HomeMy WebLinkAboutCO 21
CAG-20-126, CO #21-22
Approved by Cheryl Beyer via 1/31/2022 email
Change Order No. 21
Contract Title: Lake Washington Loop Trail
Contract No. CAG -20-126
Page 2 of 3
THE CONTRACT IS MODIFIED AS FOLLOWS:
Description of Change:
Change to Contract Plans:
As required in FWD No 19, the Contractor is directed to implement additional traffic control measures to
keep the cycle track closed during the material suspension for the traffic signal and for the bridge railing.
Reason for Change:
Contract Plans:
The segment of the cycle track between the intersections of Rainier Ave/Airport Way and E Perimeter
Drive/Logan Avenue may not be opened to users until traffic signal improvements are made at the
intersection of Shattuck/Airport Way.
The segment of the cycle track along the bridge over the Cedar River on Logan Avenue may not be
opened to users until the bridge railing is installed.
Materials:
No changes
Plans:
Plans Sheets for Cycle Track Closure: S7.02 Rev 1, S7.04 Rev 1, S7.05 Rev 2, S7.06 Rev 2
Plans Sheets for Cycle Track on Bridge Closure: S7.05 Rev 2, S7.06 Rev 2
Estimated Change Order Cost:
This Change Order does include an estimated equitable adjustment per Section 1-09.4
of the 2020 WSDOT/APWA Standard Specifications.
The Work will be measured and paid under the lump sum price of $6,410.70.
See attached.
Change Order No. 21
Contract Title: Lake Washington Loop Trail
Contract No. CAG -20-126
Page 3 of 3
Extension of Time:
The Contractor agrees that the time for Completion is extended 0 Working Days for the
additional work.
Sections 1-04.4 and 1-04.5 of the 2020 WSDOT/APWA Standard Specifications shall govern
this Change Order. The Work of the referenced Contract is modified to include the changes
detailed herein. The payment provided for herein shall constitute the complete and final
settlement for all costs of labor, equipment, materials, overhead, profit, permit fees, and all
other claims that may be made by the Contractor as a result of this change.
Attachments:
Forms to be attached to Change Order
܈ Plans
܈Equitable Adjustment Determination
New Lump
Sum Item
No.Description Quantity Unit
Lump Sum
Price Cost
CO21-1
Additional Traffic Control for Cycle
Track Closure during Material
Suspension 1 LS $6,410.70 $6,410.70
$6,410.70
$6,410.70
Contractor: Active Construction Inc.
Federal Aid No: TAP-1070(008)
Contract No: CAG 20-126
Construction Manager: Tani Stafford, PE
Equitable Adjustment Determination - CO 21
Change Order Cost
By:
Date: 12/29/2021
Lump Sum Item
Lump Sum Item Cost
Project Name: Lake Washington Loop Trail
CITY OF RENTONBY: DATE:APPROVED FOR CONSTRUCTIONOF11241 Willows Road NE, Suite 200Redmond, WA 98052425.822.4446www.otak.comType 3 Barricade withRoad Closed SignFWD 19-TCP for Cycle Track Closure TLS 7/21/2111
CITY OF RENTONBY: DATE:APPROVED FOR CONSTRUCTIONOF11241 Willows Road NE, Suite 200Redmond, WA 98052425.822.4446www.otak.comType 3 Barricade withRoad Closed signFWD 19-TCP for Cycle Track Closure TLS 7/21/2111
CITY OF RENTONBY: DATE:APPROVED FOR CONSTRUCTIONOF11241 Willows Road NE, Suite 200Redmond, WA 98052425.822.4446www.otak.comType 3 BarricadeBike Detour M4-9C(Left Arrow) (x2)Bike Yield toPeds R9-6(Orange) (x2)trafficdrum (typ)30' O.C.Type 3Barricadewith RoadClosedSignFWD 19-TCP for Cycle Track Closure TLS 7/21/212222
CITY OF RENTONBY: DATE:APPROVED FOR CONSTRUCTIONOF11241 Willows Road NE, Suite 200Redmond, WA 98052425.822.4446www.otak.comType 3Barriertrafficdrum 30'O.C. (typ)Bikes W11-1(Orange)DetourAhead W20-2(Orange)Bike Detour M4-9C(Right Arrow)Bike Yield toPeds R9-6(Orange)Bike Detour M4-9C(Right Arrow)Bike Yield toPeds R9-6(Orange)FWD 19-TCP for Cycle Track Closure TLS 7/21/2122222
CITY OF RENTONBY: DATE:APPROVED FOR CONSTRUCTIONOF11241 Willows Road NE, Suite 200Redmond, WA 98052425.822.4446www.otak.comType 3 BarricadeBike Detour M4-9C(Left Arrow) (x2)Bike Yield toPeds R9-6(Orange) (x2)Bikes W11-1(Orange)trafficdrum (typ)30' O.C.DetourAhead W20-2(Orange)2 FWD 18- Cycle Track on Bridge Closure TLS 7/21/21222
CITY OF RENTONBY: DATE:APPROVED FOR CONSTRUCTIONOF11241 Willows Road NE, Suite 200Redmond, WA 98052425.822.4446www.otak.comType 3Barriertrafficdrum 30'O.C. (typ)Bikes W11-1(Orange)DetourAhead W20-2(Orange)Bike Detour M4-9C(Right Arrow)Bike Yield toPeds R9-6(Orange)Bike Detour M4-9C(Right Arrow)Bike Yield toPeds R9-6(Orange)2 FWD 18- Cycle Track on Bridge Closure TLS 7/21/212222