HomeMy WebLinkAboutChange Order - 2CITY OF RENTON
Community Services Department
CONTRACT CHANGE ORDER AGREEMENT
DATE 10/17/2022
CONTRACT:Alexander Moore Homes
CAG #22-293
CONTRACTOR:Alexander Moore Homes
CHANGE ORDER:2
SUMMARY OF PROPOSED CHANGE:
Reason/Justification:
DESCRIPTION:
Item Qty. Description Unit Price Amount
No.w/ WSST
2 1 Additional Repairs 15,954.50$ 17,565.90$
Total this Change Order: 17,565.90$
ORIGINAL CONTRACT CURRENT CONTRACT NET CHANGE REVISED CONTRACT
AMOUNT (W/ WSST) AMOUNT THIS ORDER (W/ WSST) TOTAL AFTER CHANGE
Additional Calendar Days:
(xx calendar days) (written #) calendar days - Extension of Time. Completion Date is (date).
SIGNATURES:
Contractor:Date:
Project Manager:Date 10/25/2022
Approved By:Date:
(position of appoval authority)
239,110.23$
Edward Grube
Rotted Wood and Damaged discovered when removing siding for replacement/repair.
Details of actual repair listed on Change Order from Alexander Moore Homes
The payment specified and agreed to in this change order includes every claim by the contractor for
any extra payment with respect to the work described in this change order. The work covered by this
change order must be performed under the same terms and conditions as that included in the original
agreement. All of the other terms of the original agreement remain in effect.
221,544.33$ 221,544.33$ 17,565.90$
10/24/22
CAG-22-293, CO #2-22