CONTRACT CHANGE ORDER NO. #06 (Non FAA-Eligible)
or
SUPPLEMENTAL AGREEMENT NO.
AIRPORT Renton Municipal Airport DATE 19-Feb-15
LOCATION Renton,WA AIP PROJECT NO. 3-53-0055-024
CONTRACTOR Gary Merlino CITY OF RENTON
Construction Co., Inc. PROJECT NO. CAG-14-088
You are requested to perform the following described work upon receipt of an approved copy of this
document or as directed by the engineer:
Item Unit
No. Description Unit Price Quantity Amount
01 Saw-Cut&Sea]asphalt to concrete joints LF 8.36 576 $4,564.56
Sub-Total $42564.56
Sales Tax (9.5%) $433.63
This Change Order Total $49998.19
Previous Change Order(s)Total $(99,523.63)
Revised Contract Total $1,061,421.70
The time provided for completion in the contract is (unchanged)(decreased)(increased)by R_working
days. This document shall become an amendment to the contract and all provisions of the contract will
apply. Changes are shown on Drawing(s)No. dated three copies attached.
Recommended by:
—4 AZ*,1+
Eli ineer
Date
Approved by: 4t 5
Own,6' Date
Accepted by:
Coni(racto-r Date
Concurred by:
State er ics, (if applicable) Datd
Approved by:
Ftfderal Aviation Administration Dke
Page 1 of 3
?"A A44,u 417(4,
NOTE: Change Orders and Supplemental Agreements require FAA approval prior to construction,
otherwise no Federal participation can be granted. State Aeronautics concurrence is required when
state participation is anticipated.
JUSTIFICATION FOR CHANGE
1. Brief description of the proposed contract change(s) and location(s).
CO#05,as a result of CO#02,omits the following Bid Items:
Bid Item#1.08 (Item#01);
Bid Item#1.09 (Item#02);
Bid Item#1.10(Item#03)
CO#05, as a result of omitted Bid Items#1.08,#1.09, and#1.10,directs the Contractor to install:
Temporary Perimeter Fencing(Item #04);
Perimeter Fencing(Item #05);
Perimeter Fencing fabric along the back side of the new Blast Wall (Item#06)
2. Reason(s)for the change(s) (Continue on reverse if necessary)
Item#01 - Bid Item#1.08 was intended to be an aesthetically pleasing Perimeter Fencing system that
would extend the imagery of the Blast Wall Art Work. The removal of Schedule III (see CO#02)
negates the purpose for installing Bid Item#1.08 as specified in Contract Specification 323114.
Items#02 and #03 - Bid Items#1.09 and#1.10 were included in the Project to maintain security during;
the interim between completion of new Blast Wall erection and prior to installation of Blast Wall Art
Work. Bid Items#1.09 and#1.10,per specification 323113,consisted of galvanized steel chain link
fencing. The galvanized steel chain link fence would damage the powder coated framing members of
the new Blast Wall, and are therefore being replaced by vinyl coated perimeter fencing fabric(see Item
#06,below).
Item#04 -Temporary Perimeter Fencing was needed to avoid Contractor delay's resulting from
Perimeter Fencing revisions.
Item#05 -The removal of Bid Item#1.08 resulted in the need of an alternate Perimeter Fence.
Installation of a new Perimeter Fence consisting partially of salvaged materials from the existing
Perimeter Fence, and partially of new materials as needed to complete the Perimeter Fence installation,
proved optimal.
Item#06 - With the removal of Schedule III (see CO#02)in combination with the removal of
Bid Items#1.09 and#1.10, the backside of the new Blast Wallis rendered unsecure. In order to
ensure Airport perimeter security, and to avoid damaging the new Blast Wall powder coated framing
members, installation of one(1), two(2) foot section,attached atop the'z-girts'along the Blast Wall
bottom, and one(1), seven(7) foot section, attached immedately above the'z-girt' section, is necessary.
3. Justifications for unit prices or total cost.
Unit prices for labor are per the current labor wage rates.
Unit prices for equipment are per the current year equpiment rental rates.
Page 2 of 3
4. The sponsor's share of this cost is available from:
90%
5. If this is a supplemental agreement involving more than$2,000, is the cost estimate based on the
latest wage rate decision? Yes ❑ No❑ Not Applicable Z.
6. Has consent of surety been obtained? Yes El Not Necessary Z.
7. Will this change affect the insurance coverage? Yes❑ No Z.
8. If yes, will the policies be extended? Yes❑ No Z.
9. Has this(Change Order)(Supplemental Agreement)been discussed with FAA officials?
Yes ❑ No Z When With Whom
Comment