HomeMy WebLinkAboutCO 4AMENDMENT NO. 4 TO CAG 20-113 SMALL WORK CONTRACT
AGREEMENT FOR SIGNAL POLE RELOCATION
THIS AMENDMENT, dated for reference purposes only as April 12, 2022, is by and between the
City of Renton (the “City”), a Washington municipal corporation, and Prime Electric Inc.
(“Contractor”). The City and the Contractor are referred to collectively in this Amendmentas the
“Parties.” Once fully executed by the Parties, this Amendment is effective as of the last date
signed by both parties.
Whereas, the City engaged the services of the Contractor under Agreement CAG-20-113, dated
May 27, 2020, to provide necessary services for the replacement of a signal pole that was severely
damaged and causes a public safety hazard on the North side of the intersection of S. Grady Way
and Talbot Road S. In addition to the signal pole being replaced the signal pole foundation will
need to be relocated to the NE corner of the intersection (referred to herein as the "Agreement").
Whereas, the Parties wish to amend the Agreement to change the compensation
as settlement for a disputed amounts including taxes.
NOW THEREFORE, It is mutually agreed upon that CAG-20-113 is amended as follows:-
1. Compensation: Section 4, Compensation, is amended so that the maximum amount of
compensation payable to the consultant is increased by $3,356.04 from $109,222.94 to
$112,578.98 as a settlement for disputed amounts including taxes .
2.All terms of the Agreement not explicitly modified herein shall remain in full force and
effect and such terms shall apply to Work performed according to this Amendment as if
fully set forth herein.
CAG-20-113, CO #4-22
PAGE 2 OF 2
IN WITNESS WHEREOF, the Parties have voluntarily entered into this Amendment as of the date
last signed by the Parties below.
CITY OF RENTON
By:_____________________________
CONSULTANT
By:____________________________
Martin Pastucha
Public Works Administrator
Oliver Whitehead
Chief Operations Manager
_____________________________
Date
_____________________________
Date
Approved as to Legal Form
By: __________________________
Cheryl Beyer
Sr. Assistant City Attorney
Contract Template Updated 06/17/2021
Clb 4-12-22 (1192)
4/19/2022
Oliver Whitehead
Digitally signed by Oliver Whitehead
DN: C=US,
E=PNW-Contracts@primee.com,
O="Prime Electric, LLC", OU="Prime
Electric, LLC", CN=Oliver Whitehead
Date: 2022.04.19 14:41:27-07'00'
(approved via email from Cheryl Beyer on 4/14/2022)
3460 161st AVE SE Bellevue, WA 98008 | (P) 425.747.5200 | primee.com
Item # Item Description Unit
Measure
Unit Cost
1 Use Tax LS $ 3,356.04
Item 1 – Vault Racking Scope of work:
•Use tax on all applicable materials - $2,749.72
•Mark up per WSDOT 1-09.6(2) Materials - $577.44
•B&O Tax - $28.88
Terms and Conditions:
•All access into the above identified scope of work area will be coordinated prior to commencement. Access will
be provided in a timely manner to all facilities where work is requested. Delays and/or interruptions resulting
from lack of access may result in additional charges.
•Traffic control coordination is required and will be coordinated and provided by General Contractor.
•All work will be performed in accordance with standards, state and local codes in effect at the time of quote.
•Provisions for a lay-down area for secure on-site storage and job shack location will be coordinated prior to
commencement of scope.
•Change Order: If changes are required during the course of this project, a written contract modification will be
prior to procurement or execution of change order.
•Contingent upon mutually agreeable project schedule and contract documents.
•Assumption of scope, terms and conditions, and specific exclusions to be incorporated into contract documents.
•Deletion of scope must be agreed upon by Prime Electric prior to award.
•Standard Insurance included.
•Payment Terms: Standard payment terms are net 30 from the date of invoice.
•Retention will be at 5% maximum and released no more than 60 days following last invoice, or earlier.
•Confidential Information: This bid information is confidential and proprietary, for use only by its intended
recipients.
•We have reviewed and accounted for addendums. (None provided)
•Liquid damages will be assessed only if they are caused by Prime’s scope
•Lead time on signal poles are being Quoted at 4-6 months after receipt of stamped approved submittals.
*Note: Commodities such as wire and conduit cost can fluctuate daily, and equipment pricing generally adjusts quarterly.
All other pricing is subject to change and will be locked in once final award has been given.
**Note: Due to the unknown impact of COVID-19 related schedule and cost impacts, we have not included any potential
impacts in our proposal.
***Note: Due to continued daily fluctuation of prices, our price presented is good for a time of 30 days.
Attn: Eric Cutshall Date: 4-7-2022
Company: City of Renton Re: Talbot and Gray Pole Relocate
Address: Project Number:
Phone: 425-430-7423 From: Andrew Hollenback
Cell: E-Mail:AHollenback@primee.com
Email: ECutshall@Rentonwa.gov Phone:425-864-1753
Exhibit A-4
DocuSign Envelope ID: 8AA3C772-56FB-4B99-8DEE-44D7D86CA043
3460 161st AVE SE Bellevue, WA 98008 | (P) 425.747.5200 | primee.com
Specific Exclusions:
• Sales Tax
• Bonds
• Engineering, Survey, and/or Layouts.
• Hazardous Material Handling and Disposal.
• Dewatering
• All work of other crafts.
• Weekend or Night premiums (Standard work hours of 7am-3:30pm)
• Concrete, Asphalt & Landscaping demolition or permanent restoration
• Removal of existing concrete foundations and backfill
• Traffic Control and UPOs
• Temp site power
• Temp lighting
• Temp signal work / video detection
• Unforeseen Subsurface Conditions
• Landscape Removal/Restoration
• Utility Company Fees
• Any work or coordination pertaining to PSE owned lighting
• All Excavation, shoring, bedding, and backfill
• Concrete flatwork or pads
• Cutting or re-terminating / splicing of fiber.
Our goal is to provide quality construction with competitive pricing; we can accomplish this with your feedback. If you
should require any additional information regarding our bid response or could offer feedback to improve our bid
response, please contact me.
Respectfully,
Andrew Hollenback
Andrew Hollenback
Project Manager
DocuSign Envelope ID: 8AA3C772-56FB-4B99-8DEE-44D7D86CA043
CUSTOMER Date COP #F A #Cont #
4/7/2022 4
LABOR COSTS HOURS RATE
EMPLOYEE Name CLASS Reg OT DT Swing Night Reg OT DT Swing Night
Totals - - - - -
PRIME OWNED EQUIPMENT MATERIALS
Unit #Hours Rate Total Cost Qty Unit Rate TOTAL
191 - 45.00 - 1 - 2,749.72 2,749.72
166 - 58.95 - - - - -
270 - 38.64 - - - - -
280 - 54.90 - - - - -
282 - 54.91 - - - - -
190 - 57.39 - - - - -
179 - 62.50 - - - - -
T22 - 15.03 - - - - -
T28 - 15.50 - - - - -
142 - 62.50 - - - - -
T16 - 32.50 - - - - -
TH1 - 35.63 - - - - -
TH2 - 35.63 - - - - -
TH3 - 41.18 - - - - -
T31 - 50.00 - - - - -
B2 - 38.66 - - - - -
T12 - 8.75 - - - - -
T14 - 15.63 - - - - -
T29 - 18.29 - - - - -
- TOTAL MATERIALS 2,749.72
RENTAL EQUIPMENT TOTALS
DESCRIPTION QTY Hours Rate Total Cost TOTAL LABOR -
- - - - TOTAL PRIME EQUIPMENT -
- - - - TOTAL MATERIALS 2,749.72
- - - - -
- - - - TOTAL SUBCONTRACTORS -
- - - - TOTAL RENTAL EQUIP.-
- - - - 2,749.72
- - - - LABOR 29.00%-
- EQUIPMENT 21.00%-
SUBCONTRACTORS MATERIALS 21.00%577.44
SUBCONTRACTORS QTY Hours Rate Total Cost SUBCONTRACTOR 12.00%-
- - - - RENTAL EQUIPMENT 21.00%-
- - - - 3,327.16
- - - - B&O Tax 0.87%TAX 28.88
- 3,356.04
Estimate
JOB #
Use Tax
TOTAL
COST
-
-
City of Renton - Eric Cutshall 3001597 13410
PROJECT Talbot Road S and S Grady Way Pole Relocate
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL LABOR COST -
DESCRIPTION DESCRIPTION
-
-
-
-
-
-
Ford F650 Dump Truck -
Ford F550 utility flatbed w/tools -
Ford F150 utility flatbed w/tools USE Tax on Materials
Ford F450 utility flatbed w/tools -
Frieghtliner FL90 Auger truck -
Dump Trailer (5 yd)-
Ford F550 utility flatbed w/tools (SUPT)-
Ford F550 4x4 Utility truck w/38' manlift -
Crafco SS60 Loop Sealant machine - trailer mounted -
Takeuchi mini excavator -
Dump Trailer (5 yd)-
International 4500 w/50' manlift -
Pole Trailer -
Case 580SL 4x4 Backhoe w/extendhoe -
Case mini excavator -
Cat mini excavator -
Air Compressor -
TOTAL EQUIPMENT
-
Backhoe Trailer -
Air Compressor -
TOTAL DIRECT
-
-
-
-
TOTAL RENTAL EQUIPMENT
0
-
-
13301 SE 26th Street
Bellevue, Washington
- SUBTOTAL
-
TOTAL SUBCONTRACTORS TOTAL THIS Change Order
DocuSign Envelope ID: 8AA3C772-56FB-4B99-8DEE-44D7D86CA043
Filing Period:March 31, 2022 Due Date:April 25, 2022
Filing Frequency:Monthly
601-004-783
PRIME ELECTRIC LLC
Combined Excise Tax Return
Business & Occupation
Tax Classification Gross Amount Deductions Taxable Amount Tax Rate Tax Due
Wholesaling 20,084,891.27 0.00 20,084,891.27 97,210.870.004840
Retailing 2,446,092.49 0.00 2,446,092.49 11,521.100.004710
Whse-Radio/TV Brdcst-Pub Rd
Constr/Govt Contr/Chem Dependency
Ctr/Canned Salmon Labelers
168,674.07 0.00 168,674.07 816.380.004840
109,548.35Total Business & Occupation
State Sales and Use
Tax Classification Gross Amount Deductions Taxable Amount Tax Rate Tax Due
Use Tax 38,542.88 0.00 38,542.88 2,505.290.065000
Retail Sales 2,446,092.49 0.00 2,446,092.49 158,996.010.065000
161,501.30Total State Sales and Use
Local City and/or County Sales Tax
Location Taxable Amount Tax Rate Tax Due
0502 - PORT ANGELES -2,904.90 -66.810.023000
1700 - KING COUNTY RTA 495.55 17.840.036000
1701 - ALGONA 330.00 11.880.036000
1702 - AUBURN/KING RTA 2,089.00 75.200.036000
1704 - BELLEVUE RTA 349,197.12 12,571.100.036000
1706 - BOTHELL/KING 10,809.98 389.160.036000
1709 - DES MOINES 1,930.00 69.480.036000
Deductions
Tax Classification Deduction Amount
Business & Occupation
Other: 0.00Retailing
State Sales and Use
Sales of Batteries / Infrastructure for Electric and Hybrid Vessels 0.00Retail Sales
This amount shows the state USE tax rate paid - includes the $27,224.94 in materials
for the Talbot and Grady project. See last page for spreadsheet breakout
DocuSign Envelope ID: 8AA3C772-56FB-4B99-8DEE-44D7D86CA043
1712 - COVINGTON 1,948.00 0.022000 42.86
1714 - ISSAQUAH RTA 13,702.27 493.280.036000
1715 - KENT RTA 99,193.47 3,570.960.036000
1716 - KIRKLAND 26,581.78 983.530.037000
1718 - MEDINA 69,349.16 2,496.570.036000
1719 - MERCER ISLAND 5,345.13 192.420.036000
1724 - REDMOND RTA 703,684.68 25,332.650.036000
1725 - RENTON RTA -85,528.51 -3,079.030.036000
1726 - SEATTLE 936,818.58 35,130.700.037500
1728 - SNOQUALMIE 8,925.00 196.350.022000
1729 - TUKWILA 47,539.01 1,711.400.036000
1732 - FEDERAL WAY 1,825.01 65.700.036000
1733 - SEATAC 25,442.68 915.940.036000
1734 - BURIEN 3,682.00 132.550.036000
1735 - WOODINVILLE RTA 6,070.13 218.520.036000
1736 - NEWCASTLE 6,850.96 246.630.036000
1738 - KENMORE 4,200.00 151.200.036000
1739 - SAMMAMISH RTA 3,673.26 132.240.036000
2711 - PUYALLUP 1,703.17 59.610.035000
2716 - SUMNER 1,825.00 52.930.029000
2717 - TACOMA 6,302.37 239.490.038000
2727 - PIERCE-PTBA RTA 660.00 23.100.035000
3100 - SNOHOMISH COUNTY RTA 165.00 4.460.027000
3101 - ARLINGTON 122,526.91 3,308.230.027000
3104 - EDMONDS 5,405.00 210.800.039000
3105 - EVERETT RTA 1,485.00 49.010.033000
3109 - LAKE STEVENS 8,550.41 213.760.025000
3110 - LYNNWOOD 7,504.01 300.160.040000
3111 - MARYSVILLE 247.50 6.930.028000
3119 - MILL CREEK 1,859.34 74.370.040000
3131 - SNOHOMISH-PTBA RTA 1,657.46 64.640.039000
4000 - KING COUNTY NON-RTA 44,951.96 988.940.022000
87,598.75Total Local City and/or County Sales Tax
Local City and/or County Use Tax/Deferred Sales Tax
Location Taxable Amount Tax Rate Tax Due
1725 - RENTON RTA 27,224.94 980.100.036000
This amount shows the Local City of Renton USE tax rate paid - includes the $27,224.94
in materials for the Talbot and Grady project. See last page for spreadsheet breakout
DocuSign Envelope ID: 8AA3C772-56FB-4B99-8DEE-44D7D86CA043
1726 - SEATTLE 915.96 0.037500 34.35
1729 - TUKWILA 3,165.98 113.980.036000
4024 - REDMOND NON-RTA 7,236.00 159.190.022000
1,287.62Total Local City and/or County Use Tax/Deferred Sales Tax
Total Tax 359,936.02
Subtotal 359,936.02
Total Amount Owed 359,936.02
Prepared By:Olivia Sorensen
E-Mail Address:osorensen@primeelectric.com
Submitted Date:4/4/2022
Confirmation #:0-025-785-470
Payment Type:ACH Debit/E-Check
Amount:$359,936.02
Effective Date:4/25/2022
DocuSign Envelope ID: 8AA3C772-56FB-4B99-8DEE-44D7D86CA043
This amount shows the total state and City of Renton USE tax rate paid that Prime will
need a change order amount to match.
DocuSign Envelope ID: 8AA3C772-56FB-4B99-8DEE-44D7D86CA043