HomeMy WebLinkAboutChange Order - 01CITY OF RENTON
Community Services Department
CONTRACT CHANGE ORDER AGREEMENT
CONTRACT:
CONTRACTOR:
CHANGE ORDER:
Renton Senior Activity Center Paving Repairs
CAG-22-104
Puget Paving and Construction
#1 (Corrected)
SUMMARY OF PROPOSED CHANGE:
Reason/Justification:
7/28/2JJZ2
Additional painting of extruded concrete curbing throughout the parking lot and painting of precast
wheel stops. Removal of "flaking" paint prior to painting concrete.
DESCRIPTION:
Item Qty. Descriotion Unit Price Amount
No. w/WSST
1 1 Painting of extruded curb, painting precast s 4,8S0.00 s 5,339.85
wheel stops, and removal of "flaking" paint.
600 LF Red Fire Land, 123 LF Yellow Curbing, and
14 Precast Concrete Wheel Stops.
Total this Change Order: $ 5,339.85
ORIGINAL CONTRACT CURRENT CONTRACT NET CHANGE REVISED CONTRACT
AMOUNT (W/ WSST) AMOUNT THIS ORDER (W/ WSST) TOTAL AFTER CHANGE
$ 24,332.10 $ 24,332.10 $ S,339.85 $ 29,671.95
Additional Calendar Days:
Zero (O) calendar days. No Extension of Time. Completion Date Is September 1, 2022.
The payment specified and agreed to in this change order includes every claim by the contractor for any
extra payment with respect to the work described in this change order. The work covered by this change
order must be performed under the same terms and conditions as that Included in the original
airreement. All of the other terms of the oriirinal arzreement remain in effect.
SIGNATURES: � 7/ 1.,."{ I 2.. ?_ Contractor: Date:
Project Manager: (. � < Date 7/28/22
Approved By: &flt.� Date: 7/iq /2,1:-:
CAG-22-104, CO #1a-22
MODIFIED
Item/Code ~ Qty Units Unit Price Total Price
1 LS 4,850.00$
STANDARD CLARIFICATIONS AND EXCLUSIONS
Change Orders
Overtime/Weekends/Nights
Proposal and Acceptance
Proposal Date:7/7/2022
Job Name:Renton Senior Center- additional striping
Job Site Address:211 Burnett Ave N, Renton, WA
Customer:City of Renton Estimator:Stefan Gehring
Contact Person:Betsy Severtsen Phone:253-606-5176
Phone:(425) 757-6657 Email:stefan@pugetpaving.com
Email:bsevertsen@rentonwa.gov Wage Rate:King County, WA
600 LF of red fire lane curbing
132 LF of yellow curbing
Customer Address:1055 S Grady Way
of "flaking" paint prior to painting included. Painting includes:
Renton, WA 98057
Description
Additional painting of concrete extruded curbing throughout the
parking lot and painting of pre-cast concrete wheel stops. Removal
Wage Rate Date:5/17/2022
Unless otherwise specified, all work to be performed during normal, daytime hours • Any request for night, weekend, or overtime work will be executed
only upon written orders, and will become an additional charge over and above this proposal • This charge shall not apply if Puget Paving elects to work
nights, weekends, or overtime at its own discretion, or if a proposal specifically includes night, weekend, or overtime work.
Permitting, Bonding, Engineering, Surveying, Traffic Control
Unless otherwise specified, proposal does not include any required permits, project-specific bonding, engineering, architectural services, staking or
surveying, traffic control or state sales or other taxes • Puget Paving is fully licensed and bonded to perform construction services in Washington State.
Pricing includes one mobilization unless noted above (additional mobilizations at + $2,450 each)
Any deviations, alterations, increases from above specified work requiring additional costs will be executed only upon written orders, and will become an
additional charge over and above this proposal.
14 concrete wheel stops w/ yellow
Exhibit A-1
Retention & Payments
Union Agreements
Puget Paving is not signatory to any labor union and will not sign a job-specific union agreement as a requirement for any subcontract it enters into
Please provide Contact Info & Billing Address (if different from above):
Bill to:Phone:
Address:Email:
Authorized Buyer Signature Date of Acceptance
ASPHALT GRINDING/MILLING/DEMOLITION & HAULOFF
Any contractual requirement to withhold retention payments over 5% of contract billings may require an additional charge over and above this estimate •
Unless otherwise specified contractually, payment terms are to be made as follows: net due upon completion, finance charge of 1.5% per month on all past
due balances • Credit card payments subject to 3% processing fee
Unless otherwise specified, proposal does not include any required permits, project-specific bonding, engineering, architectural services, staking or
surveying, traffic control or state sales or other taxes • Puget Paving is fully licensed and bonded to perform construction services in Washington State.
Collection/Liens/Bond Claims
This proposal shall serve notice of our intent to place liens on any private property improved upon should payment not be received in full upon completion
of contracted work • Bonded-project owners agree to furnish any bonding information upon request, and to cooperate fully with Puget Paving’s efforts to
collect payment via liens or bond claims if necessary • This proposal may be withdrawn by Puget Paving if not accepted within 30 days of submittal.
EQUIPMENT/TRUCK RENTAL
Puget Paving has a minimum truck, labor, or equipment rental period of 4 hours. Rental time in excess of 4 hours is charged in 15 minute segments and
rental time will be rounded to the nearest 15-minute increment. Rental rates are available upon request. Rental rates update yearly and are not required
to be furnished to customer prior to rental time being charged
INSURANCE
Puget Paving carries the following liability insurance coverage:
General Liability: $1,000,000 Occurrence / $2,000,000 Aggregate / Deductible: $250
• Blanket Additional Insured Products/Completed Operations: CG8583 04/13
• Primary and Non-Contributory and Waiver of Subrogation / General Liability Extension Endorsement: CG8810 04/13
• Per Projects General Aggregate: CG8870 12/08
Auto Liability: $1,000,000 Combined Single Limit
• Blanket Additional Insured, Waiver of Subrogation Auto Coverage Enhancement: CA8810 01/10
Umbrella: $5,000,000 Limit / $10,000 Self Insurance Retention / Occurrence Form
Pollution Liability: $2,000,000 Occurrence / $2,000,000 Aggregate / Deductible: $10,000
Any contractual requirement to carry more insurance than that listed above may require an additional charge over and above this proposal
Asphalt grinders have a minimum rental period of 4 hours • It is the responsibility of the project owner/prime contractor to notify Puget Paving a minimum
of 72 hours in advance of any asphalt milling work to occur greater than 6” depth; Washington State law requires that Puget Paving call in its own locating
ticket when grinding in excess of 6” depth and will not grind in excess of that depth without valid one-call locates • Unit- or lump-sum pricing for grinding
may change as the result of a field request to grind deeper than quoted pricing • Unit- or lump-sum pricing may change as the result of under-trucked
grinding operations when Puget Paving is not responsible for truck scheduling
CIVIL/UNDERGROUND UTILITIES
Unless otherwise specified, pricing does not include dewatering, export/disposal of unsuitable soils, import of structural fill, survey staking or engineering,
resolution of unknown underground utility conflicts, bonding, permitting, or testing
I have read and understand the above described clarifications and exclusions and agree to include them in any contract I enter into with Puget Paving and
Construction, Inc.
Subgrades, if not prepared by Puget Paving, shall be firm and unyielding and graded to drain at 1% slope minimum to qualify for any warranty • Design
grades at less than 1% slope do not qualify for drainage warranty • Grades prepared by others are subject to inspection by Puget Paving staff and, if found
defective, an additional release and waiver may be required prior to paving • Puget Paving cannot be responsible for subgrade failures that result from
any reason other than negligence on the part of Puget Paving • If Puget Paving paves or imports crushed rock on subgrade prepared by others and
exceeds the asphalt or crushed rock tonnage quantity specified by more than 105% of the planned quantity, and if that overage was the result of poorly
prepared or soft subgrade it may result in an additional charge • Puget Paving reserves the right to not proceed with paving on a scheduled paving day if
weather on that day and location (precipitation/temperature) violates current WSDOT specifications--specifically, WSDOT specs disallow any asphalt
paving at less than 42 deg F for 2” lifts and 35 deg F for 3” lifts and through any amount of standing water • Precipitation limitations apply depending on
severity • If a customer/prime contractor demands that paving proceed in violation of weather specifications, an additional release and waiver of
warranty may be required prior to commencement of any paving
FINE GRADING AND ASPHALT PAVING