HomeMy WebLinkAboutAdden 05 CAG-14-146, Adden #5-16
�+ Washington State
Department of Transportation
Supplemental Agreement Organization andAddress
Number 5 KPG, �►,�.
753 9`h Avenue North
Original Agreement Number Seattle,WA 98109
CAG-14-146 Phone: (253)627-0720
Project Number Execution Date Completion Date
11/5/2014 12/31/2017
Project Title New Maximum Amount Payabfe
Downtown Circulation Project— Phase 1 $ 504,935.81
Description of Work
Provide design services for new water, sewer, storm, fiber/telemetry utilities and
coordinate design elements with The Lofts developer.
The Local Agency of_City of Renton
Desires to supplement the agreement entered in to with KPG, Inc.
and executed on 11/5/2014 and identified as Agreement No. CAG-14-146 '
All provisions in the basic agreement remain in effect except as expressly modified by this supplement.
The changes to the agreement are described as follows:
I
The PURPOSE of this Supplemental Agreement is as follows:
The additional services are described in the attached and incorporated Exhibit A.
I I
The TIME FOR EXECUTION AND COMPLETION of this project is amended as follows:
There is no change in the project completion date.
III
PAYMENT shall be amended as follows:
The original maximum amount payable was$148,818.69.Additional services increased the maximum amount payable in
Supplement 2 by$155,534,16, Supplement 3 by$40,427.78,and Supplement 4 by$71,792.04.This Supplemental Agreement
5 increases the maximum amount payable by$88,363.14, making the new maximum amount payable$504,935.81.The basis
for the increase in the maximum amount payable is detailed within the attached and incorporated Exhibit E-1.
as set forth in the attached Exhibit(s), and by this reference made a part of this supplement.
If you concur with this supplement and agree to the changes as stated above, please sign in the appropriate
spaces below and return to this office for final action.
By: Jason Fri Inc. By: enis Law Ma r ���``����`��,R�l�N�T��������''i�,
�,``, '�
; � %
Cons nt Signature Ap roving Authorit�ign tur�� �
� `�/ :=�c '� b31.
: • :
Dat % �.?`�,pFt���'���\\
Attest: � ,;,,,, \\;�''
°'/'r n i, , ��;����.:
DOT Form 140-063 J son , City Clerk
Revised 09/2005
EXHIBIT A
CITY OF RENTON
DOWNTOWN CIRCULATION PROJECT- PHASE I
(MAIN AVENUE S AND BRONSON WAY S)
WATER, SEWER, STORM, FIBER/TELEMETRY DESIGN AND DEVELOPER DESIGN
COORDINATION
SUPPLEMENT 5
SCOPE OF WORK
MAY, 2016
A. PROJECT DESCRIPTION�BACKGROUND
The City of Renton ("City") has a desire to enter into a supplemental design agreement
with KPG ("Consultant") to integrate new water, sewer, storm, fiber/telemetry utilities
and an art component into the project. Additionally, the City has decided to allow The
Lofts developer to construct the SW corner of the Main Ave S/S 2"d St intersection ahead
of the Downtown Circulation Project. This will require revisions to the 90%
signal/illumination system plans such that the developer can construct the appropriate
number, type, size, and location of conduits,j-boxes, and vaults.
Revisions to the environmental permitting documentation will be required to encapsulate
the new utility improvements.
Utility improvements are anticipated to include the following:
❑ Sanitary Sewer
o Replace 10 LF of broken sewer on S 2"d St. vicinity Sta. 53+25.
o Replace two (2) sewer 'tees' on S 2"d St.just to the west of Mill Ave S.
❑ Water
o Install 620 LF of new 12" DI water main on S 2"d St. from Wells Ave S to Mill
Ave S and connect to existing 12" water main on Main Ave S.
o Install a new hydrant on the NE corner of the S 2nd St/ Mill Ave S intersection.
❑ Storm
o Revise 90% storm design to include a new 12" storm line from CB #9 westerly
across Bronson Way S to a new Type 2 CB and continue north on Main Ave S
to a new Type 1 CB.
City of Renton
Downtown Circulation Project—Phase I
Supplement 5 KPG
Project Number: 14080 1 May,2016
o Install 160 LF of new 12" storm line from Welis Ave S to the Main Ave S alley
tying into to an existing system.
❑ Fiber/Telemetry
o Install two (2) new splice vaults at the intersection of Main Ave S/S 3�d St.
o Install one (1) new splice vault at the intersection of Main Ave S/S 2�d St.
o Remove fiber/telemetry run from Mill Ave S to Main Ave S on S 2nd St.
o Pull new fiber/telemetry on Main Ave S, Houser Way S, and Mill Ave S and
terminate in existing splice tower located at the S 2"d St / Mill Ave S
intersection.
B. ASSUMPTIONS
The following assumptions were identified to provide direction with design:
❑ The Project will require revisions SEPA Checklist (MDNS Anticipated) and Cultural
Resource Report. This effort will continue to be tracked on the preliminary design
phase (Work Element 3) of the original contract. The City will be responsible for all
project postings/advertisements and for issuing the final SEPA Determination.
❑ The final design is funded by City funds and the construction is funded by TIB and City
funds.
❑ The Consultant shall assist the City in coordinating with the City's selected artist, the
integration the art theme within the plaza space, and provide electrical
conduit/routing design (if required). Additional geotechnical and structural design (if
required) will be conducted by the City and reports/calculations will be provided to
the Consultant. The Consultant will draft the foundation details and connections in
CAD.
❑ No additional right of way and/or easements will be required.
❑ Temporary Construction Permits, if required, will be acquired by the City.
❑ Supplemental survey, basemapping, and potholing will be required and conducted by
the Consultant.
❑ Stormwater control facilities (for either detention or water quality) will not be
required. The drainage report will be revised to reflect the new storm improvements.
❑ In areas where trenching for utilities are required outside of the intersection
improvements,the Consultant shall follow the City's roadway restoration policies and
standard details. Full roadway width pavement restoration/reconstruction will not be
required where water and storm improvements extend beyond the original roadway
excavation limits.
❑ The new water, sewer, storm, and fiber/telemetry utility design will be integrated into
the 90% plan set. It is anticipated that one (1) bid package will be prepared to include
the Downtown Circulation improvements and the additional utility work.
❑ Plans will be prepared in accordance with the WSDOT Local Agency Guidelines (LAG)
and other WSDOT manuals consistent with the inherent requirements of the City's
Certification Acceptance (CA) status.
City of Renton
Downtown Circulation Project—Phase I
Supplement 5 KPG
Project Number: 14080 2 May,2016
❑ This project will be advertised through BXWA. The consultant shall provide the City
with the Final Bid Documents in PDF format to send to BXWA for advertisement. All
coordination with BXWA during bidding will be conducted by the City.
C. KPG DEuvERaB�Es
Deliverables prepared by the Consultant are identified at the end of each task.
D. CITY OF RENTON PROVIDED ITEMS:
The City of Renton will provide/prepare the following:
❑ Submittal reviews, comments, and approvals (1 to 2 sets of comments per submittal)
❑ Public notices and property owner mailing and postage
❑ Meeting room arrangements
❑ Stormwater and sewer system video and information on existing pipe conditions and
GIS data
❑ Right-of-entries for surveying, geotechnical review, and/or construction, if required
❑ Standards developed through the Streetscape Design Guideline Effort
❑ Geotechnical data and structural design for the selected art piece (if required)
E. SCOPE OF WORK
WORK ELEMENT 1—MANAGEMENT�COORDINATION�ADMINISTRATION
The Estimated project duration is 2 additional months.
1.1 The Consultant will provide continuous project management for the project
duration of the project through final design (estimate 2 months).
1.2 The Consultant will prepare monthly progress reports identifying work completed
in the previous month, work in progress, upcoming work elements, and reporting
of any delays, problems, or additional information needs. These reports will be
submitted with the Consultant invoices.
1.3 The Consultant will conduct regular project team meetings (estimate 4 meetings
total) with internal staff.
1.4 The Consultant will provide internal quality assurance/quality control (QA/QC)
reviews of all major deliverables prior to submittal to the City.
Work Element 1 Deliverables:
■ Monthly progress reports (2 months)
City of Renton
Downtown Circulation Project—Phase I
Supplement 5 KPG
Project Number: 14080 3 May,2016
■ Project Schedule Updates
WORK ELEMENT 2—SURVEY AND BASE MAPPING
2.1 Establish additional horizontal and vertical control points as necessary within the
mapping limits. The same survey control specifications will be utilized as
developed in the preliminary design phase.
2.2 Additional field survey within the following project limits:
• Field survey of planimetric features and utilities. Topographic mapping of the
existing ground will be taken at approximately at 25-ft intervals (to 2-ft. contour
intervals) within the following areas:
o Intersection of Main Ave & S 2nd St (Bronson)
■ Extend existing underground utilities (CNI to locate lines prior to
mapping)
■ Check that all existing underground utility lines extend to
structures and/or lines
■ Measure 3 manholes -Traffic control required
o S 2nd St from Wells Avenue S to approximately 160 feet east of the
intersection
■ Extend existing survey to match current base map. CNI to locate
lines prior to mapping.
o North side Houser Way S and west side Mill Ave from Main Ave S to S 2nd
St
■ Extend existing survey to include all features between lip of gutter
to back of sidewalk to do a complete base map, including a surface.
CNI to locate lines prior to mapping.
• Locate paint marks in task 2.3 at 50-ft intervals, including surface features (valves,
manholes, catch basins,junction boxes, vaults, etc.). Irrigation systems will not be
included. Perform observation and measure-downs of existing storm drain catch
basins and manholes and sewer. The approximate size,type (brick, concrete), and
general condition of the structures to confirm suitability for continued use, and
approximate size and location of pipes will be documented. These observations
will be made from the surface.
2.3 The Consultant shall coordinate utility locates, identification, survey, and other
work, as necessary, to locate all other franchise underground and overhead
utilities within two intersections in order to identify any potential conflicts with
the proposed improvements. When making requests for utility locates, the
City of Renton
Downtown Circulation Project—Phase I
Supplement 5 KPG
Project Number: 14080 4 May,2016
Consultant shall inform the Utility Notification Center that the requested locates
are for design purposes for the City of Renton.
2.4 CADD mapping work to prepare 1"=20' topographic base map and digital terrain
model (DTM) in AutoCAD format of the project within the limits described above.
Right-of-way and parcel lines within the intersection areas will be determined
from available survey records (surveys, right-of-way plans, etc.). Other areas will
utilize available GIS linework and will only be approximate.
2.5 Potholing to identify potential utility conflicts will be completed as necessary for
final design (8 estimated). The locations of the potholes will be surveyed and
added to the base map.
Work Element 2 Deliverables:
■ Electronic copies of the updated base map will be delivered to the City.
WORK ELEMENT 3—STORMWATER DOCUMENTATION
The following supplemental stormwater documentation tasks are needed to perform
additional stormwater analysis, documentation, and design to support proposed
additional utility improvements. Work Element includes the effort required to analyze
and document the stormwater analysis and design of the project in accordance with the
February 2010 City of Renton Amendments to the King County Surface Water Design
Manual.
3.1 Review the existing stormwater facilities within the project area and revise the
analysis of Core and Special Requirements applicability to include the additional
project area.
3.2 Revise the Technical Information Report for the project to include the expanded
project area. The report will include documentation of the applicability of
requirement and facility sizing calculations.
Additional Work Element 3 Deliverables:
■ Revised Draft Technical Information Report, One (1) unbound Copy, four (4) bound
copies of the report.
Work Element 3 Assumptions:
■ The project is exempt from flow control and water quality.
City of Renton
Downtown Circulation Project—Phase I
Supplement 5 KPG
Project Number: 14080 5 May,2016
WORK ELEMENT 4—ARTIST COORDINATION
This work element covers the coordination effort required to integrate the artistic
elements into the plaza area.
4.1 The Consultant will work with the artist to refine the artistic design elements,
provide guidance on art placement, and assist in the development of design
details. It is anticipate that the Consultant will prepare for and attend six (6)
meetings artist and City staff.
Work Element 4 Deliverables:
■ Meeting Notes
Work Element 4 Assumptions:
■ The City shall select an artist and art element to be integrated into the project.
WORK ELEMENT 5—COMMUNICATION SYSTEM PRELIMINARY DESIGN
This Work Element includes the effort required to develop the design modifications to the
existing City owned traffic signal telemetry, City owned fiber optic and Comcast owned
iNet fiber optic cable systems. The existing cables in the conduits between Mill Ave S and
Main Ave S on S 2�d St are seized, therefore a new layout will be required to minimize
downtime of the City's communications systems.
5.1 Coordination meetings with City of Renton traffic signal maintenance,
transportation engineering and IT department staff regarding existing conditions
including cable and equipment layouts(assume three (3) meetings and one (1)site
visit). The Consultant will prepare meeting notes documenting decisions made
during the meetings and direction given from City staff.
5.2 Prepare draft and final schematic telemetry/fiber optic cable layouts for
discussion during coordination meetings. Final layouts will be utilized in
development of the Plans (see Work Element 6)
Work Element 5 Deliverables:
■ Meeting notes
■ Draft Schematic Telemetry/Fiber Optic Cable Layout
■ Final Schematic Telemetry/Fiber Optic Cable Layout
Work Element 5 Assumptions:
■ Geographic limits of the cable modifications will be bordered by: Williams Ave S on rhe
west, S 2"d St on the north, Mill Ave S on the east, and Houser Way S on the south.
City of Renton
Downtown Circulation Project—Phase I
Supplement 5 KPG
Project Number: 14080 6 May,2016
WORK ELEMENT 6—FINAL DESIGN OF NEW UTILITIES AND ART INTEGRATION
This Work Element includes the effort required to revise the 90%Plans,Specifications and
Estimates (PS&E) to include the new water, sewer, storm, fiber/telemetry utility design,
revise the signal/illumination plans for the developer, and integrate artistic design
elements into the plaza space. Once the 90% (PS&E) has been reviewed by the City, the
Consultant shall prepare Final Bid Documents.
6.1 The consultant shall revise the 90% plans for review and approval by the City. The
90% submittal will include all comments received from the 60% review and the
following sheets revised and/or added to the plan set:
❑ 1 Cover Sheet (revised)
❑ 1 Sheet Index, Alignment Plan, and Survey Control (revised)
❑ 1 Legend and Abbreviations (revised)
❑ 2 Roadway Details (revised)
❑ 2 Site Preparation Plans and TESC Plans (revised)
❑ 2 Site Preparation Plans and TESC Plans (new)
❑ 2 Roadway Plan (revised)
❑ 2 Roadway Plan (new)
❑ 1 Drainage Profiles (revised)
❑ 1 Drainage Profiles (new)
❑ 2 Water/Sewer Plans/Profile (new)
❑ 1 Water Details (new)
❑ 1 Sewer Details (new)
❑ 1 Urban Design Plans (revised)
❑ 1 Urban Design Details (revised)
0 3 Signalization and Wiring Plans (new)
❑ 1 Signalization and Wiring Plans (revised)
❑ 1 Si�nal Details (new)
Total: 12 New Sheets, 13 Revised Sheets
6.2 The Consultant shall separate the design elements of the SW corner of S 2"d St /
Main Ave S from the existing Main Avenue 90% plans and provide the developer
with a supplemental plan set / CAD file submittal. It is anticipated that 6 plan
sheets will be provided to the developer for construction activities. Revisions to
the Main Avenue 90% design files will be required to reflect the removal of the
design elements that the developer will be constructing.
6.3 The Consultant shall prepare Final Bid Documents for review and approval by the
City. The Final Did Documents will include all comments received from the 90%
City of Renton
Downtown Circulation Project—Phase I
Supplement 5 KPG
Project Number: 14080 7 May,2016
1
review and will be complete set of contract drawings. Final Bid Document
submittal to include the revised/added plan sheets shown in Task 6.1.
6.4 The Consultant will prepare 90% and Final Bid Document specifications,
quantities, and estimates.
Work Element 6 Deliverables:
■ Deliverables under this task will include the revised Plans, Specificarions, and
Estimates and supplement the deliverables under Work Element 7 of Supplement 2.
They are the following:
❑ One (1)%-size unbound,five (5)%-size bound of the 90%Design Plans
❑ One (1J%-size unbound,five (SJ%-size bound and one (1J Full Size of the Final
Bid Document Plans
❑ One (1) hard copy, and two (2) electronic versions (PDF and Excel) of the 90%
and Final Bid Engineer's Estimate
❑ Five (5J hard copies, and electronic versions (PDFJ of the 90% and Final Bid
Document Specifications
■ Developer Submittal- Plan Sheet and CAD files
Work Element 6 Assumptions:
■ Fiber Splicing Diagrams and Plan Sheets are not included in this submittal.
ADDITIONAL SERVICES
The City may require additional services of the Consultant. The scope of these services
will be determined based on the unanticipated project needs or other considerations at
the sole discretion of the City. This work may include items identified in the current task
authorizations as well other items, which may include, but are not necessarily limited to
the following:
• Structural Engineering
• Additional Geotechnical Engineering
• Providing Construction Administration Services
• Additional and Expanded Traffic Studies
• As-Built Drawings
These services will be authorized under a future contract supplement if necessary. At the
time these services are required, the Consultant shall provide a detailed scope of work
and an estimate of costs. The Consultant shall not proceed with the work until the City
has authorized the work and issued a notice to proceed.
City of Renton
Downtown Circulation Project—Phase I
Supplement 5 KPG '
Project Number: 14080 8 May,2016
�_.._...._ _...._ __....-------------------- . _ _
�
HOUR AND FEE ESTIMATE
Exhibi�E-1
Project: City of Renton K P G
Downtown Circulation Project
• Amhiteclum •
Water,Sewer,Storm,Fiber/Telemetry and Developer Design Coordination-Supplement 5 �..���Mar+�n..:n������.�
Date: 5/17/2015 ♦ c��������K���;�x ♦
Lebor Hour Estimate
Project Lead Field Design Design CAD/Survey
Sanbr Engineer Maneger Survey Sr.Pro'ect En Inear En ineer/Surve or En ineer/Surveyor CADD Technkien Clerical HOU�S TOt91 FEC
EHxtWe Hourly Rete(2.615 Mukiplier) S 233.07 $ 168.35 $ 112.65 $ 159.64 $ 121.31 $ 100.80 $ 101.95 $ 74.45
Task Descri tion Direct Se1ery Coste DSC S 89.13 $ 64.38 $ 43.08 $ 61.05 $ 46.39 $ 38.55 $ 38.99 $ 28.47
Work Element 1-Pro'ect Mane ement/Coordination/Administration
1.1 Management and Administration 0 4 0 0 0 0 �. 0 0 4 $ 673.39
12 Prepare monihly progress reports 0 4 . 0 0 0 0 0 2 6�$ 82228
1.3 Project Team Meetings with City Staff(4) 0 4 i 0 4 4 '� 0 0 0 12 $ 1,7g7.17
1.4 QA/aC reviews 2 8 0 4 4 �' 0 0 0 18 $ 2,936.69
Reimbursable ex enses-see breakdown for details � �' $ 108.00
Task TotalS 2 20 0 8 ' 8 0 0 2 40 $ 6,337.53
Work Element 2-Surve end Base Ma in
2.1 Survey conirol 0 1 4 0 0 I 0 0 0 5 $ 618.95
22 Additional Field survey and Note Reduction . 0 . 1 , 16 . 0 , 0 � 0 . 0 _ 0 17 $ 1,970J5
2.3 Utility locate coordination 0 0 0 0 2 : 0 0 0 2 $ 242.61
2.4 Base map preparation 0 1 0 0 0 16 0 0 17 $ 1,78122
2.5 Utility Potholing(8 estimated) 0 . 0 8 0 B 0 0 0 16 $ 1,871.64
Reimbursable ex enses-see breakdown for details � ,$ 7,706.00
Tesk Total 0 3 28 �� 0 �' 10 � 16 ' 0 0 57�.a 14,193.16
Work Element 3-Sto�mwater pocumentation
3.1 Addi�ional Requirements Analysis 0 _ 0 0 2 4 0 0 0 6 $ 804.50
3.3 Revise 7echnical Memo 0 0 0 2 8 0 0 0 10 $ 7,289.72
Reimbursable ex enses-see breakdown for details $
Task Total 0 0 0 4 12 0 0 0 16 S 2,094.22
Work Element 4-Artist Coordinetion
4.1 Goordina�ion Meetings(6) , 6 2 �. 0 0 0 12 12 0 32��$ 4,16820
Reimbursable ex enses-see breakdown for details � �' ' � $ 162.00
Task Total 6 2 0 �' 0 0 12 �' 12 0 32 $ 4,330.20
Work Element 5-Communication S stem Preliminar Desi n
5.1 Coordination Meetings(assume 3 meetings and 1 site visiQ 0 3 0 10 0 10 0 0 23 $ 3,109.48
52 Draft and Final Schematic Design 0 2 0 24 0 40 0 0 66 $ 8,200.22
Reimbursable ex enses-see breakdown for details $ 162.00
Task Total 0 5 0 34 0 50 0 0 89 S 11,471.70
Work Element 6-Final Desi n of New Utilities and Art Inte retion
6.1 Revise 90%Plans 0 0 0 48 24 40 I� 72 0 184�.$ 21,g46.96
6.2 Prepare Developer Submittal . 0 � 0 0 32 16 24 '� 40 0 112 $ 13,546.86
6.3 Prepare Final Bid Documents 0 � 0 ' 0 24 '� 8 i 24 . 8 ' 0 64 $ 8,03674
6.4 Prepare Specification,Quantities,and Estimates , 0 ; 0 � 0 � i6 ' 16 ' 16 0 , 4 52 $ 6,405.77
Relmbursable ex enses-see breakdown(or details $
Task Totel 0 0 0 120 64 104 120 4 412 S 49,936.3& �
TOTAL HOURS AND TOTAL ESTIMATED FEE 2 23 28 132 94 120 120 6 525 S 88,363.14
Ciry of Renton
Water,Sewer,Slorm,FibedTelemetry
Supplement 5 1 KPG
Hour and Fee Estimate 5/17/2016
� .
HOUR AND FEE ESTIMATE
Exhibit E-1 K p G
Project: City of Renton
Downtown Circulation Project ♦ Architec�ure ♦
I,andccupe Architacwre
Water,Sewer,Storm, FiberlTelemetry and Developer Design Coordination-Supplement 5 ♦ Civil Engineering •
Date: 5/17/2015
Reimbursable Breakdown
Work Element 1 -Project Management/Coordination/Administration
Mileage(est.200 miles x 0.54 cents/mile) $ 108.00
Reproduction $ -
Task 1 -Total $ 108.00
Work Element 2-Survey and Base Mapping
Mileage(est.200 miles x 0.54 cents/mile) $ 108.00
Reproduction $ -
Potholing(8 � $700 each) $ 5,600.00
Utility Locates(CNI) $ 2,000.00
Task 2-Total $ 7,708.00
Work Element 3-Stormwater pocumentation
Mileage $ -
Reproduction $ -
Task 3-Total $ -
City of Renton
Water,Sewer,Storm, Fiber/Telemetry
Supplement 5 2 KPG
Hour and Fee Estimate 5/17/2016
!
HOUR AND FEE ESTIMATE
Exhibit E-1 K p G
Project: City of Renton
Downtown Circulation Project ♦ Architrcturr ♦
Lendvcupe Arc-hitecwrn
Water,Sewer,Storm, FiberlTelemetry and Developer Design Coordination-Supplement 5 ♦ C'ivil L'ngineering, •
Date: 5/17/2015
Reimbursable Breakdown
Work Element 4-Artist Coordination
Mileage(est.300 miles x 0.54 cents/mile) $ 162.00
Reproduction $ -
Task 4-Total $ 162.00
Work Element 5-Communication System Preliminary Design
Mileage(est.300 miles x 0.54 cents/mile) $ 162.00
Reproduction $ -
Task 5-Total $ 162.00
Work Element 6-Final Design of New Utilities and Art Integration
Mileage $ -
Reproduction $ -
Task 6-Total $ -
TOTAL REIMBURSABLES: $ 7,978.00
�
City of Renton
Water,Sewer,Storm, Fibedfelemetry
Supplement 5 3 KPG
Hour and Fee Estimate 5/17/2016
�
Exhibit E-1
FEE SUMMARY K P G
♦ Architecturo ♦
Landscape Architecture
Project: City of Renton ♦ Civil Engineering ♦
Downtown Circulation Project
Water, Sewer, Storm, Fiber/Telemetry and Developer Design Coordination - Supplement 5
Date: 5/17/2015
Description Estimated Fee
Work Element 1 - Project Management/Coordination/Administration $6,337.53
Work Element 2 - Survey and Base Mapping $14,193.16
Work Element 3 - Stormwater pocumentation $2,094.22
Work Element 4 -Artist Coordination $4,330.20
Work Element 5 - Communication System Preliminary Design $11,471.70
Work Element 6 - Final Design of New Utilities and Art Integration $49,936.33
Total Estimated Fee $88,363.14
City of Renton
Water, Sewer, Storm, Fiber/Telemetry
Supplement 5 4 KPG
Hour and Fee Estimate 5/17/2016