HomeMy WebLinkAboutAdden 6DOT Form 140-063
Revised 09/2005
Supplemental Agreement
Number
Organization and Address
Phone:
Original Agreement Number
Project Number Execution Date Completion Date
Project Title New Maximum Amount Payable
Description of Work
The Local Agency of
desires to supplement the agreement entered in to with
and executed on DQGLGHQWL¿HGDV$JUHHPHQW1R
$OOSURYLVLRQVLQWKHEDVLFDJUHHPHQWUHPDLQLQHႇHFWH[FHSWDVH[SUHVVO\PRGL¿HGE\WKLVVXSSOHPHQW
The changes to the agreement are described as follows:
I
Section 1, SCOPE OF WORK, is hereby changed to read:
II
6HFWLRQ,97,0()25%(*,11,1*$1'&203/(7,21LVDPHQGHGWRFKDQJHWKHQXPEHURIFDOHQGDUGD\V
for completion of the work to read:
III
6HFWLRQ93$<0(17VKDOOEHDPHQGHGDVIROORZV
DVVHWIRUWKLQWKHDWWDFKHG([KLELW$DQGE\WKLVUHIHUHQFHPDGHDSDUWRIWKLVVXSSOHPHQW
If you concur with this supplement and agree to the changes as stated above, please sign in the Appropriate
VSDFHVEHORZDQGUHWXUQWRWKLVRႈFHIRU¿QDODFWLRQ
By: By:
Consultant Signature Mayor Armondo Pavone Date
Jason A. Seth, City Clerk
City of Renton
Perteet, Inc.
June 30, 2020 HIPUL-STP 9917 (034)
This Supplemental Agreement No. 6 adds funds to the Construction Management contract to account for the extension of time due
to project changes and additional modifications to City of Renton's utilities such as water, sewer, and storm, and for the project
closeout Change Orders and negotiations with contractor.
No Change
Supplemental Agreement No. 6 increases contract maximum in the amount of $99,406.06 for a new Maximum Amount Payable of
$1,772,837.73. Supplemental Agreement No. 6 also incorporates updated rates and WSDOT accepted ICR FYE 2021.
6
Federal Aid No. HIPUL-STP 9917 (034)
Perteet, Inc.
2707 Colby Ave., Suite 900
Everett, WA 98201
(425) 252-7700
CAG-20-127 June 30, 2020 December 31, 2024
Williams Ave. W. & Wells Ave. S. Conversion Project $1,772,837.73
This Supplemental Agreement No. 6 adds funds to the Construction Management contract to account for the extension of time due
to project changes and additional modifications to City of Renton's utilities such as water, sewer, and storm, and for the project
closeout Change Orders and negotiations with contractor.
Perteet, Inc.City of Renton
CAG-20-127, Adden #6-22
Attest:
9/29/2022
%DVLF$JUHHPHQW6XSS 6XSS^ƵƉƉ͘ηϯ ^ƵƉƉ͘ηϰ ^ƵƉƉ͘ηϱ ^ƵƉƉ͘ηϲ7RWDO'LUHFW6DODU\&RVWΨϯϵϭ͕ϴϱϲ͘ϲϭΨ;ϭϯ͕ϴϴϱ͘ϭϵͿΨϴ͕ϲϭϳ͘ϵϴ ΨͲ ΨͲ ΨϮϲ͕Ϯϭϭ͘ϵϵ Ψϯϭ͕ϲϲϰ͘ϭϰΨϰϰϰ͕ϰϲϱ͘ϱϯ,&5,&5ΨϳϮϱ͕ϰϬϰ͘ϵϲ Ψ;Ϯϱ͕ϳϬϰ͘ϮϲͿ Ψϭϱ͕ϵϱϯ͘ϲϬ ΨͲ ΨͲ Ψϱϭ͕ϱϬϭ͘ϯϮ Ψϱϳ͕ϳϵϯ͘ϰϬΨϴϮϰ͕ϵϰϵ͘ϬϮ3URILWΨϭϭϳ͕ϱϱϲ͘ϵϴ Ψ;ϰ͕ϭϲϱ͘ϱϲͿ ΨϮ͕ϱϴϱ͘ϯϵ ΨͲ ΨͲ Ψϳ͕ϴϲϯ͘ϱϵ Ψϵ͕ϰϵϵ͘ϮϰΨϭϯϯ͕ϯϯϵ͘ϲϱ'LUHFW&RVWVΨϭ͕Ϯϯϰ͕ϴϭϴ͘ϱϲΨ;ϰϯ͕ϳϱϱ͘ϬϬͿ ΨϮϳ͕ϭϱϲ͘ϵϳ ΨͲ ΨͲ Ψϴϱ͕ϱϳϲ͘ϵϬ Ψϵϴ͕ϵϱϲ͘ϳϴΨϭ͕ϰϬϮ͕ϳϱϰ͘Ϯϭ([SHQVHVΨϮϬ͕ϯϱϮ͘ϴϬ ΨͲ Ψϭϰϳ͘ϮϬΨͲ ΨͲ ΨϮϵϵ͘ϱϮ Ψϰϰϵ͘ϮϴΨϮϭ͕Ϯϰϴ͘ϴϬ3RWHQWLDO6DODU\(VFDODWLRQΨϭϱ͕ϰϳϮ͘ϰϴ ΨͲ ΨͲ ΨͲ ΨͲ ΨͲ ΨͲΨϭϱ͕ϰϳϮ͘ϰϴ6XEFRQVXOWDQWVΨϭϲϵ͕Ϯϭϰ͘ϬϬ Ψϰϯ͕ϳϱϱ͘ϬϬ Ψϭϭ͕ϴϴϴ͘ϬϬ ΨͲ ΨͲ Ψϴ͕ϱϬϱ͘Ϯϰ ΨͲΨϮϯϯ͕ϯϲϮ͘Ϯϰ0DQDJHPHQW5HVHUYHΨϭϬϬ͕ϬϬϬ͘ϬϬ ΨͲ ΨͲ ΨͲ ΨͲ ΨͲ ΨͲΨϭϬϬ͕ϬϬϬ͘ϬϬ7RWDOΨϭ͕ϱϯϵ͕ϴϱϳ͘ϴϰ Ψ;Ϭ͘ϬϬͿ Ψϯϵ͕ϭϵϮ͘ϭϳ ΨͲ ΨͲ Ψϵϰ͕ϯϴϭ͘ϲϲ Ψϵϵ͕ϰϬϲ͘Ϭϲ Ψϭ͕ϳϳϮ͕ϴϯϳ͘ϳϯŝƚLJŽĨZĞŶƚŽŶtŝůůŝĂŵƐǀĞ͘^͘ΘtĞůůƐǀĞ͘^͘ŽŶǀĞƌƐŝŽŶWƌŽũĞĐƚŽŶƐƚƌƵĐƚŝŽŶDĂŶĂŐĞŵĞŶƚ^ĞƌǀŝĐĞƐdžŚŝďŝƚΗΗ^ƵŵŵĂƌLJŽĨWĂLJŵĞŶƚƐ^ƵƉƉůĞŵĞŶƚηϲ
ŽŶƐƚƌƵĐƚŝŽŶDĂŶĂŐĞƌŽŶƐƚƌƵĐƚŝŽŶ^ƵƉĞƌǀŝƐŽƌZĞƐŝĚĞŶƚŶŐŝŶĞĞƌ^ĞŶŝŽƌŽŶƐƚƌƵĐƚŝŽŶdĞĐŚŶŝĐŝĂŶŽŶƐƚƌƵĐƚŝŽŶdĞĐŚŶŝĐŝĂŶ/// ĐĐŽƵŶƚĂŶƚ^ͲĐƚƵĂůWĂLJƌĂƚĞ Ψϭϭϳ͘ϳϵ Ψϴϭ͘ϳϰ Ψϲϰ͘ϱϬ Ψϰϵ͘Ϯϱ Ψϰϭ͘ϯϰ Ψϱϭ͘ϬϬ/ZͲϭϴϮ͘ϱϮй ΨϮϭϰ͘ϵϵ Ψϭϰϵ͘ϭϵ Ψϭϭϳ͘ϳϯ Ψϴϵ͘ϴϵ Ψϳϱ͘ϰϱ Ψϵϯ͘Ϭϵ&ĞĞͲϯϬй Ψϯϱ͘ϯϰ ΨϮϰ͘ϱϮ Ψϭϵ͘ϯϱ Ψϭϰ͘ϳϴ ΨϭϮ͘ϰϬ Ψϭϱ͘ϯϬEĞŐŽƚŝĂƚĞĚ,ŽƵƌůLJZĂƚĞ Ψϯϲϴ͘ϭϮ ΨϮϱϱ͘ϰϱ ΨϮϬϭ͘ϱϴ Ψϭϱϯ͘ϵϮ ΨϭϮϵ͘ϮϬ Ψϭϱϵ͘ϯϵZĞŶƚŽŶtŝůůŝĂŵƐΘtĞůůƐD&ĞĞEĞŐŽƚŝĂƚĞĚ,ŽƵƌůLJZĂƚĞĂůĐƵůĂƚŝŽŶƐǁŝƚŚƚŚĞEĞǁϮϬϮϭ/ZĂŶĚϮϬϮϮZĂƚĞƐ
July 20, 2022
Perteet, Inc.
2707 Colby Avenue, Suite 900
Everett, WA 98201
Subject: Acceptance FYE 2021 ICR Risk Assessment Review
Dear Denice Moan:
Assessment review of your Indirect Cost Rate (ICR), we have accepted your proposed
FYE 2021 ICR of 182.52% of direct labor (rate includes 0.10% Facilities Capital Cost
of Money). This rate will be applicable for WSDOT Agreements and Local Agency
Contracts in Washington only. This rate may be subject to additional review if
considered necessary by WSDOT. Your ICR must be updated on an annual basis.
Costs billed to agreements/contracts will still be subject to audit of actual costs, based
on the terms and conditions of the respective agreement/contract.
This was not a cognizant review. Any other entity contracting with your firm is
responsible for determining the acceptability of the ICR.
If you have any questions, feel free to contact our office at (360) 705-7019 or via email
consultantrates@wsdot.wa.gov.
Regards;
ERIK K. JONSON
Contract Services Manager
EKJ:ah
City of RentonWilliams Ave. S & Wells Ave S. Conversion ProjectConstruction Management Services Supplement #6Construction ManagerConstruction SupervisorResident EngineerSr. Construction TechnicianConstruction Technician IIAccountantLaborLaborKutsalBrownHoweEdwardsFlodenSwansonHoursDollarsTask \ Negotiated Hourly Rate$368.12$255.45$201.58$153.92$129.20$159.38TotalTotalTask 1: Project Administration240400836$10,916.24General Project Management 16 - 4 - - - 20 $$6,696.24Billing and Progress Report 8 - - - - 8 16 $$4,220.00Task 2: Construction Administration48207536600239$51,190.38Project File/Records Keeping 8 - 8 8 16 - 440$7,856.16Submittals/Change Orders/Force Accounts 24 16 48 16 32 - 1136$29,195.04Progress Payments - - 3 4 4 - 111$1,737.22Weekly Meetings/Interviews/Payrolls/Records Keeping 16 4 16 8 8 - 552$12,401.96Task 3: Construction Observation006444072$14,033.60On-Site Construction Observation/IDR/FNR/FA - - 32 4 4 - 440$7,583.04Record Drawings Field Notes & Mark-Up - - 32 - - - 332$6,450.56Task 6: Project Close-Out2603224240106$22,816.56As-Built & Record Drawings 2 - 8 - - - 110$2,348.88Project Closeout Documentation 24 - 24 24 24 - 996$20,467.68Total Hours982017564888453Total Dollars$36,075.76$5,109.00$35,276.50$9,850.88$11,369.60$1,275.04$98,956.78 $98,956.78 Mileage ($0.585) $449.28 $449.28 Totals:$449.28 $99,406.06 Expenses:CONTRACT TOTALSUMMARYLaborExpenses