HomeMy WebLinkAboutSMP ERC Report 10-028ERC Report.docx
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
ENVIRONMENTAL REVIEW COMMITTEE REPORT
ERC MEETING DATE: May 10, 2010
Project Name: Shoreline Master Program Update
Owner: N/A
Applicant: City of Renton, Department of Community and Economic Development
Contact: Erika Conkling, AICP x6578
File Number: LUA 10-028, ECF
Project Manager: Erika Conkling, AICP x6578
Project Summary: This non-project action adopts new policies and regulations to manage shorelines
within the City of Renton.
Project Location: The proposed changes would affect properties within Renton City limits in the
vicinity of Lake Washington, Lake Desire, the Cedar River, the Green River, the
Black River, May Creek, and Springbrook Creek. Areas outside Renton City limits in
the vicinity of these waterbodies could be affected in the future upon annexation.
Exist. Bldg. Area SF: N/A Proposed New Bldg. Area (footprint):
Proposed New Bldg. Area (gross):
N/A
N/A
Site Area: N/A Total Building Area GSF: N/A
STAFF
RECOMMENDATION:
Staff Recommends that the Environmental Review Committee issue a
Determination of Non-Significance (DNS).
PART ONE: PROJECT DESCRIPTION / BACKGROUND
Update of Renton’s Shoreline Master Program (SMP) is required by state mandate and must comply with
the guidelines in WAC 173-26. The SMP provides policies and regulations for the use and development of
all property subject to shoreline jurisdiction under the Shoreline Management Act (SMA). It consists of a
series of documents that will be adopted by the Renton City Council and the Washington State
Department of Ecology. Those documents include: the Shoreline Management element of the
Comprehensive Plan; multiple amendments to Title IV of the Renton Municipal Code, including sections: 4-
3-090 Shoreline Master Program Regulations, 4-8-120 Submittal Requirements, Specific to Application
Type, 4-9-190 Shoreline Permits, 4-10-095 Shoreline Master Program, Nonconforming Uses, Activities,
Structures, and Sites, and Definitions in chapter 4-11; the Restoration Plan; and the map Renton Shoreline
Environment Overlays. The proposed SMP is based upon information in the supporting document Revised
Draft Shoreline Inventory and Analysis. The impacts of the proposed SMP are reviewed in the document
Shoreline Cumulative Effects Analysis. All documents are available for review on the project website:
www.shoreline.rentonwa.gov
Several drafts of the SMP have been prepared and reviewed. A previous notice of application and
comment period was issued for the October 2009 public hearing draft of the SMP. Several changes have
been made to the SMP since that time, particularly affecting sections related to the regulation of:
City of Renton Department of Community & Economic Development Environmental Review Committee Report
SHORELINE MASTER PROGRAM UPDATE LUA 10-028, ECF
Report of May 10, 2010 Page 2 of 5
ERC Report.docx
wetlands, dredging for existing uses, standards for docks and piers, and setback and buffer requirements
for existing single-family homes, recognition of vested rights, and non-water-oriented uses in high intensity
environments. This determination is based on the March 2010 SMP draft. Based on the Shoreline
Cumulative Effects Analysis, the proposed SMP should result in no net loss of ecological function, as
required under state law.
PART TWO: ENVIRONMENTAL REVIEW
In compliance with RCW 43.21C.240, the following environmental (SEPA) review addresses only those
project impacts that are not adequately addressed under existing development standards and
environmental regulations.
A. Environmental Threshold Recommendation
Based on analysis of probable impacts from the proposal, staff recommends that the Responsible
Officials:
Issue a DNS with a 14-day Appeal Period with a concurrent 14-day Comment Period.
B. Mitigation Measures
1. None.
C. Exhibits
Exhibit 1 Shoreline Overlay Environments Map
Exhibit 2 CD- SMP SEPA Support Documents, containing Revised Draft Shoreline Inventory
and Analysis, March 2010 and the Shoreline Cumulative Effects Analysis, March
2010
D. Environmental Impacts
The proposal is likely to have the following probable impacts:
1. Earth
Impacts: This non-project proposal will have no significant adverse impacts to the land/earth.
Mitigation Measures: None.
Nexus: N/A
2. Air
Impacts: This non-project proposal will have no significant adverse impacts to the air.
Mitigation Measures: None.
Nexus: N/A
3. Water
a. Wetland, Streams, Lakes
Impacts: This non-project proposal will have no significant adverse impacts to wetlands, streams,
or lakes. The goal of the implementation of the proposal is to achieve, at a minimum, no net loss of
ecological functions or processes in these areas, and in the ideal situation, to gradually restore
these areas over time.
City of Renton Department of Community & Economic Development Environmental Review Committee Report
SHORELINE MASTER PROGRAM UPDATE LUA 10-028, ECF
Report of May 10, 2010 Page 3 of 5
ERC Report.docx
Mitigation Measures: None.
Nexus: N/A
b. Ground Water
Impacts: This non-project proposal will have no significant adverse impacts to ground water
resources.
Mitigation Measures: None.
Nexus: N/A
c. Storm Water
Impacts: This non-project proposal will have no significant adverse impacts to storm water control,
and in fact as shoreline buffers are created and planted, existing storm water control may be
improved over time.
Mitigation Measures: None.
Nexus: N/A
4. Vegetation
Impacts: This non-project proposal will have no significant adverse impacts on vegetation. The
proposal encourages retention of existing shoreline vegetation, and the restoration of vegetation in
shoreline buffer areas with re-development of properties and for the establishment of non-water-
oriented uses within shoreline jurisdiction. It is reasonable to expect a net increase in vegetation
over time.
Mitigation Measures: None.
Nexus: N/A
5. Wildlife
Impacts: This non-project proposal will have no significant adverse impacts on wildlife. The
proposal encourages retention and restoration of shoreline habitat for all types of wildlife,
including for endangered salmonids. The goal of the implementation of the project is to result in,
at a minimum, no net loss of ecological functions and processes, and ideally, to gradually restore
ecological function and processes over time. This will provide a net benefit to wildlife.
Mitigation Measures: None.
Nexus: N/A
6. Energy and Natural Resources
Impacts: This non-project proposal will have no significant adverse impacts to energy and natural
resources.
Mitigation Measures: None.
Nexus: N/A
7. Environmental Health
a. Environmental Health Hazards
Impacts: This non-project proposal will have no significant adverse impacts to environmental
health.
City of Renton Department of Community & Economic Development Environmental Review Committee Report
SHORELINE MASTER PROGRAM UPDATE LUA 10-028, ECF
Report of May 10, 2010 Page 4 of 5
ERC Report.docx
Mitigation Measures: None.
Nexus: N/A
b. Noise
Impacts: This non-project proposal will have no significant adverse noise impacts.
Mitigation Measures: None.
Nexus: N/A
8. Aesthetics
Impacts: This non-project proposal will have no significant adverse impacts on aesthetics.
Mitigation Measures: None.
Nexus: N/A
9. Light and Glare
Impacts: This non-project proposal will have no significant adverse light and glare impacts.
Mitigation Measures: None.
Nexus: N/A
10. Parks and Recreation
Impacts: This non-project proposal will have no significant adverse impacts on parks and recreation
opportunities. One of the goals of the SMA is to increase public access to the shoreline, with the
intent, in part, of allowing more recreational access and public enjoyment. Opportunities for
additional public access will be created over time as properties redevelop.
Mitigation Measures: None.
Nexus: N/A
11. Historic and Cultural Preservation
Impacts: This non-project proposal will have no significant adverse impact on historic and cultural
preservation. Any impacts to potential or known archaeological sites that occurred as a result of
development allowed by the SMP would be evaluated at the time of project specific review. A
section of the SMP recognizes the treaty rights of tribes to use the shorelines.
Mitigation Measures: None.
Nexus: N/A
12. Transportation
Impacts: This non-project proposal will have no significant adverse impact in regard to
transportation concerns.
Mitigation Measures: None.
Nexus: N/A
13. Fire & Police
Impacts: This non-project proposal will have no significant adverse impact in regard to fire and
police protection.
City of Renton Department of Community & Economic Development Environmental Review Committee Report
SHORELINE MASTER PROGRAM UPDATE LUA 10-028, ECF
Report of May 10, 2010 Page 5 of 5
ERC Report.docx
Mitigation Measures: None.
Nexus: N/A
14. Public Services
Impacts: This non-project proposal will have no significant adverse impact in regard to the
provision of public services.
Mitigation Measures: None.
Nexus: N/A
15. Utilities
Impacts: This non-project proposal will have no significant adverse impact in regard to utility
service.
Mitigation Measures: None.
Nexus: N/A
E. Comments of Reviewing Departments
The proposal has been circulated to City Department and Division Reviewers. Where applicable, their
comments have been incorporated into the text of this report and/or “Advisory Notes to Applicant.”
Copies of all Review Comments are contained in the Official File and may be attached to this
report.
Environmental Determination Appeal Process: Appeals of the environmental determination must be
filed in writing on or before 5:00 PM, May 28, 2010.
Renton Municipal Code Section 4-8-110.B governs appeals to the Hearing Examiner. Appeals must be filed
in writing at the City Clerk’s office along with the required fee. Additional information regarding the
appeal process may be obtained from the City Clerk’s Office, Renton City Hall - 7th Floor, 1055 S. Grady
Way, Renton WA 98057.