HomeMy WebLinkAboutCO 2 CAG-13-088, CO #2-15 CONTRACT CHANGE ORDER NO. #02 (Non FAA-Eligible) or SUPPLEMENTAL AGREEMENT NO. AIRPORT Renton Municipal Airport DATE 12-Feb-15 LOCATION Renton,WA AIP PROJECT NO. 3-53-0055-024 CONTRACTOR Gary Merlino CITY OF RENTON Construction Co., Inc. PROJECT NO. CAG-14-088 You are requested to perform the following described work upon receipt of an approved copy of this document or as directed by the engineer: Item Unit No. Description Unit Price Quantity Amount 01 Removal of Schedule III(Blast Wall Art LS 90,000 1 (90,000) Work and Blast Wall Lighting)from the contract Sub-Total $ 90,000 Sales Tax 9.5% $ 8,550 This Change Order Total $ 98,550 Previous Change Orders Total $NA Revised Contract Total $1,154,015.20 The time provided for completion in the contract is (unchanged) (decreased) (increased)by 0 working days. This document shall become an amendment to the contract and all provisions of the contract will apply. Changes are shown on Drawing(s)No. dated , three copies attached. 7 r, n Recommended by: gin er/� ate Approved by: /�/ ,�✓ice s�• ! z,/z:1- i= _ Owner Date Accepted by: /_ /,-;, Co actor D te Concurred by: Zo 3 S ISO Aeron ics (if applicable) ate Approved by: Federal Aviation Administration Date Pagel of 2 NOTE: Change Orders and Supplemental Agreements require FAA approval prior to construction, otherwise no Federal participation can be granted. State Aeronautics concurrence is required when state participation is anticipated. JUSTIFICATION FOR CHANGE 1. Brief description of the proposed contract change(s) and location(s). CO#02 reduces the scope of work by removing Schedule III (Blast Wall Artwork and Blast Wall LIghting) from the contract. This reduction of scope would not change the duration of the project. 2. Reason(s) for the change(s) (Continue on reverse if necessary) An allowance of$90,000 was allocated for Schedule III. However, the cost estimated by the Contractor(Gary Merlino Constructions)was in excess of$200,000 making this part of the project unfeasible. 3. Justifications for unit prices or total cost. Since this change order is being issued before any costs were incurred by the contractor for this part of the project, Schedule III has been eliminated in its entirety from this project. 4. The sponsor's share of this cost is available from: NA 5. If this is a supplemental agreement involving more than $2,000, is the cost estimate based on the latest wage rate decision? Yes ❑ No ❑ Not Applicable H. 6. Has consent of surety been obtained? Yes ❑ Not Necessary Z. 7. Will this change affect the insurance coverage? Yes ❑ No Z. 8. If yes, will the policies be extended? Yes ❑ No Z. 9. Has this (Change Order) (Supplemental Agreement)been discussed with FAA officials? Yes ❑ No ® When With Whom Comment Though this is an AIP funded project, Schedule II & III of the project are being funded by the City of Renton. Hence removal of Schedule III was not discussed with the FAA. City of Renton reserves its rights to perform this work as an independent project at a later date. Submit 4 copies to the FAA Page 2 of 2