HomeMy WebLinkAbout0895.06 E 09092022.pdfEarth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com
FIELD REPORT
Project No. 0895.06 Page 1 of 2 Report ID 0895.06 E 09092022
Date Fri 9/9/2022 Weather Clear sky 61°F
Arrival/Departure Time(s) 8:00 AM – 3:00 PM Travel Time (hr) 1.25
Project Name Weatherly Inn
Location 4500 Talbot Road S., Renton
ESNW Rep. & Phone Maricel Fee 425-984-9615
Client Info/Contact RJ Development | Jeff Bennett
General Contractor Info/Contact Johannsen | Brad
Permit No(s).
Reviewed By LAC
Initials/Date
SSR
Initials/Date Field Supervisor Project Manager
Limitations: The presence of our field representative at the site is to provide our client with a source of professional advice, opinions, and recommendations based upon the field representative’s observations and testing of the contractor’s work. Our services do not include supervision or direction of the contractor, their employees, or agents. Geotechnical recommendations for
obtaining project objectives may be made by our representatives; however, direction of the actual work should come from the owner or contractor, as appropriate. The contractor is responsible
for complying with the contract documents at all times, regardless of the presence of our field representative. Jobsite safety, including compliance with all applicable state or federal regulations,
is the sole responsibility of the contractor. The observations, recommendations, and conclusions provided in this field report are preliminary until reviewed by the ESNW project manager.
As requested by the client, ESNW rep was on-site to observe and make recommendations regarding
fence post excavations along the northern margin of the site. While on-site, the following was observed:
Northern Fence Post Hole Excavation Observations & Recommendations:
Upon arrival on-site, ESNW rep observed the grading contractor, Johansen Construction, continue
excavating fence post holes directly behind the previously constructed fill rockery along the northern
margin of the site. Per ESNW project manager, Scott Riegel’s, recommendations, the grading contractor
carefully excavate a total of 37 pilot holes for the proposed fence posts along the northern edge. Each
approximately 2-foot-wide by four-foot-deep excavation was observed to consist of previously installed
rockery elements, including 2-man stones, 2-inch-to-4-inch clean crushed rock, Miragrid 5-XT geogrid,
and structural backfill soil. ESNW rep observed the grading contractor carefully cut and remove localized
sections of rockery elements (geogrid), taking care to not disturb other elements through-out the
surrounding rockery section. Some sections will need to be re-excavated with larger machinery. These
spots were marked by the contractor. Drain pipes with filter fabric were observed at the first 2
excavation sites and the sites along the western edge of the parking lot.
Western Fence Post Hole Excavation Observations & Recommendations:
Upon excavating the first section along the western edge of the parking lot, the drain pipe for the
rockery was discovered to be 2 feet 8 inches from the surface and impeded the excavation process. This
pipe was broken open during excavation on September 2, 2022 but contractor relayed to ESNW rep that
they would be repairing it. ESNW project manager, Scott Riegel, recommended that the contactors cut
through the pipe as they continue excavating and cap the ends of the pipe. The recommendation was
relayed to the site superintendent who had an alternative suggestion, to shorten the shoring depth from
4 feet to approximately 2 feet and leave the drain pipe, or other utilities, intact. A total of 10 pilot holes
were excavated for the proposed fence posts along the western edge of the parking lot. Excavation will
continue on September 15, 2022. Please see attached map and images below.
Report ID 0895.06 E 09092022 Page 2 of 2
Earth Solutions NW, LLC
ESNW rep will return when requested.
Excavation sites
from 9/1
Excavation sites from
8/31 and 8/30
Excavation sites
from 9/2
= site where drain
pipe was damaged
Excavation site from 9/8 with
shoring depth of 32 inches North
Excavation sites from 9/9
with shoring depth of
approximately 32 inches
Top: Exposed
irrigation pipe
Bottom: Exposed
rockery drain
pipe