HomeMy WebLinkAbout0895.06 E 04052022.pdf
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100 Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com
FIELD REPORT
Project No. 0895.06 Page 1 of 2 Report ID 0895.06 E 04052022
Date Tue 4/5/2022 Weather 50F Cloudy
Arrival/Departure Time(s) 10:00 AM/ 10:15 AM Travel Time (hr) 1.25
Project Name Weatherly Inn
Location 4500 Talbot Road S., Renton
ESNW Rep. & Phone Jackson Lundgren 206-468-0991
Client Info/Contact RJ Development | Duane Meyer
General Contractor Info/Contact Johannsen | Brad
Permit No(s).
Reviewed By LAC
Initials/Date
SSR
Initials/Date Field Supervisor Project Manager
Limitations: The presence of our field representative at the site is to provide our client with a source of professional advice, opinions, and recommendations based upon the field representative’s
observations and testing of the contractor’s work. Our services do not include supervision or direction of the contractor, their employees, or agents. Geotechnical recommendations for obtaining project objectives may be made by our representatives; however, direction of the actual work should come from the owner or contractor, as appropriate. The contractor is responsible for complying with the contract documents at all times, regardless of the presence of our field representative. Jobsite safety, including compliance with all applicable state or federal regulations, is the sole responsibility of the contractor. The observations, recommendations, and conclusions provided in this field report are preliminary until reviewed by the ESNW project manager.
As requested by the client, ESNW rep was onsite at the Weatherly Inn development to observe and
document slope conditions during wall excavation. While onsite the following was observed:
Wall Excavation Slope Conditions:
ESNW rep arrived onsite and observed that the contractor was continuing installation of rebar and
concrete wall forms. ESNW rep observed the 6-block high eco block wall within the excavation remained
stable, and native soil conditions were suitable for temporary vertical cut slope. The slopes of the
excavation were observed to be stable and unchanging in their current temporary over steepened
condition, however it is the responsibility of the contractor to perform all necessary safety
measures in accordance with state and federal regulations. ESNW rep observed contractor
should re-anchor damaged plastic sheeting. Contractor should contact ESNW for further observations
if any changes in slope condition occur. ESNW rep will return as requested by client for further
observations.
Fig. 1: Plastic sheeting partially covering slopes along wall excavation.
Report ID 0895.06 E 04052022 Page 2 of 2
Earth Solutions NW, LLC
Fig. 2: Approximate area of plastic sheeting requiring re-anchoring
Re-anchor plastic sheeting