HomeMy WebLinkAboutAddendum - 2City of Renton
Gray & Osborne, Inc.
November 26, 2019 CAG-19-333
The Scope of Work described in the original agreement is amended to add the additional work and costs as set forth in Supplement
Agreement 2 Exhibit B attached and incorporated by reference.
No Change.
As set forth in Supplement Agreement 2, Exhibit A attached and incorporated by reference adding $36,196.25. Basic Agreement
$23,565.16 + Supplement Agreement 1 $54,790.29 + Supplement Agreement 2 $36,196.25 = $114,551.70.
2
CAG-19-333
Gray & Osborne, Inc.
1130 Rainier Avenue South, Suite 300
Seattle, WA 98144
(206) 284-0860
CAG-19-333 11/26/2019 December 31, 2023
2020 Street Patch and Overlay $114,551.70
In continuation of the City of Renton annual Street Overlay Program, this project will resurface and repair local streets, collector
streets, and alleyways at various locations in the City. The 2019-2020 Curb Ramps for Overlay project is under a separate
agreement.
Michael B. Johnson, P.E., President
CAG-19-333, Adden #2-22
Armondo Pavone, City of Renton Mayor
ATTEST:
Jason A. Seth, City Clerk
10-24-2022
Basic
Agreement Supplement No. 1 Supplement No. 2 Total
Direct Salary Cost $7,412.80 $16,981.55 $9,570.50 $33,964.85
Overhead
(Including Payroll Additives)$13,939.03 $31,932.11 $17,996.37 $63,867.51
Direct Non-Salary Costs $137.75 $1,121.80 $5,949.64 $7,209.19
Fixed Fee $2,075.58 $4,754.83 $2,679.74 $9,510.15
Total $23,565.16 $54,790.29 $36,196.25 $114,551.70
Summary of Payments
EXHIBIT A
Task Description hrs hrs $ hrs $ hrs $ hrs $ hrs $ hrs $ hrs $10 3.f Conformed Construction Docs0.5$32.630.5$22.254$127.00 $0.00 $0.00 $0.00 $0.00 $0.00 $181.885.011 3.g. ROM0.5$32.634$178.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $210.634.512 3.h. Non-Material Submittal List0.5$32.638$356.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $388.638.513 3.i. Bid Analysis0.5$32.63 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $32.630.514 3.k. Pre Award Meeting1$65.25 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $65.251.015 3.q. Materials (assumes 39 RAMs)18$1,174.5038.50$1,713.25 $0.0039$1,482.00 $0.00 $0.00 $0.00 $0.00 $4,369.7595.516 3.v. Preconstruction Meeting2$130.502$89.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $219.504.0173.cc. Weekly construction meeting(assumes 8 meetings)8$522.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $522.008.0183.ii Testing ***4$261.0012$534.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $795.0016.0193.jj. Permanent Monuments1$65.25 $0.00 $0.00 $0.004$219.002$90.008$328.008$284.00 $986.2523.0203.tt. RFI's (assumes 8)4$261.008$356.00 $0.008$304.00 $0.00 $0.00 $0.00 $0.00 $921.0020.021 3.bbb Change Orders (assumes 8)8$522.008$356.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $878.0016.048 $3,132.00 81 $3,604.50 4 $127.00 47 $1,786.00 4 $219.00 2 $90.00 8 $328.00 8 $284.00 $9,570.50 202.048 $3,132.00 81 $3,604.50 4 $127.00 47 $1,786.00 4 $219.00 2 $90.00 8 $328.00 8 $284.00 $9,570.50Direct Labor $9,570.50Fee0.28 $2,679.74Overhead 1.8804$17,996.37Expenses$64.64Subconsultants ***MTC$5,885.00Total Supplement No 2 $36,196.25Supplement NO 1 $54,790.29Original Contract $23,565.16TOTAL$114,551.70Exhibit A-1ContractHoursProject Name:Budget EstimateBernie HaydenContractTotalsHourly Totals$35.50$65.25$44.50 $31.75Zack LiebowitzProf Licensed Surveyor SurveyorHourly Subtotals$45.00Ron AlbrechtSurveyor$38.00 $41.00$54.75Rick BondPrincipal/PMFunction/TitleMichael BallardEmployee Tani StaffordBrian BollenEmployee Rate 2022 Overlay - Supplement No 2 - CMCivil Engr Technician Engineer in TrainingBrian SchulkinSurveyor
Page 1 of 3
EXHIBIT B
SCOPE OF WORK
City of Renton
2020 Street Patch and Overlay
Agreement No: CAG-19-333 (Supplemental Agreement No. 2)
SCOPE OF WORK:
Additional services include: Engineer of Record’s Role, material Testing Laboratory, overall Project
Management, coordination with the City, monthly report and invoicing. This Supplement No. 2 assumes
that there are 40 working days in the construction contract and time to complete/close-out the project.
10.0 – Preparation of Conformed Plans and Special Provisions
After bid opening, the CONSULTANT shall conform Special Provisions and/or Engineering Plans and deliver
to CITY for incorporation into the final construction contract documents. Addenda modifications to Special
Provisions shall be incorporated into final conformed Special Provisions. Addenda modifications to
individual sheets of the Engineering Plans shall be shown without clouds in the final conformed
Engineering Plans.
11.0 Prepare preliminary Record of Materials (ROM)
The CONSULTANT will prepare a preliminary Record of Materials (ROM) based on the construction
contract specifications. The primary purpose of the ROM is for tracking the approval and acceptance
requirements for materials permanently incorporated into the project. At a minimum, the ROM will
include the bid item number, quantity, unit of measurement, description, specification reference (note if
standard spec. (SS) or special provision (SP)) and conditions of engineer approval.
12.0 Master List of Submittals
The CONSULTANT will prepare a preliminary Master List of Submittals based on the construction contract
specifications. The primary purpose of the Master List of Submittals is for tracking the approval of
submittals (e.g. shop drawings, SWPPP, critical path schedule, etc.) the Contractor is required to provide.
At a minimum, the list will include the specification reference (note if standard spec. (SS) or special
provision (SP)), documents required for submission, and when the submittal is required.
13.0 – Bid Analysis
The CONSULTANT will support the City in the Bid Review phase in accordance with the construction
contract specifications.
14.0- Pre- Award Meeting
The CITY and Consultant will hold the official Pre-award Meeting for the project. Typically, the Contractor,
and Design Engineering Support Team attend this meeting. The primary purpose is to discuss award date,
preliminary schedule, and settle preliminary matters, Contract execution process and requirements,
submittals plus any other topic deemed important for construction. Prior to the COVID-19 pandemic, this
Page 2 of 3
meeting was typically held in person at Renton City Hall. Since COVID-19, these meetings have been
conduction on-line. For this project, it may be either or some combination thereof.
15.0- Materials
The construction contract has requirements for the Contractor to submit various documents for review.
These documents include but are not limited to the following:
9 Requests for Approval of Materials (RAM’s)
9 Shop Drawings
The Consultant will be tasked with providing an initial review of submittals with recommendations for
approval or rejection. The CITY may provide additional review comments.
16.0- Preconstruction Meeting
The CITY and consultant will hold the official Preconstruction Meeting for the project. Typically, the
Contractor, and Design Engineering Support Team attend this meeting. The primary purpose is to discuss
and settle preliminary matters, project schedule, weekly meeting schedule, invoice cutoff date, submittals
plus any other topic deemed important for construction. Prior to the COVID-19 pandemic, this meeting
was typically held in person at Renton City Hall. Since COVID-19, these meetings have been conduction
on-line. For this project, it may be either or some combination thereof.
17- Weekly Construction Meetings –
The CITY and Contractor will hold weekly meetings for the duration of construction. The Consultant is
anticipated to routinely attend these meetings. Estimate 8 weekly meetings.
18.0 –Testing
The Consultant will support the City with materials inspection, material testing and compaction testing to
measure compliance with Project Contract Provisions. Material testing services will be provided by MTC.
19.0- Permanent Monuments
The CONSULTANT will prepare a support the City in protecting permanent monuments found in the
construction zone. Currently none are shown on the plans.
20.0- Requests for Information (RFI’s)
x The Contractor will be instructed to submit all Requests for Information (RFI’s) to the CITY.
x The CITY will provide copies of all RFI’s to the CONSULTANT.
x The CITY will either provide suggested draft responses to the CONSULTANT for review or request
responses from the CONSULTANT. The CONSULTANT shall provide written responses to RFI’s to
the CITY, when requested by the CITY to do so.
x The CITY will provide the RFI response to the Contractor.
21.0 – Change Orders
x The Consultant will initiate and prepare draft change orders for review and comment by the CITY.
Once finalized, the CONSULTANT and CITY will sign the change order, prior to issuance to the
Contractor.
Page 3 of 3
x For change orders requiring revisions to plan sheets and/or specifications, the CONSULANT shall
prepare and deliver revised plan sheets and/or specifications to the CITY for incorporation into
the change order, when requested by the CITY to do so.
DELIVERABLES
The following deliverables shall be provided.
x Conformed Construction Documents – electronic copy only
x Draft and Final ROM
x Draft and Final Non Materials Submittal List
x Meeting minutes (Preaward, Preconstruction, and weekly)
x Materials Testing Reports (by MTC)
x Draft and final responses to RFIs
x Change orders