HomeMy WebLinkAboutCO 29
CAG-20-126, CO #29-22
Approved by Cheryl Beyer via 5/3/2022 email 6/22/2022
ATTEST:
Jason A. Seth, City Clerk
Change Order No. 29
Contract Title: Lake Washington Loop Trail
Contract No. CAG -20-126
Page 2 of 5
THE CONTRACT IS MODIFIED AS FOLLOWS:
Description of Change:
x Revise the quantities of the following unit price items in the contract:
o Bid Item No. 10 Contractor Provided UPO
Estimated Added Quantity = 24 HR @ $195.00/HR = $4,680.00
o Bid Item No. 13 Sawcutting
Estimated Added Quantity = 70 LF @ $4.25/LF = $297.50
o Bid Item No. 17 Crushed Surfacing Top Course
Estimated Added Quantity = 5 TN @ $52.50/TN = $262.50
o Bid Item No. 18 Crushed Surfacing Base Course
Estimated Added Quantity = 5 TN @ $47.00/TN = $235.00
o Bid Item No. 19 HMA Cl 1/2" PG 64-22
Estimated Added Quantity = 5 TN @ $115.00/TN = $575.00
o Bid Item No. 56 Cement Conc. Traffic Curb & Gutter
Estimated Added Quantity = 50 LF @ $50/LF = $2,500.00
o Bid Item No. 61 Cement Conc. Sidewalk
Estimated Added Quantity = 6 SY @ $66/SY = $396.00
The location for the above items is the intersection of Airport Way/Shattuck Ave S
x Add the following lump sum item to the contract:
o Lump Sum Item No. 29-1 SHATTUCK REVISIONS
Quantity = 1 LS, Lump Sum Amount = $63,202.29
Location is the intersection of Airport Way and Shattuck Ave S
Change to Contract Plans:
As required in FWD No 17, FWD 20 and FWD No 23, the Contractor is directed to directed make the
following plans revisions at the intersection of Airport/Shattuck:
1.) Furnish and install 1 EA Type 8 J-Box (per the WSDOT Standard Plans with non-skid locking lid) at the
SW corner of Airport /Shattuck between new ramp and new landing to replace the existing J-box.
Furnish and install 1 EA Type 2 J-Box (per the WSDOT Standard Plans) at the NW corner of
Airport/Shattuck and 1 EA Type 2 J-box at the new power connection on Shattuck, south of Airport Way.
Install 2 EA-3-inch Sch. 80 PVC Conduits (see new Wire Note #17) in the same utility trench as 1 EA- 3-
inch Sch. 80 PVC per revised Wire Note #2. See the Plan Sheet TS9.01 Rev1.
2.) Reduce the utility trench construction limits on Shattuck from the existing pole on Tillicum/ Shattuck
to the revised power source connection which is the new Type 2 J-Box with non-skid locking lid noted
Change Order No. 29
Contract Title: Lake Washington Loop Trail
Contract No. CAG -20-126
Page 3 of 5
above. The Type 2 J-box shall be used to intercept the existing service conduit and conductors and
splice the existing power wires to the new 3-#2 wires (Wire Note #2). The Contractor shall coordinate
the work with PSE and the City. The Contractor shall provide temporary power to the signal at
Airport/Shattuck and street lights as needed for the PSE splice and connection. See Plans Sheets TS9.01
Rev 1, TS 9.02 Rev 1 and C3.11 Rev 2.
3.) The curb ramp and sidewalk on the SW corner of the intersection of Airport/Shattuck shall be
removed and waste-hauled/disposed. It shall be replaced with a new ADA-compliant WSDOT Type
Parallel A Curb Ramp and sidewalk transitions, per Plan Sheets C2.04 Rev 2 and C3.05 Rev 2 and C311
Rev 2. Contractor shall provide a Ped TCP for this work.
5.) Remove the existing plastic crosswalk lines on the Airport Way Crossing of Shattuck Ave S, on the
Shattuck Ave S crossing at Airport Way and at the Airport Way crossing at Logan Avenue N, by sand
blasting, per Special Provision 8-22.3(6). The Contractor is directed to replace the markings with
thermoplastic markings per COR Standard Plan 127 and Special Provision 8-22.2.
6.) Rewire the Shattuck and Airport Way Traffic Signal poles with new conductor and to terminate
conductors in the new controller cabinet. The Contractor is directed to furnish and install two each
terminal cans on Poles #3 and #4. The terminal cans shall be natural finished aluminum and shall meet
City of Renton Standard Plan 140. The work required for the service cabinet installation, rewiring and
PSE service transfer may be completed with multiple stops and starts as required to minimize working
days.
7.) Furnish and install two “No Pedestrian Crossing” signs R9-3 (18”x18”) and one “Use Crosswalk”
directional sign R9-3bP (18”x12”) on the easterly approach of the intersection, as shown on plans sheet
S7-04 Rev 3.
Reason for Change:
Contract Plans:
The original plans showed the point of connection for the signal and illumination improvements at the
northwest corner of the Shattuck/Tillicum intersection. Trenching at this location would trigger the
need for a utility pole relocation and curb ramp improvements. It was determined that a point of
connection was possible to the north of the original location. The T-cut trench restoration work across
Airport Way at Shattuck will require a substantial patch within the marked crosswalk on Airport Way.
This work triggers the need for a curb ramp retrofit at the SW corner of Airport Way and Shattuck Ave S.
This demolition work and reconstruction of the curb ramp at the SW corner of Airport/Shattuck is added
to the Contract.
Change Order No. 29
Contract Title: Lake Washington Loop Trail
Contract No. CAG -20-126
Page 4 of 5
The utility trench transverse patch crossings at the intersection of Airport Way/Shattuck and Airport
Way/Logan encroached on portions of the thermoplastic crosswalk pavement markings at these marked
crosswalks, so the crosswalk markings needed to be replaced as a result.
The plans called for the existing signal wire to extend and connect to the new signal cabinet at the
intersection of Shattuck/Airport Way. The entire signal is required to be rewired as a result. The
installation of two terminal cans on poles 3 and 4 simplifies the rewire work.
The addition of the no pedestrian crossing signs and use crosswalk directional sign clarifies that there is
no pedestrian crossing allowed on the east approach to the intersection.
Materials:
The terminal cans shall be natural finished aluminum and shall meet City of Renton Standard Plan 140.
Plans:
Plans Sheets C2.04 Rev 2, C3.05 Rev 2, C3.11 Rev 2, TS9.01 dated 9/7/21, TS9.02 dated 9/7/21 and
TS9.03, dated 9/7/21, S7.04 Rev 3, S7.05 Rev 3, WSDOT Standard Plan J-40.10-04, WSDOT Standard Plan
J-40.30-04, COR Standard Plan 127.
Equitable Adjustment:
This Change Order does include an equitable adjustment per Section 1-09.4 of the 2020
WSDOT/APWA Standard Specifications. See attached.
Extension of Time:
The Contractor agrees that the time for Completion is extended 0 Working Days for the
additional work. A time extension for this work has been addressed in Change Order No 11.
Sections 1-04.4 and 1-04.5 of the 2020 WSDOT/APWA Standard Specifications shall govern
this Change Order. The Work of the referenced Contract is modified to include the changes
detailed herein. The payment provided for herein shall constitute the complete and final
settlement for all costs of labor, equipment, materials, overhead, profit, permit fees, and all
other claims that may be made by the Contractor as a result of this change.
Change Order No. 29
Contract Title: Lake Washington Loop Trail
Contract No. CAG -20-126
Page 5 of 5
Attachments:
Forms to be attached to Change Order
܈ Plans
Bid Item No.Description
Quantity
Change Unit Unit Price Estimated Cost
10 Contractor Provided UPO 24 HR $195.00 $4,680.00
13 Sawcutting 70 LF $4.25 $297.50
17 Crushed Surfacing Top Course 5 TN $52.50 $262.50
18 Crushed Surfacing Base Course 5 TN $47.00 $235.00
19 HMA Cl 1/2" PG 64-22 5 TN $115.00 $575.00
56 Cement Conc. Traffic Curb & Gutter 50 LF $50.00 $2,500.00
61 Cement Conc. Sidewalk 6 SY $66.00 $396.00
$8,946.00
New Lump
Sum Item
No. Description Quantity Unit Unit Price Cost
CO29 -1a Cement Conc. Curb Ramp Type Parallel A 1 EA $10,115.79 $10,115.79
CO29 -1b Junction Box upgrade 1 EA Type 8 and 1 EA Type 2 1 LS $6,629.55 $6,629.55
CO29 -1c Junction Box Type 2 1 EA $2,409.25 $2,409.25
CO29 -1d Pavement and Concrete Removal 45 SY $132.18 $5,948.10
CO29 -1e Temporary Power 1 LS $0.00 $0.00
CO29 -1f Curb and Gutter Removal 50 LF $72.77 $3,638.50
CO29 -1g Credit for reduced trenching on Shattuck -67 LF $101.00 -$6,767.00
CO29 -1h Increased Traffic Control for lane shift 1 LS $7,374.57 $7,374.57
CO29 -1i Conduit and wire upgrades 1 LS $8,425.28 $8,425.28
CO29 -1j Rewire Signal and Furnish and Install Two Terminal Cans 1 LS $21,300.25 $21,300.25
CO29 -1k Vactor Excavation 1 LS $4,128.00 $4,128.00
$63,202.29
$72,148.29
By:
Date: 1/26/22
Equitable Adjustment Change Order No 26
Project Name: Lake Washington Loop Trail
Contractor: Active Construction Inc.
Federal Aid No: TAP-1070(008)
Contract No: CAG 20-126
Construction Manager: Tani Stafford, PE
Total Estimated Change Order Cost
Bid Item Change and Lump Sum Item
Lump Sum Item Cost - CO 29-1 Shattuck Revisions
Estimated Bid Item Cost
CITY OF RENTONBY: DATE:APPROVED FOR CONSTRUCTIONOF11241 Willows Road NE, Suite 200Redmond, WA 98052425.822.4446www.otak.com
CITY OF RENTONBY: DATE:APPROVED FOR CONSTRUCTIONOF11241 Willows Road NE, Suite 200Redmond, WA 98052425.822.4446www.otak.comVERTHORZ
CITY OF RENTONBY: DATE:APPROVED FOR CONSTRUCTIONOF11241 Willows Road NE, Suite 200Redmond, WA 98052425.822.4446www.otak.com
xxx CITY OF RENTONBY:DATE:APPROVED FOR CONSTRUCTIONOFTransportation Planning | Design | Traffic Impact & Operations11400 SE 8th Street, Suite 200, Bellevue, WA 98004 | Office (425) 889-6747Transportation Engineering NorthWestProject Contact: Elyse Stemmler, P.E.Phone: 425-250-5004TENWLEFT TURNYIELDYELLOWON FLASHINGSHATTUCKAve S3-12-222 Rev 7 - replace APS push buttons per orig. plans TLS 3/12/222Replace existing push buttons with APS push buttons per the original plan
CITY OF RENTONBY: DATE:APPROVED FOR CONSTRUCTIONOFTransportation Planning | Design | Traffic Impact & Operations11400 SE 8th Street, Suite 200, Bellevue, WA 98004 | Office (425) 889-6747Transportation Engineering NorthWestProject Contact: Elyse Stemmler, P.E.Phone: 425-250-5004TENWCABINETPED HEADSSIGNAL HEADSINTSERVICE501502 AC+AC-Ø2621622623626741742743744745761762763764765Ø4Ø64849696878178278378478572172272372472588892928625Ø4641642643646645Ø6661662663666665414261626816826836866858182Ø2Ø8931932935941942945951952955961962965DBACØ4Ø8Ø2Ø612312324V PWR24V RTNGROUND12312324V PWR24V RTNGROUND24V PWR24V RTNGROUND24V PWR24V RTNGROUND1234VIDEOVIDEOVIDEOVIDEOVIDEO SURGESUPPRESSORCAMERAPHASE 8CAMERAPHASE 6CAMERAPHASE 4CAMERAPHASE 2CONTROLLERLOOP DETECTIONØ8Ø5651652653656655Ø1611612613616615111251526A16A26A36A66A5OLA21226B16B26B36B66B5OLBOLB1OLB26C16C26C36C66C56D16D26D36D66D5OLCOLDOLC1OLC2SIGNAL HEADS
CITY OF RENTONBY: DATE:APPROVED FOR CONSTRUCTIONOFTransportation Planning | Design | Traffic Impact & Operations11400 SE 8th Street, Suite 200, Bellevue, WA 98004 | Office (425) 889-6747Transportation Engineering NorthWestProject Contact: Elyse Stemmler, P.E.Phone: 425-250-5004TENWMIN.2'-0"85°GFTYPE IITYPE IIITYPE IVTYPE VCOMBINATION LIGHTINGMAST ARMSTRAIN POLECOMBINATION LIGHTINGLOCATION STATIONO180°POLE ORIENTATION AND ATTACHMENT POINT DETAILSIGNAL ARMFROM OFFSET LINEDEGREES CLOCKWISEPOLE ORIENTATIONATTACHMENT POINTTO 0 POINTANGLE (P.O.A.)ROADWAY0°LineOffsetBASE PLATE270°TYPICAL E1CNDEGCIPYTIOPERESLATC90°FTATATORE0°MHMTNCLOKWEIS2VERTICAL CLEARANCELIMITS OF VERTICAL CLEARANCE REQUIREMENTFULFILL MUTCD REQUIREMENTSMINIMUM: 16'-6"B2aALL HANDHOLESAT 180B71B3babB421ROADWAYB6ad1" NIPPLEB5212B10aB92bB11c1fCDDFCURB OR EDGE OF SHOULDER6'-0"jiIiHhH12'-0"8'-0"ggGboraA1EEjA2CLI42" to 48"1B1aPAINT SPECIFICATIONS:ALL STEEL SIGNAL POLE PARTSSHALL BE GALVANIZED. ALLPOLE METAL COMPONENTSSHALL BE FACTORY PRIME ANDPOWDER COATED.FINISH COLOR: COLOR SHALLMATCH EXISTING OR BLACK(SEE SPECIAL PROVISIONS)e232413 1/2"-16" BASE DIAROUND SMOOTH STEELTAPERED POLE(0.14"/FT TAPER)(4) STANDARD SLOTS ACCEPTING:GALVANIZED ANCHOR BOLTS(4) 1 1/2"-2"Ø x 60" LONG1.5"-2" A36STEEL PLATE18-22"Ø BOLTCIRCLE3'-6"AND MAST ARMSIGNAL STANDARDSIGNAL STANDARDSTANDARD AND STRAINPOLE STANDARDSPECIAL DESIGN STANDARDTYPE SDTOP OF FOUNDATION SHALL MATCH TOP OF CURB, SHOULDER, OR SIDEWALK, WHICHEVER IS HIGHEST.
CITY OF RENTONBY: DATE:APPROVED FOR CONSTRUCTIONOF11241 Willows Road NE, Suite 200Redmond, WA 98052425.822.4446www.otak.comArrow points to theright22 FWD 20 - Remove and Replace Xwalk Markings TLS 7/21/21Remove andReplace ther-moplasticcrosswalkmarkings perCOR StandardPlan 17211FWD 19-TCP for Cycle Track Closure TLS 7/21/21Type 3 Barricade withRoad Closed sign