HomeMy WebLinkAbout5719.05 S 06082022Earth Solutions NWLLC 15365 NE 90th Street, Suite 100 Redmond, WA 98052 Main (425) 449-4704 | Fax (425) 449-4711 www.esnw.com FIELD REPORT Project No. 5719.05 Page 1 of 3 Report ID 5719.05 S 06082022 Date Wed 6/8/2022 Weather 50F Sun Arrival/Departure Time(s) 9:45 AM/ 10:15 AM Travel Time (hr) 1.0 Project Name Solera Location 2902 NE Sunset Blvd, Renton ESNW Rep., CESCL No., Phone No. & Report Statement Jackson Lundgren, CESCL Number: EF8183892 “This report is true, accurate, and complete to the best of my knowledge and belief.” Client Info/Contact Heartland Construction, LLC | Craig Vierling, Benham Hansen Permit No(s). WAR310291 Reviewed By MLP Initials/Date N/A Field Supervisor Project Manager Initials/Date Limitations: The presence of our field representative at the site is to provide our client with a source of professional advice, opinions, and recommendations based upon the field representative’s observations and testing of the contractor’s work. Our services do not include supervision or direction of the contractor, their employees, or agents. Recommendations for obtaining project objectives may be made by our representatives; however, direction of the actual work should come from the owner or contractor, as appropriate. The contractor is responsible for complying with the contract documents at all times, regardless of the presence of our field representative. Jobsite safety, including compliance with all applicable state or federal regulations, is the sole responsibility of the contractor. The observations, recommendations, and conclusions provided in this field report are preliminary until reviewed by the ESNW project manager. Type of visit:  Weekly  Monthly  Post–Storm Event Precipitation since last inspection (approximate): 0.94 inches Precipitation in last 24 hours (approximate): 0.00 inches Phase of active construction (check all that apply):  Pre-construction  Clearing, demolition, or grading  Infrastructure or roads  Concrete pours  Vertical construction  Utilities  Off-site improvements  Site temporarily stabilized  Final stabilization Was water quality sampling part of this inspection?  Yes  No If “Yes”: • Record results in the table below. • Hanna Turbidity Meter No. XXX Monitoring Point Monitoring Location Turbidity (NTU) pH Description of Discharge Notes Report ID 5719.05 S 06082022 Page 2 of 3 Earth Solutions NW, LLC Erosion Control BMPs (13 Elements) Overall Condition (Good; Fair; Poor) Needs Repair? (Yes; No) Comments 1. Preserve Vegetation; Mark Clearing Limits • Buffer Zones around Sensitive Areas • Silt Fence G N Silt fences are in good condition 2. Establish Construction Access • Fabric; Quarry Spalls • Wheel Wash • Sweeper Truck G N Construction entrance has crushed rock Site has preexisting asphalt 3. Control Flow Rates • Stormwater Vault or Facility • Straw Wattles • Check Dams G N Sand bags are in place on paved roadway on southern end of site 4. Install Sediment Controls • Silt Fence • Straw Bale Barriers • Vegetation • Straw • Sediment Ponds, Traps & Filters • Treatment • Water Truck G N Silt fences are in good condition 5. Stabilize Soils • Nets & Blankets • Mulch, Bark & Rock • Hydroseeding; Grass • Plastic Sheeting • Stockpiles F Y Cover soil stockpile in southwestern site corner with plastic sheeting 6. Protect Slopes • Benching; Track-Walking • Pipe Slope Drains • Plastic Sheeting; Anchors G N Plastic sheeting covers cut slopes and is anchored down with ropes with sandbags attached 7. Protect Drain Inlets • Catch Basin Inserts G N CB inserts along NE 12th St as well as on site sandbag and straw wattles around catch basins 8. Stabilize Channels and Outlets • Channel Lining • Check Dam • Outlet Protection • Nets and Blankets - - N/A 9. Control Pollutants • Chemical Storage Area Covered • Concrete Handling - - N/A 10. Control Dewatering - - N/A 11. Maintain BMPs F Y See recommendations 12. Maintain SWPPP & Site Logbook G N Available upon request 13. Protect Low-Impact Development (LID BMPs) • Bioretention Rain Garden Facilities • Permeable Pavement - - N/A Do existing BMPs need to be modified or removed, or do other BMPs need to be installed?  Yes  No List the action items in the table below: Element # Description and Location Action Required Completion Date 5 SW corner of site, native silty sand stockpile Cover in plastic sheeting Report ID 5719.05 S 06082022 Page 3 of 3 Earth Solutions NW, LLC BMP LEGEND JOB SHACK PLASTIC CONSTRUCTION ENTRANCE SANDBAG SILT FENCE HIGH VISBILITY FENCE STOCKPILE