Supplemental Agreement OrganizationandAddress
Num ber 3 David Evans and Associates, Inc.
1115 West Bay Drive NW,Suite 301
Original Agreement Number olympia,WA 98502
CAG-14-112 Phone: (360)705-2185
Project Number Execution Date Completion Date
8/21/2014 12/31/2016
Project Title Engineering Support Services New Maximum Amount Payable
Bridge Inspection and Repair Program � 77,303.81
Description of Work
Provide Engineering Support Services for the City of Renton's Bridge Inspection and Repair Program.
The Local Agency of City of Renton
desires to supplement the agreement entered into with David Evans and Associates, Inc.
and executed on August 21,2014 and identified as Agreement No. CAG-14-112
All provisions in the basic agreement remain in effect except as expressly modified by this supplement.
The changes to the agreement are described as follows:
I
Section 1, SCOPE OF WORK, is hereby changed to read:
See attached Exhibit A-1.
I I
Section IV, TIME FOR BEGINNING AND COMPLETION, is amended to change the number of calendar days for
completion of the work to read: No change.
III
Section V, PAYMENT, shall be amended as follows:
See attached Exhibit E-1.
as set forth in the attached Exhibit A, and by this reference made a part of this supplement.
If you concur with this supplement and agree to the changes as stated above, please sign in the appropriate spaces
below and return to this office for final action.
David Evans and Associates,Inc. Gregg Zimmerman, Public Works Administrator
By: By:
� a�so«a-r� �'/�
Consultant Signature provi Auth rity Signature
��I'/�
DOT Form 140-063 EF D te
Revised 9/2005
Exhibit A
Summary of Payments
Permit Ratings, Monster Road and Oakesdale Ave. Bridges
Agreement No. CAG-14-112
Basic Agreement Supplement#1 Supplement#2 Supplement#3 Total
Direct Salary Cost 11,283.80 11,785.15 Date change only 2,207.00 25,275.95
Overhead
(Including Payroll Additives) 19,127.17 19,977.00 Date change only 4,016.00 43,120.17
Oirect Non-Salary Costs
(includes Subconsultant
charges) 1,051.00 274.00 Date change only 0.00 1,325.00
Fixed Fee 3,385.14 3,535.55 Date change only 662.00 7,582.69
Management Reserve Fund Date change only 0.00
Total 34,847.11 35,571.70 0.00 6,885.00 77,303.81
EXHIBIT A-1
SCOPE OF WORK
Supplement#3
AGENCY: CITY OF RENTON
CONSULTANT: David Evans and Associates, Inc.
CONTRACT: CAG-14-112
PROJECT: Engineering Support Services, Bridge Inspection and Repair Program
TASK 11—OVERWEIGHT LOAD EVALUATION FOR TWO RENTON BRIDGES
The City of Renton (Agency) is requesting professional services from David Evans and Associates, Inc.
(Consultant)as part of the Engineering Support Services, Bridge Inspection and Repair Program Project
(Project).This Scope of Work(Scope) includes development of overload permit ratings for the Monster
Road (RENTON-28)and Oakesdale Ave. SW(RENTON-25) Bridges.
A. DESIGN CRITERIA
The permit ratings performed for this Scope sha�l be in accordance with the criteria used in the original
Ioad ratings.
B. GENERAL ASSUMPTIONS:
The following scope and associated costs are based on the assumptions outlined below:
• No fatal flaws found in review of existing load rating reports
• Capacities,as well as moment, shear and stress demands can be readily extracted from the
existing Load Rating Reports
• Permit Live load models (girder and crossbeam)will be created using the parameters from
existing load rating report
• All parameters for creation of Permit Live load models(girder and crossbeam)can be readily
extracted from the existing Load Rating reports.
• Rating factors will be calculate using the capacities, and moment/shear/stress demands from
the existing load rating report combined with the moments, shears and stresses from the permit
live load model created by DEA.
• Bridges will be analyzed assuming only permit truck is on the bridge
• The deliverables are not full load rating reports, but a short memo summarizing the rating factors
for each bridge based on calculations provided in appendix.
C. DELIVERABLES:
All deliverables to be prepared and produced by the Consultant, as part of this scope of work,are
identified at the end of each task listed below.
Page 1 of 3
D. SCOPE OF WORK:
TASK 11.1—PROJECT MANAGEMENT
The following items are to be performed by the Consultant, under this task.
Assumptions for Task 11.1:
• The budget shown in Exhibit E-1 assumes this task is one (1) month in duration.
11.1.1 Overall Project Management
• Supervision of personnel and activities for compliance with contract scope and schedule and
proper charging of time against the contract.
11.1.2 Invoicing
• Preparation of one invoice that include the following:
o Spreadsheet summary of budget, expenses to date, expenses for invoice period for each
task.
o Summary of work accomplished for the invoice period.
o Summary of outstanding issues to be resolved by the Agency.
o Backup detail that includes the name, direct salary rate and hours charged,for each
individual charging time to this contract,for the work period.
o Backup detail of all direct non-salary costs included in the invoice for the work period.
DELIVERABLES
The following deliverables and delivery times are included in Task 11.1.
• Monthly progress report and invoice with backup documentation.
TASK 11.2—Monster Road Bridge Permit Rating
The following items are to be performed by the Consultant, under this task:
• Review of existing load rating calculations
• Create a girder model for permit truck
• Create crossbeam model for permit truck
• Develop rating factors for permit truck
• Prepare Summary Memo
• Perform a Quality Assurance/Quality Control review of the summary memo.
Page 2 of 3
DELIVERABLES
The following deliverables and delivery times are included in Task 11.2.
• Summary memorandum including supporting calculations and assumptions to be delivered to
the client by 5:00 PM, February 29th, 2016.
TASK 11.3—Oakesdale Ave SW Bridge Permit Rating
The following items are to be performed by the Consultant, under this task:
• Review of existing load rating calculations
• Create a girder model for permit truck
• Create crossbeam model for permit truck
• Develop rating factors for permit truck
• Prepare Summary Memo
� Perform a Quality Assurance/Quality Control review of the summary memo.
DELIVERABLES
The following deliverables and delivery times are included in Task 11.3.
• Summary memorandum including supporting calculations and assumptions,to be delivered to
the dient by 5:00 PM, February 29th, 2016.
Page 3 of 3
Exhibit E-1
City of Renton
Permit Ratings, Monster Road and Oakesdale Ave. Bridges
CAG-14-112, Supplement 3
David Evans and Associates, Inc.
Direct
Classification Hrs. x Rate = Cost
1 Project Manager(PMGR) Rich Hovde 6 $ 61.00 $366
3 Sr. Bridge Engineer(SBEN) Eric Ferluga 15 $ 48.66 $730
4 Sr. Bridge Engineer(SBEN) Robert Fulton 15 $ 52.80 $792
5 Design Engineer(DEEN) Anne Petrich 0 $ 29.00 $0
17 Administrative Assistant(ADMA) Brenda Alongi 2 $ 20.00 $40
18 Project Administrator(PADM) Jodi Wills 9 $ 31.00 $279
Total Hrs. 47
Salary Cost $ 2,207
Salary Escalation Cost(estimated)
Escalation -%of Labor Cost 0% per year @ 0 year(s) $0
Total Salary Cost $ 2,207
Overhead Cost @ 181.98% of Direct Labor $ 4,016
Net Fee @ 30.0% of Direct Labor $ 662
Total Overhead&Net Fee Cost $ 4,678
Direct Expenses No. Unit Each Cost
Reproduction Costs
Copies 0 pages @ $0.06 /page $ -
Reports 0 reports @ $15 /report $ -
Plans 0 sets @ $2 /set $ -
Parking 0 @ $8 $ -
Mail/Deliveries/Fed Ex 0 @ $20 $ -
Mileage 0 miles @ $0.540 /mile $ -
Subtotal $ -
David Evans and Associates Total $ 6,885
Exhibit E-1
City of Renton
Permit Ratings, Monster Road and Oakesdale Ave. Bridges
CAG-14-112, Supplement 3
David Evans and Associates, Inc. � 3 4 5 17 �s
z z
� �
c7 c00nv � w �
5 L
^ L L � � O
LL � � �
� � � �
N = � N Q y
� m � � j '�
c W W �
'rn :� E
m � � � m -6
� rn � w Q �
� � �
� c Q �
a� ` ` � •� � a�i 0
Work •o m m 'u� E p 'o Q
Element# Work Element a` c`n c`n o Q Q a` � DEA % of
direct rates: $s�.00 $as.ss $52.so $2s.00 $20.00 $31.00
Total Total Total Total Total Total Total Total
hrs hrs hrs hrs hrs hrs $ Hours
TASK 11 OVERWEIGHT LOAD EVALUATION ON TWO RENTON BRIDGES
11.1 Project Management 8�Quality Control
11.1.1 Project Management 2 1 $477 6.38%
11.1.2 Monthly Progress Reports and Invoices 2 $193 4.26%
Work Element 11.1 Total 2 3 $671 10.64°l0
11.2 Monster Road Bridge Permit Rating
Review Existing Load Rating Calculations 2 $304 4.26%
Create Girder Model for Permit Truck 2 $304 4.26%
Create Crossbeam Model for Permit Truck 2 $304 4.26%
Develop Rating Factors for Permit Truck 2 $304 4.26%
Prepare Summary Memo 1 2 1 2 $750 12.77%
Quality Assurance/Quality Control Review 1 2 3 1 $1,085 14.89%
Work Element 11.2 Total 2 12 3 1 3 $3,049 �•68°�0
David Evans and Associates, Inc. � 3 4 5 17 �8
z z
� �
w
C� c°°n� � w �
L
a � � Q tn O
� N t�/� �
� C C � Q �
m m m N ; '�
c W W c -
co � � � i� �
� rn rn w Q �
() 'a "� � '� Q (� �
Work 'o °� °� 'v, E p 'o Q
Element# Work Element a` c`n c`n o Q Q a` a DEA % of
direct rates: $s�.00 $as.ss $52.so $2s.00 $20.00 $31.00
Total Total Total Total Total Total Total Total
hrs hrs hrs hrs hrs hrs $ Hours
11.3 Oakesdale Ave SW Bridge Permit Rating
Review Existing Load Rating Calculations 2 $329 4.26%
Create Girder Model for Permit Truck 2 $329 4.26%
Create Crossbeam Model for Permit Truck 2 $329 4.26%
Develop Rating Factors for Permit Truck 2 $32g 4.26°/a
Prepare Summary Memo 1 2 1 2 $776 12�77%
Quality Assurance/Quality Control Review 1 3 2 1 $1,072 14.89%
Work Element 11.3 Total 2 3 12 1 3 $3,165 44.6$%
EXPENSES
SALARY ESCALATION
PROIECT WORK ELfMENTS TOTALS 6 15 15 2 9 $6,885 100.00%