences should be drawn regarding Biological Pollutants, as
they may relate to this project. The term “Biological Pollutants” includes, but is not limited to, molds, fungi,
spores, bacteria, and viruses, and/or any of their byproducts.
If Client desires these specialized services, they should be obtained from a consultant who offers services
in this specialized field.
Appendix E
Operations and Maintenance Manual
APPENDIX A MAINTENANCE REQUIREMENTS FOR STORMWATER FACILITIES AND ON-SITE BMPS
12/12/2016 2017 City of Renton Surface Water Design Manual A-6
NO. 3 – DETENTION TANKS AND VAULTS
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITIONS WHEN
MAINTENANCE IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
Site Trash and debris Any trash and debris which exceed 1 cubic foot per 1,000 square feet (this is about equal to the amount of trash it would take to fill up one standard size office garbage can). In general, there should be no visual evidence of dumping.
Trash and debris cleared from site.
Noxious weeds Any noxious or nuisance vegetation which may constitute a hazard to City personnel or the public.
Noxious and nuisance vegetation removed according to applicable regulations. No danger of noxious vegetation where City personnel or the public might normally be.
Contaminants and pollution Any evidence of contaminants or pollution such as oil, gasoline, concrete slurries or paint.
Materials removed and disposed of according to applicable regulations. Source control BMPs implemented if appropriate. No contaminants present other than a surface oil film.
Excessive growth of grass/groundcover Grass or groundcover exceeds 18 inches in height. Grass or groundcover mowed to a height no greater than 6 inches.
Tank or Vault Storage Area Trash and debris Any trash and debris accumulated in vault or tank (includes floatables and non-floatables).
No trash or debris in vault.
Sediment accumulation Accumulated sediment depth exceeds 10% of the diameter of the storage area for ½ length of storage vault or any point depth exceeds 15% of diameter. Example:
72-inch storage tank would require cleaning when sediment reaches depth of 7 inches for more than ½ length of tank.
All sediment removed from storage area.
Tank Structure Plugged air vent Any blockage of the vent. Tank or vault freely vents.
Tank bent out of shape Any part of tank/pipe is bent out of shape more than 10% of its design shape. Tank repaired or replaced to design.
Gaps between sections, damaged
joints or cracks or tears in wall
A gap wider than ½-inch at the joint of any tank sections or any evidence of soil
particles entering the tank at a joint or through a wall.
No water or soil entering tank through joints or walls.
Vault Structure Damage to wall, frame, bottom, and/or top slab
Cracks wider than ½-inch, any evidence of soil entering the structure through cracks or qualified inspection personnel determines that the vault is not structurally sound.
Vault is sealed and structurally sound.
Inlet/Outlet Pipes Sediment accumulation Sediment filling 20% or more of the pipe. Inlet/outlet pipes clear of sediment.
Trash and debris Trash and debris accumulated in inlet/outlet pipes (includes floatables and non-floatables).
No trash or debris in pipes.
Damaged inlet/outlet pipes Cracks wider than ½-inch at the joint of the inlet/outlet pipes or any evidence of soil entering at the joints of the inlet/outlet pipes.
No cracks more than ¼-inch wide at the joint of the inlet/outlet pipe.
Access Manhole Cover/lid not in place Cover/lid is missing or only partially in place. Any open manhole requires immediate maintenance.
Manhole access covered.
APPENDIX A MAINTENANCE REQUIREMENTS FOR STORMWATER FACILITIES AND ON-SITE BMPS
2017 City of Renton Surface Water Design Manual 12/12/2016 A-7
NO. 3 – DETENTION TANKS AND VAULTS
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITIONS WHEN
MAINTENANCE IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
Access Manhole (cont.) Locking mechanism not working Mechanism cannot be opened by one maintenance person with proper tools. Bolts cannot be seated. Self-locking cover/lid does not work.
Mechanism opens with proper tools.
Cover/lid difficult to remove One maintenance person cannot remove cover/lid after applying 80 lbs of lift. Cover/lid can be removed and reinstalled by one maintenance person.
Ladder rungs unsafe Missing rungs, misalignment, rust, or
cracks.
Ladder meets design standards. Allows
maintenance person safe access.
Large access
doors/plate
Damaged or difficult
to open
Large access doors or plates cannot be
opened/removed using normal equipment.
Replace or repair access door so it can
opened as designed.
Gaps, doesn't cover completely Large access doors not flat and/or access opening not completely covered. Doors close flat; covers access opening completely.
Lifting rings missing, rusted Lifting rings not capable of lifting weight of door or plate. Lifting rings sufficient to lift or remove door or plate.
APPENDIX A MAINTENANCE REQUIREMENTS FOR STORMWATER FACILITIES AND ON-SITE BMPS
12/12/2016 2017 City of Renton Surface Water Design Manual A-8
NO. 4 – CONTROL STRUCTURE/FLOW RESTRICTOR
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITION WHEN MAINTENANCE
IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
Structure Trash and debris Trash or debris of more than ½ cubic foot which is located immediately in front of the structure opening or is blocking capacity of the structure by more than 10%.
No Trash or debris blocking or potentially blocking entrance to structure.
Trash or debris in the structure that exceeds 1/3 the depth from the bottom of basin to invert the lowest pipe into or out of the basin.
No trash or debris in the structure.
Deposits of garbage exceeding 1 cubic foot in volume. No condition present which would attract or support the breeding of insects or rodents.
Sediment accumulation Sediment exceeds 60% of the depth from the bottom of the structure to the invert of the lowest pipe into or out of the structure or the bottom of the FROP-T section or is
within 6 inches of the invert of the lowest pipe into or out of the structure or the bottom of the FROP-T section.
Sump of structure contains no sediment.
Damage to frame and/or top slab Corner of frame extends more than ¾ inch past curb face into the street (If applicable).
Frame is even with curb.
Top slab has holes larger than 2 square inches or cracks wider than ¼ inch. Top slab is free of holes and cracks.
Frame not sitting flush on top slab, i.e., separation of more than ¾ inch of the frame from the top slab.
Frame is sitting flush on top slab.
Cracks in walls or bottom Cracks wider than ½ inch and longer than 3 feet, any evidence of soil particles entering structure through cracks, or maintenance person judges that structure is unsound.
Structure is sealed and structurally sound.
Cracks wider than ½ inch and longer than 1 foot at the joint of any inlet/outlet pipe or
any evidence of soil particles entering structure through cracks.
No cracks more than 1/4 inch wide at the joint of inlet/outlet pipe.
Settlement/ misalignment Structure has settled more than 1 inch or has rotated more than 2 inches out of alignment.
Basin replaced or repaired to design standards.
Damaged pipe joints Cracks wider than ½-inch at the joint of the inlet/outlet pipes or any evidence of soil entering the structure at the joint of the inlet/outlet pipes.
No cracks more than ¼-inch wide at the joint of inlet/outlet pipes.
Contaminants and pollution Any evidence of contaminants or pollution such as oil, gasoline, concrete slurries or paint.
Materials removed and disposed of according to applicable regulations. Source control BMPs implemented if appropriate. No contaminants present other than a surface oil film.
Ladder rungs missing or unsafe Ladder is unsafe due to missing rungs, misalignment, rust, cracks, or sharp edges. Ladder meets design standards and allows maintenance person safe access.
FROP-T Section Damaged FROP-T T section is not securely attached to
structure wall and outlet pipe structure should support at least 1,000 lbs of up or down pressure.
T section securely attached to wall and
outlet pipe.
Structure is not in upright position (allow up to 10% from plumb). Structure in correct position.
APPENDIX A MAINTENANCE REQUIREMENTS FOR STORMWATER FACILITIES AND ON-SITE BMPS
2017 City of Renton Surface Water Design Manual 12/12/2016 A-9
NO. 4 – CONTROL STRUCTURE/FLOW RESTRICTOR
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITION WHEN MAINTENANCE
IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
FROP-T Section (cont.) Damaged FROP-T (cont.) Connections to outlet pipe are not watertight or show signs of deteriorated grout.
Connections to outlet pipe are water tight; structure repaired or replaced and works as designed.
Any holes—other than designed holes—in
the structure.
Structure has no holes other than designed
holes.
Cleanout Gate Damaged or missing cleanout gate Cleanout gate is missing. Replace cleanout gate.
Cleanout gate is not watertight. Gate is watertight and works as designed.
Gate cannot be moved up and down by one maintenance person. Gate moves up and down easily and is watertight.
Chain/rod leading to gate is missing or damaged. Chain is in place and works as designed.
Orifice Plate Damaged or missing
orifice plate
Control device is not working properly due
to missing, out of place, or bent orifice plate.
Plate is in place and works as designed.
Obstructions to orifice plate Any trash, debris, sediment, or vegetation blocking the plate. Plate is free of all obstructions and works as designed.
Overflow Pipe Obstructions to
overflow pipe
Any trash or debris blocking (or having the
potential of blocking) the overflow pipe.
Pipe is free of all obstructions and works
as designed.
Deformed or damaged lip of overflow pipe
Lip of overflow pipe is bent or deformed. Overflow pipe does not allow overflow at an elevation lower than design
Inlet/Outlet Pipe Sediment accumulation Sediment filling 20% or more of the pipe. Inlet/outlet pipes clear of sediment.
Trash and debris Trash and debris accumulated in
inlet/outlet pipes (includes floatables and non-floatables).
No trash or debris in pipes.
Damaged inlet/outlet
pipe
Cracks wider than ½-inch at the joint of the
inlet/outlet pipes or any evidence of soil entering at the joints of the inlet/outlet pipes.
No cracks more than ¼-inch wide at the
joint of the inlet/outlet pipe.
Metal Grates (If applicable) Unsafe grate opening Grate with opening wider than 7/8 inch. Grate opening meets design standards.
Trash and debris Trash and debris that is blocking more
than 20% of grate surface.
Grate free of trash and debris. footnote to
guidelines for disposal
Damaged or missing grate Grate missing or broken member(s) of the grate. Grate is in place and meets design standards.
Manhole Cover/Lid Cover/lid not in place Cover/lid is missing or only partially in place. Any open structure requires urgent maintenance.
Cover/lid protects opening to structure.
Locking mechanism
not working
Mechanism cannot be opened by one
maintenance person with proper tools. Bolts cannot be seated. Self-locking cover/lid does not work.
Mechanism opens with proper tools.
Cover/lid difficult to remove One maintenance person cannot remove cover/lid after applying 80 lbs. of lift. Cover/lid can be removed and reinstalled by one maintenance person.
APPENDIX A MAINTENANCE REQUIREMENTS FOR STORMWATER FACILITIES AND ON-SITE BMPS
12/12/2016 2017 City of Renton Surface Water Design Manual A-10
NO. 5 – CATCH BASINS AND MANHOLES
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITION WHEN MAINTENANCE
IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
Structure Sediment accumulation Sediment exceeds 60% of the depth from the bottom of the catch basin to the invert of the lowest pipe into or out of the catch basin or is within 6 inches of the invert of the lowest pipe into or out of the catch basin.
Sump of catch basin contains no sediment.
Trash and debris Trash or debris of more than ½ cubic foot which is located immediately in front of the catch basin opening or is blocking capacity of the catch basin by more than 10%.
No Trash or debris blocking or potentially blocking entrance to catch basin.
Trash or debris in the catch basin that exceeds 1/3 the depth from the bottom of basin to invert the lowest pipe into or out of the basin.
No trash or debris in the catch basin.
Dead animals or vegetation that could generate odors that could cause complaints or dangerous gases (e.g., methane).
No dead animals or vegetation present within catch basin.
Deposits of garbage exceeding 1 cubic foot in volume. No condition present which would attract or support the breeding of insects or rodents.
Damage to frame and/or top slab Corner of frame extends more than ¾ inch past curb face into the street (If applicable).
Frame is even with curb.
Top slab has holes larger than 2 square inches or cracks wider than ¼ inch. Top slab is free of holes and cracks.
Frame not sitting flush on top slab, i.e., separation of more than ¾ inch of the frame from the top slab.
Frame is sitting flush on top slab.
Cracks in walls or bottom Cracks wider than ½ inch and longer than 3 feet, any evidence of soil particles entering catch basin through cracks, or maintenance person judges that catch
basin is unsound.
Catch basin is sealed and is structurally sound.
Cracks wider than ½ inch and longer than 1 foot at the joint of any inlet/outlet pipe or any evidence of soil particles entering catch basin through cracks.
No cracks more than 1/4 inch wide at the joint of inlet/outlet pipe.
Settlement/ misalignment Catch basin has settled more than 1 inch or has rotated more than 2 inches out of alignment.
Basin replaced or repaired to design standards.
Damaged pipe joints Cracks wider than ½-inch at the joint of the inlet/outlet pipes or any evidence of soil entering the catch basin at the joint of the inlet/outlet pipes.
No cracks more than ¼-inch wide at the joint of inlet/outlet pipes.
Contaminants and pollution Any evidence of contaminants or pollution such as oil, gasoline, concrete slurries or paint.
Materials removed and disposed of according to applicable regulations. Source control BMPs implemented if appropriate. No contaminants present other than a surface oil film.
Inlet/Outlet Pipe Sediment accumulation Sediment filling 20% or more of the pipe. Inlet/outlet pipes clear of sediment.
Trash and debris Trash and debris accumulated in
inlet/outlet pipes (includes floatables and non-floatables).
No trash or debris in pipes.
APPENDIX A MAINTENANCE REQUIREMENTS FOR STORMWATER FACILITIES AND ON-SITE BMPS
2017 City of Renton Surface Water Design Manual 12/12/2016 A-11
NO. 5 – CATCH BASINS AND MANHOLES
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITION WHEN MAINTENANCE
IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
Inlet/Outlet Pipe (cont.) Damaged inlet/outlet pipe Cracks wider than ½-inch at the joint of the inlet/outlet pipes or any evidence of soil entering at the joints of the inlet/outlet pipes.
No cracks more than ¼-inch wide at the joint of the inlet/outlet pipe.
Metal Grates (Catch Basins) Unsafe grate opening Grate with opening wider than 7/8 inch. Grate opening meets design standards.
Trash and debris Trash and debris that is blocking more than 20% of grate surface. Grate free of trash and debris. footnote to guidelines for disposal
Damaged or missing grate Grate missing or broken member(s) of the grate. Any open structure requires urgent maintenance.
Grate is in place and meets design standards.
Manhole Cover/Lid Cover/lid not in place Cover/lid is missing or only partially in place. Any open structure requires urgent maintenance.
Cover/lid protects opening to structure.
Locking mechanism not working Mechanism cannot be opened by one maintenance person with proper tools. Bolts cannot be seated. Self-locking cover/lid does not work.
Mechanism opens with proper tools.
Cover/lid difficult to remove One maintenance person cannot remove cover/lid after applying 80 lbs. of lift. Cover/lid can be removed and reinstalled by one maintenance person.
APPENDIX A MAINTENANCE REQUIREMENTS FOR STORMWATER FACILITIES AND ON-SITE BMPS
12/12/2016 2017 City of Renton Surface Water Design Manual A-12
NO. 6 – CONVEYANCE PIPES AND DITCHES
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITIONS WHEN
MAINTENANCE IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
Pipes Sediment & debris accumulation Accumulated sediment or debris that exceeds 20% of the diameter of the pipe. Water flows freely through pipes.
Vegetation/root growth in pipe Vegetation/roots that reduce free movement of water through pipes. Water flows freely through pipes.
Contaminants and pollution Any evidence of contaminants or pollution such as oil, gasoline, concrete slurries or paint.
Materials removed and disposed of according to applicable regulations. Source control BMPs implemented if appropriate.
No contaminants present other than a surface oil film.
Damage to protective coating or corrosion Protective coating is damaged; rust or corrosion is weakening the structural integrity of any part of pipe.
Pipe repaired or replaced.
Damaged pipes Any dent that decreases the cross section area of pipe by more than 20% or is determined to have weakened structural integrity of the pipe.
Pipe repaired or replaced.
Ditches Trash and debris Trash and debris exceeds 1 cubic foot per 1,000 square feet of ditch and slopes. Trash and debris cleared from ditches.
Sediment accumulation Accumulated sediment that exceeds 20% of the design depth. Ditch cleaned/flushed of all sediment and debris so that it matches design.
Noxious weeds Any noxious or nuisance vegetation which may constitute a hazard to City personnel or the public.
Noxious and nuisance vegetation removed according to applicable regulations. No danger of noxious vegetation where City personnel or the public might normally be.
Contaminants and pollution Any evidence of contaminants or pollution such as oil, gasoline, concrete slurries or paint.
Materials removed and disposed of according to applicable regulations. Source control BMPs implemented if appropriate. No contaminants present other than a surface oil film.
Excessive vegetation growth Vegetation that reduces free movement of water through ditches. Water flows freely through ditches.
Erosion damage to
slopes
Any erosion observed on a ditch slope. Slopes are not eroding.
Rock lining out of place or missing (If applicable)
One layer or less of rock exists above native soil area 5 square feet or more, any exposed native soil.
Replace rocks to design standards.
APPENDIX A MAINTENANCE REQUIREMENTS FOR STORMWATER FACILITIES AND ON-SITE BMPS
12/12/2016 2017 City of Renton Surface Water Design Manual A-40
NO. 28 – NATIVE VEGETATED SURFACE/NATIVE VEGETATED LANDSCAPE BMP
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITION WHEN MAINTENANCE
IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
Site Trash and debris Trash and debris accumulated on the native vegetated surface/native vegetated landscape site.
Native vegetated surface site free of any trash or debris.
Vegetation Insufficient vegetation Less than two species each of native
trees, shrubs, and groundcover occur in the design area.
A minimum of two species each of native
trees, shrubs, and groundcover is established and healthy.
Poor vegetation
coverage
Less than 90% if the required vegetated
area has healthy growth.
A minimum of 90% of the required
vegetated area has healthy growth.
Undesirable
vegetation present
Weeds, blackberry, and other undesirable
plants are invading more than 10% of vegetated area.
Less than 10% undesirable vegetation
occurs in the required native vegetated surface area.
Vegetated Area Soil compaction Soil in the native vegetation area
compacted.
Less than 8% of native vegetation area is
compacted.
Insufficient vegetation Less than 3.5 square feet of native vegetation area for every 1 square foot of impervious surface.
A minimum of 3.5 square feet of native vegetation area for every 1 square foot of impervious surface.
Excess slope Slope of native vegetation area greater than 15%. Slope of native growth area does not exceed 15%.
NO. 29 – PERFORATED PIPE CONNECTIONS BMP
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITIONS WHEN
MAINTENANCE IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
Preventive Blocking, obstructions Debris or trash limiting flow into perforated pipe system or outfall of BMP is plugged or otherwise nonfunctioning.
Outfall of BMP is receiving designed flows from perforated pipe connection.
Inflow Inflow impeded Inflow into the perforated pipe is partially or fully blocked or altered to prevent flow from
getting into the pipe.
Inflow to the perforated pipe is unimpeded.
Pipe Trench Area Surface compacted Ground surface over the perforated pipe trench is compacted or covered with impermeable material.
Ground surface over the perforated pipe is not compacted and free of any impervious cover.
Outflow Outflow impeded Outflow from the perforated pipe into the
public drainage system is blocked.
Outflow to the public drainage system is
unimpeded.
Outfall Area Erosion or landslides Existence of the perforated pipe is causing or exasperating erosion or landslides. Perforated pipe system is sealed off and an alternative BMP is implemented.
APPENDIX A MAINTENANCE REQUIREMENTS FOR STORMWATER FACILITIES AND ON-SITE BMPS
2017 City of Renton Surface Water Design Manual 12/12/2016 A-41
NO. 30 – PERMEABLE PAVEMENT BMP
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITIONS WHEN
MAINTENANCE IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
Preventive Surface cleaning/ vegetation control Media surface vacuumed or pressure washed annually, vegetation controlled to design maximum. Weed growth suggesting sediment accumulation.
No dirt, sediment, or debris clogging porous media, or vegetation limiting infiltration.
Porous Concrete, Porous Asphaltic Concrete, and Permeable Pavers
Trash and debris Trash and debris on the pavement interfering with infiltration; leaf drop in fall season.
No trash or debris interfering with infiltration.
Sediment accumulation Sediment accumulation on the pavement interfering with infiltration; runoff from adjacent areas depositing sediment/debris on pavement.
Pavement infiltrates as designed; adjacent areas stabilized.
Insufficient infiltration rate Pavement does not infiltrate at a rate of 10 inches per hour. Pavement infiltrates at a rate greater than 10 inches per hour.
Excessive ponding Standing water for a long period of time on the surface of the pavement. Standing water infiltrates at the desired rate.
Broken or cracked pavement Pavement is broken or cracked. No broken pavement or cracks on the surface of the pavement.
Settlement Uneven pavement surface indicating settlement of the subsurface layer. Pavement surface is uniformly level.
Moss growth Moss growing on pavement interfering with infiltration. No moss interferes with infiltration.
Inflow restricted Inflow to the pavement is diverted,
restricted, or depositing sediment and debris on the pavement.
Inflow to pavement is unobstructed and not
bringing sediment or debris to the pavement.
Underdrain not freely flowing Underdrain is not flowing when pavement has been infiltrating water. Underdrain flows freely when water is present.
Overflow not
controlling excess water
Overflow not controlling excess water to
desired location; native soil is exposed or other signs of erosion damage are present.
Overflow permits excess water to leave the
site at the desired location; Overflow is stabilized and appropriately armored.
Permeable Pavers Broken or missing pavers Broken or missing paving blocks on surface of pavement. No missing or broken paving blocks interfering with infiltration.
Uneven surface Uneven surface due to settlement or scour of fill in the interstices of the paving blocks. Pavement surface is uniformly level.
Compaction Poor infiltration due to soil compaction
between paving blocks.
No soil compaction in the interstices of the
paver blocks limiting infiltration.
Poor vegetation growth (if applicable) Grass in the interstices of the paving blocks is dead. Healthy grass is growing in the interstices of the paver blocks.
Bioltration
SUBMITTAL PACKAGE
Oldcastle Infrastructure
(800) 579-8819
OldcastleStormwater.com
BIOPOD™
TABLE OF CONTENTS
1 - FEATURES & BENEFITS
2 - WA ECOLOGY GULD APPROVAL
3 - INSPECTION & MAINTENANCE
SECTION 1
FEATURES & BENEFITS
STORMWATER
BIOPOD™ SYSTEM WITH STORMMIX™ MEDIA
Sustainable Green Infrastructure for Stormwater Management
BioPod systems utilize an advanced biofiltration design for filtration,
sorption and biological uptake to remove Total Suspended Solids (TSS),
dissolved metals, nutrients, gross solids, trash and debris as well as
petroleum hydrocarbons from stormwater runoff. Environmentally friendly
and aesthetically pleasing, BioPod systems are a proven, Low-Impact
Development (LID) solution for stormwater treatment. BioPod systems
integrate seamlessly into standard site drainage and can accommodate
a wide variety of vegetation to meet green infrastructure requirements.
Stormwater Treatment,NATURALLY
STANDARD SIZES
BioPod units are available in many standard
and custom sizes to meet most site-specific
requirements. Contact your local Oldcastle
Infrastructure representative for additional
sizes.
4’ x 4’
4’ x 6’
4’ x 8’
4’ x 10’
6’ x 6’
6’ x 8’
6’ x 12’
8’ x 16’
BIORETENTION / BIOFILTRATION
BioPod systems use StormMix media, an engineered
high-flow rate media (153 in/hr) to remove stormwater
pollutants. The BioPod system has received a General Use
Level Designation (GULD) approval from the Washington
State Department of Ecology for Basic (TSS), Phosphorus,
and Enhanced (dissolved metals) treatment.
Offering flexibility of design and construction for your storm drain system,
the BioPod system comes as an all-in-one, single-piece unit composed of
durable precast concrete for ease of installation and a long service life.
The BioPod system is offered in four configurations:
High-Flow Bypass
BioPod system offers an optional internal high-flow bypass that eliminates
the need for a separate bypass structure, reducing costs and simplifying
design so unit can be placed in a “sag” condition.
Hydromodification
BioPod system can be used in conjunction with other Oldcastle detention
systems to address hydromodification and water treatment requirements.
Collected flows may be utilized to supplement irrigation of the unit or
surrounding vegetated areas by integrating a harvesting system, reducing
consumption of local potable water.
LEED WITH BIOPOD
Can assist in earning LEED credits for:
• Sustainable Sites (6.1, 6.2)
• Water Efficiency (1.1, 1.2, 3.1, 3.2)
• Materials & Resources (4.1, 4.2; 5.1, 5.2
in AZ, CA, NV, UT)
BIOPOD SURFACE
At-grade vault with media only,
no vegetation.
BIOPOD TREE
Vault with media and tree(s).
BIOPOD PLANTER
Vault with media and vegetation.
BIOPOD UNDERGROUND
Below-grade vault with media
only, no vegetation.
Stormwater Treatment,NATURALLY
(800) 579-8819
oldcastlestormwater.com
BIOPOD™ SYSTEM WITH STORMMIX™ MEDIA
SECTION 2
WA ECOLOGY GULD APPROVAL
May 2019
GENERAL USE LEVEL DESIGNATION FOR BASIC (TSS), DISSOLVED
METALS (ENHANCED), AND PHOSPHORUS TREATMENT
For
Oldcastle Infrastructure, Inc.’s
The BioPod™ Biofilter
(Formerly the TreePod Biofilter)
Ecology’s Decision:
Based on Oldcastle Infrastructure, Inc. application submissions for the The BioPod™
Biofilter (BioPod), Ecology hereby issues the following use level designation:
1. General Use Level Designation (GULD) for Basic, Enhanced, and Phosphorus
Treatment:
Sized at a hydraulic loading rate of 1.6 gallons per minute (gpm) per square foot (sq
ft) of media surface area.
Constructed with a minimum media thickness of 18-inches (1.5-feet).
2. Ecology approves the BioPod at the hydraulic loading rate listed above, to achieve the
maximum water quality design flow rate. The water quality design flow rates are
calculated using the following procedures:
Western Washington: For treatment installed upstream of detention or retention,
the water quality design flow rate is the peak 15-minute flow rate as calculated using
the latest version of the Western Washington Hydrology Model or other Ecology-
approved continuous runoff model.
Eastern Washington: For treatment installed upstream of detention or retention,
the water quality design flow rate is the peak 15-minute flow rate as calculated using
one of the three methods described in Chapter 2.2.5 of the Stormwater Management
Manual for Eastern Washington (SWMMEW) or local manual.
Entire State: For treatment installed downstream of detention, the water quality
design flow rate is the full 2-year release rate of the detention facility.
3. The GULD has no expiration date, but may be amended or revoked by Ecology.
Ecology’s Conditions of Use:
The BioPod shall comply with these conditions:
1) Applicants shall design, assemble, install, operate, and maintain the BioPod
installations in accordance with Oldcastle Infrastructure, Inc.’s applicable manuals and
the Ecology Decision.
2) BioPod media shall conform to the specifications submitted to and approved by Ecology
3) Maintenance: The required inspection/maintenance interval for stormwater treatment
devices is often dependent on the efficiency of the device and the degree of pollutant
loading from a particular drainage basin. Therefore, Ecology does not endorse or
recommend a “one size fits all” maintenance cycle for a particular model/size of
manufactured filter treatment device.
The BioPod is designed for a target maintenance interval of 1 year. Maintenance
includes replacing the mulch, assessing plant health, removal of trash, and raking
the top few inches of engineered media.
A BioPod system tested at the Lake Union Ship Canal Test Facility in Seattle, WA
required maintenance after 1.5 months, or 6.3% of a water year. Monitoring
personnel observed similar maintenance issues with other systems evaluated at the
Test Facility. The runoff from the Test Facility may be unusual and maintenance
requirements of systems installed at the Test Facility may not be indicative of
maintenance requirements for all sites.
Test results provided to Ecology from a BioPod System evaluated in a lab following
New Jersey Department of Environmental Protection Laboratory Protocol for
Filtration MTDs have indicated the BioPod System is capable of longer maintenance
intervals.
Owners/operators must inspect BioPod systems for a minimum of twelve months
from the start of post-construction operation to determine site-specific
inspection/maintenance schedules and requirements. Owners/operators must
conduct inspections monthly during the wet season, and every other month during
the dry season. (According to the SWMMWW, the wet season in western
Washington is October 1 to April 30. According to the SWMMEW, the wet season
in eastern Washington is October 1 to June 30.) After the first year of operation,
owners/operators must conduct inspections based on the findings during the first
year of inspections.
Conduct inspections by qualified personnel, follow manufacturer’s guidelines, and
use methods capable of determining either a decrease in treated effluent flow rate
and/or a decrease in pollutant removal ability.
4) Install the BioPod in such a manner that you bypass flows exceeding the maximum
operating rate and you will not resuspend captured sediment.
5) Discharges from the BioPod shall not cause or contribute to water quality standards
violations in receiving waters.
Applicant: Oldcastle Infrastructure, Inc.
Applicant’s Address: 7100 Longe St, Suite 100
Stockton, CA 95206
Application Documents:
Technical Evaluation Report TreePod™ BioFilter System Performance Certification Project,
Prepared for Oldcastle, Inc., Prepared by Herrera Environmental Consultants, Inc. February 2018
Technical Memorandum: Response to Board of External Reviewers’ Comments on the Technical
Evaluation Report for the TreePod™ Biofilter System Performance Certification Project,
Oldcastle, Inc. and Herrera Environmental Consultants, Inc., February 2018
Technical Memorandum: Response to Board of External Reviewers’ Comments on the Technical
Evaluation Report for the TreePod™ Biofilter System Performance Certification Project,
Oldcastle, Inc. and Herrera Environmental Consultants, Inc., January 2018
Application for Pilot Use Level Designation, TreePod™ Biofilter – Stormwater Treatment
System, Oldcastle Stormwater Solutions, May 2016
Emerging Stormwater Treatment Technologies Application for Certification: The TreePod™
Biofilter, Oldcastle Stormwater Solutions, April 2016
Applicant’s Use Level Request:
General Use Level Designation as a Basic, Enhanced, and Phosphorus Treatment device
in accordance with Ecology’s Stormwater Management Manual for Western Washington
Applicant’s Performance Claims:
Based on results from laboratory and field-testing, the applicant claims the BioPod™ Biofilter
operating at a hydraulic loading rate of 153 inches per hour is able to remove:
80% of Total Suspended Solids (TSS) for influent concentrations greater than 100 mg/L
and achieve a 20 mg/L effluent for influent concentrations less than 100 mg/L.
60% dissolved zinc for influent concentrations 0.02 to 0.3 mg/L.
30% dissolved copper for influent concentrations 0.005 to 0.02 mg/L.
50% or greater total phosphorus for influent concentrations 0.1 to 0.5 mg/L.
Ecology’s Recommendations:
Ecology finds that:
Oldcastle Infrastructure, Inc. has shown Ecology, through laboratory and field testing,
that the BioPod™ Biofilter is capable of attaining Ecology’s Basic, Total Phosphorus,
and Enhanced treatment goals.
Findings of Fact:
Field Testing
1. Herrera Environmental Consultants, Inc. conducted monitoring of the BioPod™ Biofilter at
the Lake Union Ship Canal Test Facility in Seattle Washington between November 2016 and
April 2018. Herrera collected flow-weight composite samples during 14 separate storm
events and peak flow grab samples during 3 separate storm events. The system was sized at
an infiltration rate of 153 inches per hour or a hydraulic loading rate of 1.6 gpm/ft2.
2. The D50 of the influent PSD ranged from 3 to 292 microns, with an average D50 of 28
microns.
3. Influent TSS concentrations ranged from 17 mg/L to 666 mg/L, with a mean concentration of
98 mg/L. For all samples (influent concentrations above and below 100 mg/L) the bootstrap
estimate of the lower 95 percent confidence limit (LCL 95) of the mean TSS reduction was
84% and the bootstrap estimate of the upper 95 percent confidence limit (UCL95) of the
mean TSS effluent concentration was 8.2 mg/L.
4. Dissolved copper influent concentrations from the 17 events ranged from 9.0 µg/L to 21.1
µg/L. The 21.1 µg/L data point was reduced to 20.0 µg/L, the upper limit to the TAPE
allowed influent concentration range, prior to calculating the pollutant removal. A bootstrap
estimate of the LCL95 of the mean dissolved copper reduction was 35%.
5. Dissolved zinc influent concentrations from the 17 events ranged from 26.1 µg/L to 43.3
µg/L. A bootstrap estimate of the LCL95 of the mean dissolved zinc reduction was 71%.
6. Total phosphorus influent concentrations from the 17 events ranged from 0.064 mg/L to 1.56
mg/L. All influent data greater than 0.5 mg/L were reduced to 0.5 mg/L, the upper limit to the TAPE
allowed influent concentration range, prior to calculating the pollutant removal. A bootstrap
estimate of the LCL95 of the mean total phosphorus reduction was 64%.
7. The system experienced rapid sediment loading and needed to be maintained after 1.5
months. Monitoring personnel observed similar sediment loading issues with other systems
evaluated at the Test Facility. The runoff from the Test Facility may not be indicative of
maintenance requirements for all sites.
Laboratory Testing
1. Good Harbour Laboratories (GHL) conducted laboratory testing at their site in Mississauga,
Ontario in October 2017 following the New Jersey Department of Environmental Protection
Laboratory Protocol for Filtration MTDs. The testing evaluated a 4-foot by 6-foot standard
biofiltration chamber and inlet contour rack with bypass weir. The test sediment used during
the testing was custom blended by GHL using various commercially available silica sands,
which had an average d50 of 69 µm. Based on the lab test results:
a. GHL evaluated removal efficiency over 15 events at a Maximum Treatment Flow Rate
(MTFR) of 37.6 gpm, which corresponds to a MTFR to effective filtration treatment area
ratio of 1.80 gpm/ft2. The system, operating at 100% of the MTFR with an average
influent concentration of 201.3 mg/L, had an average removal efficiency of 99 percent.
b. GHL evaluated sediment mass loading capacity over an additional 16 events using an
influent SSC concentration of 400 mg/L. The first 11 runs were evaluated at 100% of the
MTFR. The BioPod began to bypass, so the remaining 5 runs were evaluated at 90% of
the MTFR. The total mass of the sediment captured was 245.0 lbs and the cumulative
mass removal efficiency was 96.3%.
2. Herrera Environmental Consultants Inc. conducted laboratory testing in September 2014 at
the Seattle University Engineering Laboratory. The testing evaluated the flushing
characteristics, hydraulic conductivity, and pollutant removal ability of twelve different
media blends. Based on this testing, Oldcastle Infrastructure, Inc. selected one media blend,
Mix 8, for inclusion in their TAPE evaluation of the BioPod™ Biofilter.
a. Herrera evaluated Mix 8 in an 8-inch diameter by 36-inch tall polyvinyl chloride (PVC)
column. The column contained 18-inches of Mix 8 on top of 6-inches of pea gravel. The
BioPod will normally include a 3-inch mulch layer on top of the media layer; however,
this was not included in the laboratory testing.
b. Mix 8 has a hydraulic conductivity of 218 inches per hour; however, evaluation of the
pollutant removal ability of the media was based on an infiltration rate of 115 inches per
hour. The media was tested at 75%, 100%, and 125% of the infiltration rate. Based on the
lab test results:
The system was evaluated using natural stormwater. The dissolved copper and
dissolved zinc concentrations in the natural stormwater were lower than the TAPE
influent standards; therefore, the stormwater was spiked with 66.4 mL of 100 mg/L
Cu solution and 113.6 mL of 1,000 mg/L Zn solution.
The BioPod removed an average of 81% of TSS, with a mean influent concentration
of 48.4 mg/L and a mean effluent concentration of 9.8 mg/L.
The BioPod removed an average of 94% of dissolved copper, with a mean influent
concentration of 10.6 µg/L and a mean effluent concentration of 0.6 µg/L.
The BioPod removed an average of 97% of dissolved zinc, with a mean influent
concentration of 117 µg/L and a mean effluent concentration of 4 µg/L.
The BioPod removed an average of 97% of total phosphorus, with a mean influent
concentration of 2.52 mg/L and a mean effluent concentration of 0.066 mg/L. When
total phosphorus influent concentrations were capped at the TAPE upper limit of 0.5
mg/L, calculations showed an average removal of 87%.
Other BioPod Related Issues to be Addressed By the Company:
1. Conduct hydraulic testing to obtain information about maintenance requirements on a site
with runoff that is more typical of the Pacific Northwest.
Technology Description: Download at
https://oldcastleprecast.com/stormwater/bioretention-
biofiltration-applications/bioretention-biofiltration-
solutions/
Contact Information:
Applicant: Chris Demarest
Oldcastle Infrastructure, Inc.
(925) 667-7100
Chris.demarest@oldcastle.com
Applicant website: https://oldcastleprecast.com/stormwater/
Ecology web link: https://ecology.wa.gov/Regulations-Permits/Guidance-technical-
assistance/Stormwater-permittee-guidance-resources/Emerging-stormwater-treatment-
technologies
Ecology: Douglas C. Howie, P.E.
Department of Ecology
Water Quality Program
(360) 407-6444
douglas.howie@ecy.wa.gov
Revision History
Date Revision
March 2018 GULD granted for Basic Treatment
March 2018 Provisional GULD granted for Enhanced and Phosphorus Treatment
June 2016 PULD Granted
April 2018 GULD for Basic and Provisional GULD for Enhanced and
Phosphorus granted, changed name to BioPod from TreePod
July 2018 GULD for Enhanced and Phosphorus granted
September 2018 Changed Address for Oldcastle
December 2018 Added minimum media thickness requirement
May 2019 Changed language on who must Install and maintain the device from
Oldcastle to Applicants
SECTION 3
INSPECTION & MAINTENANCE
Maintenance Specifications
BIOMOD®DRAINA G E P R OTECTION SY
ST
E
MSA division of
Oldcastle Infrastructure
MODULAR BIORETENTION SYSTEM
Scope
Federal, State and Local Clean Water Act regulations and those of insurance carriers require that post-
construction stormwater Best Management Practices (BMPs) be performed on a recurring basis. The intent of
the regulations is to ensure that the BMPs, on a continuing basis, efficiently remove pollutants from stormwater runoff, thereby preventing pollution of the nation’s water resources. These requirements apply to the BioMod Modular Bioretention System.
Recommended Frequency of Service
Properly designed and installed bioretention cells require some regular maintenance, most frequently during the first year or two of establishment. Oldcastle Infrastructure recommends that installed BioMod units be inspected and serviced on a recurring basis for sediment buildup, trash removal, erosion, and to evaluate the health of
the vegetation. Ultimately, the frequency depends on the amount of runoff, pollutant loading and interference
from debris and litter; however, it is recommended that each installation be serviced at least two times per year.
Drainage Protection Systems (DPS), a division of Oldcastle Infrastructure, is available to do an onsite evaluation upon request.
Recommended Timing of Service
Guidelines for the timing of service are as follows:
1. For areas with a definitive rainy season: Prior to and following the rainy season.
2. For areas subject to year-round rainfall: On a recurring basis (at least two times per year).
3. For areas with winter snow and summer rain: Prior to and after the snow season.
4. For installed devices not subject to the elements (wash racks, parking garages, etc.):
On a recurring basis (no less than two times per year).
Service Procedures
1. Bioretention cells will require supplemental irrigation during the first 2-3 years after planting. Drought tolerant species may need little additional water after this period, except during prolonged drought, when
supplemental irrigation may become necessary for plant survival. Verify that the maintenance plan includes
a watering schedule for the establishment period and in times of extreme drought after plants have been
established.
2. Inspect the inlet surface adjacent to the BioMod unit and the inlet opening for trash and debris accumulation.
Remove and dispose as required.
3. For units with pre-filtration, open the access cover of the pre-filtration chamber and inspect for collected
pollutants. Remove and dispose of all materials. (Pre-filtration chamber allows for the use of industrial
vacuum equipment if available). Close pre-filter access cover.
4. For units with internal bypass overflow screens, check for any blockage or obstructions to the flow path
and remove as necessary. Check for any potential future blockage or obstruction beneath and around the
overflow screens. Remove and dispose of all materials.
5. Inspect the area beneath the tree grate (when applicable), and if necessary, remove the tree grate and
dispose of any collected trash or debris.
6. For units without pre-filtration, remove and replace the mulch layer as necessary, taking care to disturb the
plant’s roots as little as possible. Units without pre-filtration may see more sediment enter the system. If
sediment buildup reaches 25% of the ponding depth, it should be removed, taking care to minimize soil disturbance.
2
Maintenance SpecificationS
3
7. Inspect for standing water. If present, or if soil media is appreciably moist more than 72 hours following a rain event, carefully remove and replace the top 4-6 inches of soil media (as well as the mulch layer) taking care to disturb the plant’s roots as little as possible. Mulch should be re-applied when erosion is evident. In areas expected to have low metal loads in the runoff, mulch is needed to maintain a 2-3 inch depth. In areas
with relatively high metal loads, replace the mulch once per year.
8. While vegetation is being established, remove weeds by hand (weeding frequency should decrease over
time, as the vegetation grows). Inspect and prune the plants as needed to maintain adequate shape and
health. If vegetation appears to be in poor health with no obvious cause, a landscape specialist should be
consulted. Although occasional pruning or trimming might be needed, bioretention cells should generally not be mowed on a regular basis. In some instances where it is desired to maintain fast-growing, annual herbaceous plant cover, annual mowing may be appropriate.
9. Replace dead plants. If a particular species proves to be prone to mortality, it may need to be replaced with a different species that is more likely to succeed on the particular site.
Disposal of Collected Debris, Hydrocarbons and Sediment
The collected debris, hydrocarbons and sediment shall be disposed of in accordance with local, state and federal
agency requirements. Where hazardous materials are encountered, these standard maintenance procedures will be ceased immediately and the property owner notified for further work authorization.
DPS also has the capability of servicing all manner of catch basin inserts and catch basins with or without inserts, underground oil/water separators, stormwater interceptors and other such devices. All DPS personnel are highly qualified technicians and are confined-space trained and certified. Call us at (888) 950-8826 for further information and assistance.
BUILDINGSTRUCTURES
OUR MARKETS
TRANSPORTATION
WATER
ENERGYCOMMUNICATIONS
December 2018 v.1
www.oldcastleinfrastructure.com
800-579-8819
BIOMOD®
MODULAR BIORETENTION SYSTEM
Appendix F
Bond Quantities Worksheet
Planning Division |1055 South Grady Way – 6 th Floor | Renton, WA 98057 (425) 430-7200
•
•
Section I: Project Information
•
•
•
Section II: Bond Quantities Worksheets
•
•Section II.a EROSION CONTROL (Stabilization/Erosion Sediment Control (ESC))
•Section II.b TRANSPORTATION (Street and Site Improvements)
•Section II.c DRAINAGE (Drainage and Stormwater Facilities):
•Section II.d WATER -ONLY APPLICABLE IF WATER SERVICE IS PROVIDED BY CITY OF RENTON
•Section II.e SANITARY SEWER -ONLY APPLICABLE IF SEWER SERVICE IS PROVIDED BY CITY OF RENTON
•
•
•
•
•
•
Section III. Bond Worksheet
• This section calculates the required Permit Bond for construction permit issuance as well as the required Maintenance Bond for project close-out
submittals to release the permit bond on a project.
All unit prices include labor, equipment, materials, overhead and profit.
Complete the 'Quantity' columns for each of the appropriate section(s). Include existing Right-of-Way (ROW), Future Public Improvements and Private
Improvements.
The 'Quantity Remaining' column is only to be used when a project is under construction. The City allows one (1) bond reduction during the life of the
project with the exception of the maintenance period reduction.
Excel will auto-calculate and auto-populate the relevant fields and subtotals throughout the document. Only the 'Quantity' columns should need
completing.
Additional items not included in the lists can be added under the "write-in" sections. Provide a complete description, cost estimate and unit of measure
for each write-in item.
Note: Private improvements, with the exception of stormwater facilities, are not included in the bond amount calculation, but must be entered on the
form. Stormwater facilities (public and private) are required to be included in the bond amount.
BOND QUANTITY WORKSHEET INSTRUCTIONS
This worksheet is intended to be a "working" copy of the bond quantity worksheet, which will be used throughout all phases of the project, from initial
submittal to project close-out approval.
Submit this workbook, in its entirety, as follows:
The following forms are to be completed by the engineer/developer/applicant as applicable to the project:
The Bond Worksheet form will auto-calculate and auto-populate from the information provided in Section I and Section II.
This section includes all pertinent information for the project
Section II contains a separate spreadsheet TAB for each of the following specialties:
(1) electronic copy (.xlsx format) and (1) hard copy of the entire workbook for civil construction permit submittal. Hard copies are to be included as part
of the Technical Information Report (TIR).
(1) electronic copy (.xlsx format) and (1) hard copy of the entire workbook for final close-out submittal.
This section must be completed in its entirety
Information from this section auto-populates to all other relevant areas of the workbook
Page 1 of 14
Ref 8-H Bond Quantity Worksheet INSTRUCTIONS
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 12/19/2019
Planning Division |1055 South Grady Way – 6 th Floor | Renton, WA 98057 (425) 430-7200
Date Prepared:
Name:
PE Registration No:
Firm Name:
Firm Address:
Phone No.
Email Address:
Project Name: Project Owner:
CED Plan # (LUA): Phone:
CED Permit # (U):Address:
Site Address:
Street Intersection: Addt'l Project Owner:
Parcel #(s): Phone:
Address:
Clearing and grading greater than or equal to 5,000 board feet of timber?
Yes/No:No Water Service Provided by:
If Yes, Provide Forest Practice Permit #:Sewer Service Provided by:
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
PROJECT INFORMATION
CITY OF RENTON
CITY OF RENTON
1Select the current project status/phase from the following options:
For Approval - Preliminary Data Enclosed, pending approval from the City;
For Construction - Estimated Data Enclosed, Plans have been approved for contruction by the City;
Project Closeout - Final Costs and Quantities Enclosed for Project Close-out Submittal
(425) 226-1850
Engineer Stamp Required
(all cost estimates must have original wet stamp and signature)
Clearing and Grading Utility Providers
N/A
Project Location and Description Project Owner Information
Willowcrest Townhomes
Seattle, WA 98104
0923059080
Homestead Community Land Trust
19-000061,BSP,PUD (206) 323-1227
12/18/2019
Prepared by:
FOR APPROVALProject Phase 1
peter@coterraengineering.com
Peter Apostol, PE
35163
Coterra Engineering
321 3rd Ave South, #406, Seattle, WA 98104
(206) 596-7115
1132 Edmonds Ave NE
412 Maynard Ave South, #201
Renton Housing AuthorityEdmonds Ave ME & NE Sunset Blvd
PO Box 2316Abbreviated Legal
Description:
THE SOUTH HALF OF THE WEST HALF OF THE NORTHWEST QUARTER
OF THE NORTHWEST QUARTER OF THE NORTHWEST QUARTER OF
SECTION 9, TOWNSHIP 23 NORTH, RANGE 5 EAST, WILLAMETTE
MERIDIAN, IN KING COUNTY WASHINGTON.
Renton, WA 98056
Page 2 of 14
Ref 8-H Bond Quantity Worksheet SECTION I PROJECT INFORMATION
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 12/19/2019
CED Permit #:
Unit
Reference #Price Unit Quantity CostBackfill & compaction-embankment ESC-1 6.50$CYCheck dams, 4" minus rock ESC-2 SWDM 5.4.6.3 80.00$EachCatch Basin Protection ESC-3 35.50$Each 26 923.00Crushed surfacing 1 1/4" minus ESC-4 WSDOT 9-03.9(3)95.00$CYDitchingESC-5 9.00$CYExcavation-bulk ESC-6 2.00$CY
Fence, silt ESC-7 SWDM 5.4.3.1 1.50$LF 562 843.00
Fence, Temporary (NGPE)ESC-8 1.50$LF
Geotextile Fabric ESC-9 2.50$SY
Hay Bale Silt Trap ESC-10 0.50$Each
Hydroseeding ESC-11 SWDM 5.4.2.4 0.80$SY
Interceptor Swale / Dike ESC-12 1.00$LFJute Mesh ESC-13 SWDM 5.4.2.2 3.50$SYLevel Spreader ESC-14 1.75$LFMulch, by hand, straw, 3" deep ESC-15 SWDM 5.4.2.1 2.50$SYMulch, by machine, straw, 2" deep ESC-16 SWDM 5.4.2.1 2.00$SYPiping, temporary, CPP, 6"ESC-17 12.00$LFPiping, temporary, CPP, 8"ESC-18 14.00$LF
Piping, temporary, CPP, 12"ESC-19 18.00$LF
Plastic covering, 6mm thick, sandbagged ESC-20 SWDM 5.4.2.3 4.00$SY
Rip Rap, machine placed; slopes ESC-21 WSDOT 9-13.1(2)45.00$CY
Rock Construction Entrance, 50'x15'x1'ESC-22 SWDM 5.4.4.1 1,800.00$Each
Rock Construction Entrance, 100'x15'x1'ESC-23 SWDM 5.4.4.1 3,200.00$Each 1 3,200.00
Sediment pond riser assembly ESC-24 SWDM 5.4.5.2 2,200.00$Each
Sediment trap, 5' high berm ESC-25 SWDM 5.4.5.1 19.00$LFSed. trap, 5' high, riprapped spillway berm section ESC-26 SWDM 5.4.5.1 70.00$LFSeeding, by hand ESC-27 SWDM 5.4.2.4 1.00$SYSodding, 1" deep, level ground ESC-28 SWDM 5.4.2.5 8.00$SYSodding, 1" deep, sloped ground ESC-29 SWDM 5.4.2.5 10.00$SYTESC Supervisor ESC-30 110.00$HRWater truck, dust control ESC-31 SWDM 5.4.7 140.00$HR
Unit
Reference #Price Unit Quantity Cost
EROSION/SEDIMENT SUBTOTAL:4,966.00
SALES TAX @ 10%496.60
EROSION/SEDIMENT TOTAL:5,462.60
(A)
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
FOR EROSION & SEDIMENT CONTROL
Description No.
(A)
WRITE-IN-ITEMS
Page 3 of 14
Ref 8-H Bond Quantity Worksheet SECTION II.a EROSION_CONTROL
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 12/19/2019
CED Permit #:
Existing Future Public Private
Right-of-Way Improvements Improvements
(D)(E)Description No.Unit Price Unit Quant.Cost Quant.Cost Quant.Cost Quant.CostGENERAL ITEMSBackfill & Compaction- embankment GI-1 6.00$CY
Backfill & Compaction- trench GI-2 9.00$CY 300 2,700.00 250 2,250.00
Clear/Remove Brush, by hand (SY)GI-3 1.00$SY
Bollards - fixed GI-4 240.74$Each
Bollards - removable GI-5 452.34$Each
Clearing/Grubbing/Tree Removal GI-6 10,000.00$Acre 0.86 8,600.00
Excavation - bulk GI-7 2.00$CY
Excavation - Trench GI-8 5.00$CY 300 1,500.00 250 1,250.00
Fencing, cedar, 6' high GI-9 20.00$LF
Fencing, chain link, 4'GI-10 38.31$LF
Fencing, chain link, vinyl coated, 6' high GI-11 20.00$LF
Fencing, chain link, gate, vinyl coated, 20'GI-12 1,400.00$Each
Fill & compact - common barrow GI-13 25.00$CY 1800 45,000.00
Fill & compact - gravel base GI-14 27.00$CY
Fill & compact - screened topsoil GI-15 39.00$CY
Gabion, 12" deep, stone filled mesh GI-16 65.00$SY
Gabion, 18" deep, stone filled mesh GI-17 90.00$SY
Gabion, 36" deep, stone filled mesh GI-18 150.00$SY
Grading, fine, by hand GI-19 2.50$SY 1200 3,000.00
Grading, fine, with grader GI-20 2.00$SY 1400 2,800.00
Monuments, 3' Long GI-21 250.00$Each
Sensitive Areas Sign GI-22 7.00$Each
Sodding, 1" deep, sloped ground GI-23 8.00$SY
Surveying, line & grade GI-24 850.00$Day 1 850.00
Surveying, lot location/lines GI-25 1,800.00$Acre 0.86 1,548.00
Topsoil Type A (imported)GI-26 28.50$CY
Traffic control crew ( 2 flaggers )GI-27 120.00$HR
Trail, 4" chipped wood GI-28 8.00$SY
Trail, 4" crushed cinder GI-29 9.00$SY
Trail, 4" top course GI-30 12.00$SY
Conduit, 2"GI-31 5.00$LF
Wall, retaining, concrete GI-32 55.00$SF
Wall, rockery GI-33 15.00$SF 900 13,500.00
SUBTOTAL THIS PAGE:4,200.00 78,798.00
(B)(C)(D)(E)
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
FOR STREET AND SITE IMPROVEMENTS
Quantity Remaining
(Bond Reduction)
(B)(C)
Page 4 of 14
Ref 8-H Bond Quantity Worksheet SECTION II.b TRANSPORTATION
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 12/19/2019
CED Permit #:
Existing Future Public Private
Right-of-Way Improvements Improvements
(D)(E)Description No.Unit Price Unit Quant.Cost Quant.Cost Quant.Cost Quant.Cost
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
FOR STREET AND SITE IMPROVEMENTS
Quantity Remaining
(Bond Reduction)
(B)(C)
ROAD IMPROVEMENT/PAVEMENT/SURFACINGAC Grinding, 4' wide machine < 1000sy RI-1 30.00$SY
AC Grinding, 4' wide machine 1000-2000sy RI-2 16.00$SY
AC Grinding, 4' wide machine > 2000sy RI-3 10.00$SY
AC Removal/Disposal RI-4 35.00$SY 61 2,135.00
Barricade, Type III ( Permanent )RI-5 56.00$LF
Guard Rail RI-6 30.00$LF
Curb & Gutter, rolled RI-7 17.00$LF
Curb & Gutter, vertical RI-8 12.50$LF 26 325.00 650 8,125.00
Curb and Gutter, demolition and disposal RI-9 18.00$LF 26 468.00
Curb, extruded asphalt RI-10 5.50$LF
Curb, extruded concrete RI-11 7.00$LF
Sawcut, asphalt, 3" depth RI-12 1.85$LF 80 148.00 330 610.50
Sawcut, concrete, per 1" depth RI-13 3.00$LF
Sealant, asphalt RI-14 2.00$LF
Shoulder, gravel, 4" thick RI-15 15.00$SY
Sidewalk, 4" thick RI-16 38.00$SY 14 532.00 125 4,750.00
Sidewalk, 4" thick, demolition and disposal RI-17 32.00$SY 14 448.00
Sidewalk, 5" thick RI-18 41.00$SY
Sidewalk, 5" thick, demolition and disposal RI-19 40.00$SY
Sign, Handicap RI-20 85.00$Each 2 170.00
Striping, per stall RI-21 7.00$Each 6 42.00
Striping, thermoplastic, ( for crosswalk )RI-22 3.00$SF
Striping, 4" reflectorized line RI-23 0.50$LF
Additional 2.5" Crushed Surfacing RI-24 3.60$SY
HMA 1/2" Overlay 1.5"RI-25 14.00$SY
HMA 1/2" Overlay 2"RI-26 18.00$SY
HMA Road, 2", 4" rock, First 2500 SY RI-27 28.00$SY
HMA Road, 2", 4" rock, Qty. over 2500SY RI-28 21.00$SY
HMA Road, 4", 6" rock, First 2500 SY RI-29 45.00$SY 61 2,745.00 1215 54,675.00
HMA Road, 4", 6" rock, Qty. over 2500 SY RI-30 37.00$SY
HMA Road, 4", 4.5" ATB RI-31 38.00$SY
Gravel Road, 4" rock, First 2500 SY RI-32 15.00$SY
Gravel Road, 4" rock, Qty. over 2500 SY RI-33 10.00$SY
Thickened Edge RI-34 8.60$LF
SUBTOTAL THIS PAGE:6,801.00 68,372.50
(B)(C)(D)(E)
Page 5 of 14
Ref 8-H Bond Quantity Worksheet SECTION II.b TRANSPORTATION
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 12/19/2019
CED Permit #:
Existing Future Public Private
Right-of-Way Improvements Improvements
(D)(E)Description No.Unit Price Unit Quant.Cost Quant.Cost Quant.Cost Quant.Cost
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
FOR STREET AND SITE IMPROVEMENTS
Quantity Remaining
(Bond Reduction)
(B)(C)
PARKING LOT SURFACING No.2" AC, 2" top course rock & 4" borrow PL-1 21.00$SY
2" AC, 1.5" top course & 2.5" base course PL-2 28.00$SY
4" select borrow PL-3 5.00$SY
1.5" top course rock & 2.5" base course PL-4 14.00$SY
SUBTOTAL PARKING LOT SURFACING:
(B)(C)(D)(E)
LANDSCAPING & VEGETATION No.Street Trees LA-1
Median Landscaping LA-2
Right-of-Way Landscaping LA-3
Wetland Landscaping LA-4
SUBTOTAL LANDSCAPING & VEGETATION:
(B)(C)(D)(E)
TRAFFIC & LIGHTING No.Signs TR-1
Street Light System ( # of Poles)TR-2
Traffic Signal TR-3
Traffic Signal Modification TR-4
SUBTOTAL TRAFFIC & LIGHTING:
(B)(C)(D)(E)
WRITE-IN-ITEMS
SUBTOTAL WRITE-IN ITEMS:
STREET AND SITE IMPROVEMENTS SUBTOTAL:6,801.00 4,200.00 147,170.50
SALES TAX @ 10%680.10 420.00 14,717.05
STREET AND SITE IMPROVEMENTS TOTAL:7,481.10 4,620.00 161,887.55
(B)(C)(D)(E)
Page 6 of 14
Ref 8-H Bond Quantity Worksheet SECTION II.b TRANSPORTATION
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 12/19/2019
CED Permit #:
Existing Future Public PrivateRight-of-Way Improvements Improvements
(D)(E)Description No.Unit Price Unit Quant.Cost Quant.Cost Quant.Cost Quant.Cost
DRAINAGE (CPE = Corrugated Polyethylene Pipe, N12 or Equivalent) For Culvert prices, Average of 4' cover was assumed. Assume perforated PVC is same price as solid pipe.)Access Road, R/D D-1 26.00$SY 103 2,678.00
* (CBs include frame and lid)
Beehive D-2 90.00$Each
Through-curb Inlet Framework D-3 400.00$Each
CB Type I D-4 1,500.00$Each 1 1,500.00 10 15,000.00
CB Type IL D-5 1,750.00$Each
CB Type II, 48" diameter D-6 2,300.00$Each 1 2,300.00 5 11,500.00
for additional depth over 4'D-7 480.00$FT 5 2,400.00
CB Type II, 54" diameter D-8 2,500.00$Each 1 2,500.00
for additional depth over 4'D-9 495.00$FT 3 1,485.00
CB Type II, 60" diameter D-10 2,800.00$Each
for additional depth over 4'D-11 600.00$FT
CB Type II, 72" diameter D-12 6,000.00$Each
for additional depth over 4'D-13 850.00$FT
CB Type II, 96" diameter D-14 14,000.00$Each
for additional depth over 4'D-15 925.00$FT
Trash Rack, 12"D-16 350.00$Each
Trash Rack, 15"D-17 410.00$Each
Trash Rack, 18"D-18 480.00$Each
Trash Rack, 21"D-19 550.00$Each
Cleanout, PVC, 4"D-20 150.00$Each 13 1,950.00
Cleanout, PVC, 6"D-21 170.00$Each
Cleanout, PVC, 8"D-22 200.00$Each
Culvert, PVC, 4"D-23 10.00$LF 160 1,600.00
Culvert, PVC, 6"D-24 13.00$LF
Culvert, PVC, 8"D-25 15.00$LF 35 525.00 950 14,250.00
Culvert, PVC, 12"D-26 23.00$LF
Culvert, PVC, 15"D-27 35.00$LF
Culvert, PVC, 18"D-28 41.00$LF
Culvert, PVC, 24"D-29 56.00$LF
Culvert, PVC, 30"D-30 78.00$LF
Culvert, PVC, 36"D-31 130.00$LF
Culvert, CMP, 8"D-32 19.00$LF
Culvert, CMP, 12"D-33 29.00$LF
SUBTOTAL THIS PAGE:4,325.00 53,363.00
(B)(C)(D)(E)
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
FOR DRAINAGE AND STORMWATER FACILITIES
Quantity Remaining
(Bond Reduction)(B)(C)
Page 7 of 14
Ref 8-H Bond Quantity Worksheet SECTION II.c DRAINAGE
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 12/19/2019
CED Permit #:
Existing Future Public PrivateRight-of-Way Improvements Improvements
(D)(E)Description No.Unit Price Unit Quant.Cost Quant.Cost Quant.Cost Quant.Cost
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
FOR DRAINAGE AND STORMWATER FACILITIES
Quantity Remaining
(Bond Reduction)(B)(C)
DRAINAGE (Continued)Culvert, CMP, 15"D-34 35.00$LF
Culvert, CMP, 18"D-35 41.00$LF
Culvert, CMP, 24"D-36 56.00$LF
Culvert, CMP, 30"D-37 78.00$LFCulvert, CMP, 36"D-38 130.00$LF
Culvert, CMP, 48"D-39 190.00$LF
Culvert, CMP, 60"D-40 270.00$LF
Culvert, CMP, 72"D-41 350.00$LF
Culvert, Concrete, 8"D-42 42.00$LF
Culvert, Concrete, 12"D-43 48.00$LF
Culvert, Concrete, 15"D-44 78.00$LF
Culvert, Concrete, 18"D-45 48.00$LF
Culvert, Concrete, 24"D-46 78.00$LF
Culvert, Concrete, 30"D-47 125.00$LF
Culvert, Concrete, 36"D-48 150.00$LF
Culvert, Concrete, 42"D-49 175.00$LF
Culvert, Concrete, 48"D-50 205.00$LF
Culvert, CPE Triple Wall, 6"D-51 14.00$LF
Culvert, CPE Triple Wall, 8"D-52 16.00$LF
Culvert, CPE Triple Wall, 12"D-53 24.00$LF
Culvert, CPE Triple Wall, 15"D-54 35.00$LF
Culvert, CPE Triple Wall, 18"D-55 41.00$LF
Culvert, CPE Triple Wall, 24"D-56 56.00$LF
Culvert, CPE Triple Wall, 30"D-57 78.00$LF
Culvert, CPE Triple Wall, 36"D-58 130.00$LF
Culvert, LCPE, 6"D-59 60.00$LF
Culvert, LCPE, 8"D-60 72.00$LF
Culvert, LCPE, 12"D-61 84.00$LF
Culvert, LCPE, 15"D-62 96.00$LF
Culvert, LCPE, 18"D-63 108.00$LF
Culvert, LCPE, 24"D-64 120.00$LF
Culvert, LCPE, 30"D-65 132.00$LF
Culvert, LCPE, 36"D-66 144.00$LF
Culvert, LCPE, 48"D-67 156.00$LF
Culvert, LCPE, 54"D-68 168.00$LF
SUBTOTAL THIS PAGE:
(B)(C)(D)(E)
Page 8 of 14
Ref 8-H Bond Quantity Worksheet SECTION II.c DRAINAGE
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 12/19/2019
CED Permit #:
Existing Future Public PrivateRight-of-Way Improvements Improvements
(D)(E)Description No.Unit Price Unit Quant.Cost Quant.Cost Quant.Cost Quant.Cost
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
FOR DRAINAGE AND STORMWATER FACILITIES
Quantity Remaining
(Bond Reduction)(B)(C)
DRAINAGE (Continued)Culvert, LCPE, 60"D-69 180.00$LF
Culvert, LCPE, 72"D-70 192.00$LF
Culvert, HDPE, 6"D-71 42.00$LF
Culvert, HDPE, 8"D-72 42.00$LF
Culvert, HDPE, 12"D-73 74.00$LF
Culvert, HDPE, 15"D-74 106.00$LF
Culvert, HDPE, 18"D-75 138.00$LF
Culvert, HDPE, 24"D-76 221.00$LF
Culvert, HDPE, 30"D-77 276.00$LF
Culvert, HDPE, 36"D-78 331.00$LF
Culvert, HDPE, 48"D-79 386.00$LF
Culvert, HDPE, 54"D-80 441.00$LF
Culvert, HDPE, 60"D-81 496.00$LF
Culvert, HDPE, 72"D-82 551.00$LF
Pipe, Polypropylene, 6"D-83 84.00$LF
Pipe, Polypropylene, 8"D-84 89.00$LF
Pipe, Polypropylene, 12"D-85 95.00$LF
Pipe, Polypropylene, 15"D-86 100.00$LF
Pipe, Polypropylene, 18"D-87 106.00$LF
Pipe, Polypropylene, 24"D-88 111.00$LF
Pipe, Polypropylene, 30"D-89 119.00$LF
Pipe, Polypropylene, 36"D-90 154.00$LF
Pipe, Polypropylene, 48"D-91 226.00$LF
Pipe, Polypropylene, 54"D-92 332.00$LF
Pipe, Polypropylene, 60"D-93 439.00$LF
Pipe, Polypropylene, 72"D-94 545.00$LF
Culvert, DI, 6"D-95 61.00$LF
Culvert, DI, 8"D-96 84.00$LF
Culvert, DI, 12"D-97 106.00$LF 25 2,650.00
Culvert, DI, 15"D-98 129.00$LF
Culvert, DI, 18"D-99 152.00$LF
Culvert, DI, 24"D-100 175.00$LF
Culvert, DI, 30"D-101 198.00$LF
Culvert, DI, 36"D-102 220.00$LF
Culvert, DI, 48"D-103 243.00$LF
Culvert, DI, 54"D-104 266.00$LF
Culvert, DI, 60"D-105 289.00$LF
Culvert, DI, 72"D-106 311.00$LF
SUBTOTAL THIS PAGE:2,650.00
(B)(C)(D)(E)
Page 9 of 14
Ref 8-H Bond Quantity Worksheet SECTION II.c DRAINAGE
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 12/19/2019
CED Permit #:
Existing Future Public PrivateRight-of-Way Improvements Improvements
(D)(E)Description No.Unit Price Unit Quant.Cost Quant.Cost Quant.Cost Quant.Cost
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
FOR DRAINAGE AND STORMWATER FACILITIES
Quantity Remaining
(Bond Reduction)(B)(C)
Specialty Drainage ItemsDitching SD-1 9.50$CY
Flow Dispersal Trench (1,436 base+)SD-3 28.00$LF
French Drain (3' depth)SD-4 26.00$LF
Geotextile, laid in trench, polypropylene SD-5 3.00$SY
Mid-tank Access Riser, 48" dia, 6' deep SD-6 2,000.00$Each
Pond Overflow Spillway SD-7 16.00$SY
Restrictor/Oil Separator, 12"SD-8 1,150.00$Each
Restrictor/Oil Separator, 15"SD-9 1,350.00$Each
Restrictor/Oil Separator, 18"SD-10 1,700.00$Each
Riprap, placed SD-11 42.00$CY
Tank End Reducer (36" diameter)SD-12 1,200.00$Each
Infiltration pond testing SD-13 125.00$HR
Permeable Pavement SD-14
Permeable Concrete Sidewalk SD-15
Culvert, Box __ ft x __ ft SD-16
SUBTOTAL SPECIALTY DRAINAGE ITEMS:
(B)(C)(D)(E)STORMWATER FACILITIES (Include Flow Control and Water Quality Facility Summary Sheet and Sketch)
Detention Pond SF-1 Each
Detention Tank SF-2 50,000.00$Each 1 50,000.00
Detention Vault SF-3 Each
Infiltration Pond SF-4 Each
Infiltration Tank SF-5 Each
Infiltration Vault SF-6 Each
Infiltration Trenches SF-7 Each
Basic Biofiltration Swale SF-8 Each
Wet Biofiltration Swale SF-9 Each
Wetpond SF-10 Each
Wetvault SF-11 Each
Sand Filter SF-12 Each
Sand Filter Vault SF-13 Each
Linear Sand Filter SF-14 Each
Proprietary Facility SF-15 25,000.00$Each 1 25,000.00
Bioretention Facility SF-16 Each
SUBTOTAL STORMWATER FACILITIES:75,000.00
(B)(C)(D)(E)
Page 10 of 14
Ref 8-H Bond Quantity Worksheet SECTION II.c DRAINAGE
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 12/19/2019
CED Permit #:
Existing Future Public PrivateRight-of-Way Improvements Improvements
(D)(E)Description No.Unit Price Unit Quant.Cost Quant.Cost Quant.Cost Quant.Cost
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
FOR DRAINAGE AND STORMWATER FACILITIES
Quantity Remaining
(Bond Reduction)(B)(C)
WRITE-IN-ITEMS (INCLUDE ON-SITE BMPs)WI-1
WI-2
WI-3
WI-4
WI-5
WI-6
WI-7
WI-8
WI-9
WI-10
WI-11
WI-12
WI-13
WI-14
WI-15
SUBTOTAL WRITE-IN ITEMS:
DRAINAGE AND STORMWATER FACILITIES SUBTOTAL:6,975.00 128,363.00
SALES TAX @ 10%697.50 12,836.30
DRAINAGE AND STORMWATER FACILITIES TOTAL:7,672.50 141,199.30
(B) (C) (D) (E)
Page 11 of 14
Ref 8-H Bond Quantity Worksheet SECTION II.c DRAINAGE
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 12/19/2019
CED Permit #:
Existing Future Public Private
Right-of-Way Improvements Improvements
(D)(E)Description No.Unit Price Unit Quant.Cost Quant.Cost Quant.Cost Quant.Cost
Connection to Existing Watermain W-1 2,000.00$Each 1 2,000.00
Ductile Iron Watermain, CL 52, 4 Inch Diameter W-2 50.00$LF
Ductile Iron Watermain, CL 52, 6 Inch Diameter W-3 56.00$LF 6 336.00 171 9,576.00
Ductile Iron Watermain, CL 52, 8 Inch Diameter W-4 60.00$LF
Ductile Iron Watermain, CL 52, 10 Inch Diameter W-5 70.00$LF
Ductile Iron Watermain, CL 52, 12 Inch Diameter W-6 80.00$LF 285 22,800.00
Gate Valve, 4 inch Diameter W-7 500.00$Each
Gate Valve, 6 inch Diameter W-8 700.00$Each
Gate Valve, 8 Inch Diameter W-9 800.00$Each
Gate Valve, 10 Inch Diameter W-10 1,000.00$Each
Gate Valve, 12 Inch Diameter W-11 1,200.00$Each 4 4,800.00
Fire Hydrant Assembly W-12 4,000.00$Each 1 4,000.00
Permanent Blow-Off Assembly W-13 1,800.00$Each
Air-Vac Assembly, 2-Inch Diameter W-14 2,000.00$Each
Air-Vac Assembly, 1-Inch Diameter W-15 1,500.00$Each
Compound Meter Assembly 3-inch Diameter W-16 8,000.00$Each
Compound Meter Assembly 4-inch Diameter W-17 9,000.00$Each
Compound Meter Assembly 6-inch Diameter W-18 10,000.00$Each
Pressure Reducing Valve Station 8-inch to 10-inch W-19 20,000.00$Each
WATER SUBTOTAL:33,936.00 9,576.00
SALES TAX @ 10%3,393.60 957.60
WATER TOTAL:37,329.60 10,533.60
(B) (C) (D) (E)
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
FOR WATER
Quantity Remaining
(Bond Reduction)
(B)(C)
Page 12 of 14
Ref 8-H Bond Quantity Worksheet SECTION II.d WATER
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 12/19/2019
CED Permit #:
Existing Future Public PrivateRight-of-Way Improvements Improvements
(D)(E)Description No.Unit Price Unit Quant.Cost Quant.Cost Quant.Cost Quant.Cost
Clean Outs SS-1 1,000.00$Each 12 12,000.00
Grease Interceptor, 500 gallon SS-2 8,000.00$Each
Grease Interceptor, 1000 gallon SS-3 10,000.00$Each
Grease Interceptor, 1500 gallon SS-4 15,000.00$Each
Side Sewer Pipe, PVC. 4 Inch Diameter SS-5 80.00$LF
Side Sewer Pipe, PVC. 6 Inch Diameter SS-6 95.00$LF 133 12,635.00
Sewer Pipe, PVC, 8 inch Diameter SS-7 105.00$LF 525 55,125.00
Sewer Pipe, PVC, 12 Inch Diameter SS-8 120.00$LF
Sewer Pipe, DI, 8 inch Diameter SS-9 115.00$LF
Sewer Pipe, DI, 12 Inch Diameter SS-10 130.00$LF 29 3,770.00
Manhole, 48 Inch Diameter SS-11 6,000.00$Each 1 6,000.00 5 30,000.00
Manhole, 54 Inch Diameter SS-13 6,500.00$Each
Manhole, 60 Inch Diameter SS-15 7,500.00$Each
Manhole, 72 Inch Diameter SS-17 8,500.00$Each
Manhole, 96 Inch Diameter SS-19 14,000.00$Each
Pipe, C-900, 12 Inch Diameter SS-21 180.00$LF
Outside Drop SS-24 1,500.00$LS 1 1,500.00
Inside Drop SS-25 1,000.00$LS
Sewer Pipe, PVC, ____ Inch Diameter SS-26Lift Station (Entire System)SS-27 LS
SANITARY SEWER SUBTOTAL:6,000.00 90,395.00 24,635.00
SALES TAX @ 10%600.00 9,039.50 2,463.50
SANITARY SEWER TOTAL:6,600.00 99,434.50 27,098.50
(B) (C) (D) (E)
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
FOR SANITARY SEWER
Quantity Remaining
(Bond Reduction)(B)(C)
Page 13 of 14
Ref 8-H Bond Quantity Worksheet SECTION II.e SANITARY SEWER
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 12/19/2019
Planning Division |1055 South Grady Way – 6th Floor | Renton, WA 98057 (425) 430-7200
Date:
Name: Project Name:
PE Registration No: CED Plan # (LUA):
Firm Name:CED Permit # (U):
Firm Address: Site Address:
Phone No. Parcel #(s):
Email Address:Project Phase:
Site Restoration/Erosion Sediment Control Subtotal (a)
Existing Right-of-Way Improvements Subtotal (b) (b)14,081.10$
Future Public Improvements Subtotal (c)141,384.10$
Stormwater & Drainage Facilities(Public & Private)Subtotal (d) (d)148,871.80$
(e)
(f)
Site Restoration
Civil Construction Permit
Maintenance Bond 60,867.40$
Bond Reduction 2
Construction Permit Bond Amount 3
Minimum Bond Amount is $10,000.00
1Estimate Only - May involve multiple and variable components, which will be established on an individual basis by Development Engineering.
2 The City of Renton allows one request only for bond reduction prior to the maintenance period. Reduction of not more than 70% of the original bond amount, provided that the remaining 30% will
cover all remaining items to be constructed.
3Required Bond Amounts are subject to review and modification by Development Engineering.
* Note: The word BOND as used in this document means any financial guarantee acceptable to the City of Renton.
** Note: All prices include labor, equipment, materials, overhead and profit.
(206) 596-7115
peter@coterraengineering.com
Willowcrest Townhomes
19-000061,BSP,PUD
1132 Edmonds Ave NE
0923059080
FOR APPROVAL
321 3rd Ave South, #406, Seattle, WA 98104
175,456.05$
P
(a) x 100%
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
BOND CALCULATIONS
12/18/2019
Peter Apostol, PE
35163
Coterra Engineering
R
((b x 150%) + (d x 100%))
S
(e) x 150% + (f) x 100%
Bond Reduction: Existing Right-of-Way Improvements (Quantity
Remaining)2
Bond Reduction: Stormwater & Drainage Facilities (Quantity
Remaining)2
T
(P +R - S)
Prepared by: Project Information
CONSTRUCTION BOND AMOUNT */**
(prior to permit issuance)
EST1
((b) + (c) + (d)) x 20%
-$
MAINTENANCE BOND */**
(after final acceptance of construction)
5,462.60$
14,081.10$
169,993.45$
5,462.60$
-$
148,871.80$
-$
Page 14 of 14
Ref 8-H Bond Quantity Worksheet SECTION III. BOND WORKSHEET
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 12/19/2019
Appendix G
Conveyance Calculations
Conveyance Capacity Check
Input pipe size, n value and slope to calculate capacity of pipe flowing full
Pipe Typ. Slope Qf Vf
pipe full pipe full
(in.)n (ft./ft.)(cfs)(ft/s)
8 0.012 0.01 1.313 3.76
Q 100 yr (whole, developed project site)0.603 CFS (From MGSFlood)
Q 100 yr (upstream run-on from adjacent properties)0.074 CFS (From MGSFlood)
Q 100 yr (Glennwood Townhomes TDA #2)0.194 CFS (From MGSFlood)
0.871 CFS TOTAL
USING MANNINGS EQUATION, 8" DIAMETER STORM PIPE WITH A MINIMUM SLOPE OF 1% WILL
MEET CAPACITY REQUIREMENTS
coterra
collaborative civil engineering + site development + infrastructure design
coterra321 3rd Avenue South, Suite 406Seattle, Washington 98104206.596.7115 coterraengineering.comENGINEERING PLLC
—————————————————————————————————
MGS FLOOD
PROJECT REPORT
Program Version: MGSFlood 4.38
Program License Number: 201510001
Project Simulation Performed on: 12/19/2019 8:06 AM
Report Generation Date: 12/19/2019 8:07 AM
—————————————————————————————————
Input File Name: Willowcrest - Upstream Run On.fld
Project Name: Renton Homestead
Analysis Title: Peak Flow - Upstream
Comments:
———————————————— PRECIPITATION INPUT ————————————————
Computational Time Step (Minutes): 15
Extended Precipitation Time Series Selected
Climatic Region Number: 13
Full Period of Record Available used for Routing
Precipitation Station : 96004005 Puget East 40 in_5min 10/01/1939-10/01/2097
Evaporation Station : 961040 Puget East 40 in MAP
Evaporation Scale Factor : 0.750
HSPF Parameter Region Number: 1
HSPF Parameter Region Name : USGS Default
********** Default HSPF Parameters Used (Not Modified by User) ***************
********************** WATERSHED DEFINITION ***********************
Predevelopment/Post Development Tributary Area Summary
Predeveloped Post Developed
Total Subbasin Area (acres) 0.145 0.145
Area of Links that Include Precip/Evap (acres) 0.000 0.000
Total (acres) 0.145 0.145
----------------------SCENARIO: PREDEVELOPED
Number of Subbasins: 1
---------- Subbasin : Basin A - Existing ----------
-------Area(Acres) --------
Till Forest 0.000
Till Pasture 0.000
Till Grass 0.145
Outwash Forest 0.000
Outwash Pasture 0.000
Outwash Grass 0.000
Wetland 0.000
Green Roof 0.000
User 2 0.000
Impervious 0.000
----------------------------------------------
Subbasin Total 0.145
----------------------SCENARIO: POSTDEVELOPED
Number of Subbasins: 1
---------- Subbasin : Basin A - Proposed ----------
-------Area(Acres) --------
Till Forest 0.000
Till Pasture 0.000
Till Grass 0.145
Outwash Forest 0.000Outwash Pasture 0.000
Outwash Grass 0.000
Wetland 0.000
Green Roof 0.000
User 2 0.000
Impervious 0.000
----------------------------------------------
Subbasin Total 0.145
************************* LINK DATA *******************************
----------------------SCENARIO: PREDEVELOPED
Number of Links: 0
************************* LINK DATA *******************************
----------------------SCENARIO: POSTDEVELOPED
Number of Links: 0
**********************FLOOD FREQUENCY AND DURATION STATISTICS*******************
----------------------SCENARIO: PREDEVELOPED
Number of Subbasins: 1
Number of Links: 0
----------------------SCENARIO: POSTDEVELOPED
Number of Subbasins: 1
Number of Links: 0
***********Groundwater Recharge Summary *************
Recharge is computed as input to Perlnd Groundwater Plus Infiltration in Structures
Total Predeveloped Recharge During Simulation
Model Element Recharge Amount (ac-ft)
-----------------------------------------------------------------------------------------------
Subbasin: Basin A - Existing 17.721
_____________________________________
Total: 17.721
Total Post Developed Recharge During Simulation
Model Element Recharge Amount (ac-ft)
-----------------------------------------------------------------------------------------------
Subbasin: Basin A - Proposed 17.721
_____________________________________
Total: 17.721
Total Predevelopment Recharge Equals Post Developed
Average Recharge Per Year, (Number of Years= 158)
Predeveloped: 0.112 ac-ft/year, Post Developed: 0.112 ac-ft/year
***********Water Quality Facility Data *************
----------------------SCENARIO: PREDEVELOPED
Number of Links: 0
----------------------SCENARIO: POSTDEVELOPED
Number of Links: 0
***********Compliance Point Results *************
Scenario Predeveloped Compliance Subbasin: Basin A - Existing
Scenario Postdeveloped Compliance Subbasin: Basin A - Proposed
*** Point of Compliance Flow Frequency Data ***
Recurrence Interval Computed Using Gringorten Plotting Position
Predevelopment Runoff Postdevelopment Runoff
Tr (Years) Discharge (cfs) Tr (Years) Discharge (cfs)
----------------------------------------------------------------------------------------------------------------------
2-Year 1.364E-02 2-Year 1.364E-02
5-Year 2.339E-02 5-Year 2.339E-02
10-Year 3.425E-02 10-Year 3.425E-02
25-Year 5.196E-02 25-Year 5.196E-02
50-Year 6.728E-02 50-Year 6.728E-02
100-Year 7.389E-02 100-Year 7.389E-02
200-Year 8.125E-02 200-Year 8.125E-02
** Record too Short to Compute Peak Discharge for These Recurrence Intervals
Appendix H
Drainage Review Flow Chart
SECTION 1.1 DRAINAGE REVIEW
12/12/2016 2017 City of Renton Surface Water Design Manual 1-14
FIGURE 1.1.2.A FLOW CHART FOR DETERMINING TYPE OF DRAINAGE REVIEW REQUIRED