HomeMy WebLinkAboutW_Waiver_Form_220504_v1.pdfFrom:Nathan Janders
To:Gina Brooks
Cc:Alex Morganroth; daikyulee@gmail.com
Subject:RE: Preapplication meeting
Date:Wednesday, May 4, 2022 12:13:02 PM
See below
As for the Geotech report I do not need one for the sake of stormwater review. Because the site is encumbered by a
landslide hazard the infiltrative BMP’s are not feasible and therefore the Geotech report is not needed.
NATHAN JANDERS, P.E., Civil Engineer III
City of Renton | CED | Planning Division
1055 S Grady Way | 6th Floor | Renton, WA 98057
Virtual Permit Center | Online Applications and Inspections
(425) 430-7382 | NJanders@rentonwa.gov
From: Alex Morganroth <AMorganroth@Rentonwa.gov>
Sent: Wednesday, May 4, 2022 10:41 AM
To: Gina Brooks <GRB@coredesigninc.com>; daikyulee@gmail.com
Cc: Nathan Janders <NJanders@Rentonwa.gov>
Subject: RE: Preapplication meeting
Hi Gina – thanks for your patience on this. Between a vacation and a conference back-to-back, it’s taking me a little bit to
catch up. Please see below for responses to your questions in red.
Nate – if you can confirm the submittal items related to your review, that would be great. I don’t see a geotech report
listed – is that something you need?
-Alex
ALEX MORGANROTH, AICP, Senior Planner
City of Renton | CED | Planning Division
1055 S Grady Way | 6th Floor | Renton, WA 98057
Virtual Permit Center | Online Applications and Inspections
(425) 430-7219 | amorganroth@rentonwa.gov
From: Gina Brooks
Sent: Friday, April 22, 2022 8:43 AM
To: 'Alex Morganroth' <AMorganroth@Rentonwa.gov>; daikyulee@gmail.com
Cc: Nathan Janders <NJanders@Rentonwa.gov>; Corey Thomas <cthomas@rentonrfa.org>
Subject: RE: Preapplication meeting
Alex,
I wanted to circle back on the required submittal items for this project. Upon our preapplication meeting and if my
memory serves me right, we discussed the option of a “limited” submittal package. Nathan had mentioned his concerns
about the storm drainage design and associated report. He had mentioned the City would want to review the storm report
and design and then determine next steps. My understanding is the “limited” submittal package would allow the
“development team” to produce sufficient documents and plans for the City’s review and determination if additional work,
documents, and plans would be required. A bit of a stair step process. My hope is to produce sufficient materials for City
review and avoid generating materials that would overwise be determined not applicable or needed.
With that in mind,
1. We are preparing plans which show the impervious coverage on the property and within the offsite easement and
provided a breakdown of those areas via zoning boundaries.
2. We are preparing a storm drainage report and drainage design for the project.
3. We will be providing an arborist report which will delineate those trees that have been removed. These removed
trees, if any, will be shown on the plans we are providing.
4. We are also, proposing to remove some of the impervious to keep the project within Simplified and Targeted
Drainage Review.
I am respectfully requesting our submittal package include the following submittal items (numbers correspond to submittal
items within the Grade and Fill Permit Submittal Requirements checklist attached.
1. Preapp meeting summary – Yes, please provide
2. Waiver Form (need to get this form from you once we determine the submittal items required) – This email chain
can be submitted as a PDF as proof of a waiver – not separate list required.
3. Land Use Permit App form – Yes, please provide
4. Fees (can you provide the fees due? Or will my client be invoiced upon receipt of package?) Will send invoice upon
receipt of submittal package, which can be paid online. The total fee for the Grade and Fill Permit is $5,410 + 5%
technology fee.
5. Project Narrative– Yes, please provide
8. Title Report– Yes, please provide
12. Tree Retention Worksheet – Yes, please provide
13. Arborist Report– Yes, please provide
18. Utilities Plan (We are preparing a Site Plan but, no utilities were previously installed or proposed) – Yes, please
provide
19. Drainage Control Plan (We are preparing a Site Plan but, no utilities were previously installed or proposed. This plan
shows the BMP mitigation.) Nate, please confirm. [NJ] confirmed, please provide.
20. Drainage Report – Yes, please provide
22. Fill Source Statement??? All I have is where the fill originated from which is 13504 SE 50th Place, Bellevue, WA
98006 A little more information is necessary – what type of fill was it? Who brought it in?
29. Grading Plan (The previous grading is shown on the Site Plan we will be preparing) Ok
We would prefer to prepare the landscape and tree replacement (if required) plan at a later time when the scope of the
landscape requirements are determined by City review. At this time, we only anticipate landscaping in the area of
proposed gravel removal. The remaining disturbed area has since been vegetated with grass. – We’ll need something at
least conceptual to review.
Please let me know your thoughts so, we can move this project along.
Thanks so much,
Gina R. Brooks, P.E.
Associate, Sr. Project Engineer
Core Design Inc.
O 425.885.7877
www.coredesigninc.com
From: Alex Morganroth <AMorganroth@Rentonwa.gov>
Sent: Thursday, January 27, 2022 9:57 AM
To: Gina Brooks <GRB@coredesigninc.com>; daikyulee@gmail.com; asiaais1004@yahoo.com
Cc: Nathan Janders <NJanders@Rentonwa.gov>; Corey Thomas <cthomas@rentonrfa.org>
Subject: Preapplication meeting
Good morning,
Please find attached the staff comments for the Lee Code Compliance preapplication meeting to be held virtually today at
10am. I’ve also attached the submittal requirements for the Grade and Fill Permit. If you have any trouble getting into the
meeting, please let me know as soon as possible.
Thank you,
ALEX MORGANROTH, AICP, Senior Planner
City of Renton | CED | Planning Division
1055 S Grady Way | 6th Floor | Renton, WA 98057
Virtual Permit Center | Online Applications and Inspections
(425) 430-7219 | amorganroth@rentonwa.gov