Loading...
HomeMy WebLinkAboutCO 5 Denis Law Amy' City or'"'„, Mayor N:Y O� =N`rC� Public Works Department-Maintenance Division C.O.#5 Page 1 of 1 CONTRACT CHANGE ORDER AGREEMENT CONTRACT: Sidewalk Rehabilitation and Replacement Project I CAG-09-187 I CONTRACTOR: Archer Construction,Inc. SUMMARY OF PROPOSED CHANGE: Reason/Justification:After the curb and gutter were placed in the Maplewood Glen neighborhood(Schedule B),the grade of the sod in the planter strip was too uneven in the seven foot planter strip. It was decided to remove all the sod and install new sod. To help offset the cost of the sod removal,it was then decided to use hydroseed instead of sod. Sod would have cost over$11,000. The weather this time of year is favorable for hydroseeding. Contract Change:Add item for Hydroseed to Schedule B Add new bid items to the schedule of prices(Schedule A). Item Approx Units Description Unit Price Amount No. Quantity Schedule B#25(Added) I 11,265 I Square Feet I Hydroseed I $0.12 I $1,351.80 Total this Change Order: $1,351.80 All work,materials,and measurement to be in accordance with the provisions of the Standard Specifications and Special Provisions for the type of construction involved. ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATE NET CHANGE ESTIMATED CONTRACT AMOUNT AMOUNT THIS ORDER TOTAL AFTER CHANGE $288,581.23 $311,624.44 $1,351.80 $312,976.24 SIGNATURES: Contractor: ( ✓ Date: <z 7/t/y.C3 P roject Manager: ( / e Date: vA.(l V Approved By: / �, Date: V ' Transportation Design Supervisor) 3555 NE 2nd Street • Renton,Washington 98056 • rentonwa.gov