Loading...
HomeMy WebLinkAboutCO 167/26/2022               CAG-20-065, CO #16-22 Approved by Cheryl Beyer via 7/20/2022 email            Change Order No. 16 Contract Title: Duvall Ave NE Contract No. CAG 20-065 Page 3 of 3 Plans: Plan Sheet WA6-060122 Equitable Adjustment: This work is an unforeseen change and therefore the Change Order does include an equitable adjustment per Section 1-09.4 of the 2021 WSDOT/APWA Standard Specifications. See attached. Extension of Time: The Time for Completion is extended 0 Working Days. Sections 1-04.4 and 1-04.5 of the 2021 WSDOT/APWA Standard Specifications shall govern this Change Order. The Work of the referenced Contract is modified to include the changes detailed herein. The payment provided for herein shall constitute the complete and final settlement for all costs of labor, equipment, materials, overhead, profit, permit fees, and all other claims that may be made by the Contractor as a result of this change. To be attached to Change Order: ܈܈ Plans