Loading...
HomeMy WebLinkAboutCO 24 RevisedCHANGE ORDER Owner Architect COR Form (This form is to be executed in triplicate and each party is to retain an original.) Contractor Project Name: RENTON SENIOR HOUSING Date: September 1, 1992 Oc+ober 1, 1992 Project Address: 3151 NE 161h Street Change Omer No.: 24 (Revised) Contractor Name. KIRTLEY-COLE ASSOCIATES ORB Project No.: COR Project No.: 9007 CAG 095-91 b Address 1002 - 10th Street Snohomish, Washington 98290 Contract For. General Construction Contract Date: October 31, 1991 The Contract is hereby amended as follows: 1. Per ORB Proposal Request 049R, 783192, and Kirtley-Cole Modification Proposal Add $3,537.21 #66, 7130192 (copies attached): 'Add circuit breaker - unit refrigerator.' 2. Per Kirtley-Cole Modification Proposal #65, 7130192, (copy attached): 'Add caulking -interior side of exterior walls.` Add $1,847.71] 3, Per Kiriley-Cole Modification Proposal 076, 8114/92, and Field Directive No. 26, 9116192 (copies attachecr): 'Furnish and instail (4) ea. HD5A at north wall and Add $615.76 (3) ea, at south wall of Room 149, to stiffen wall." TOTAL CONSTRUCTION COST IMPACT OF THIS CHANGE ORDER: ...... ........................ . A (l d 56,000.67 I ! j The Change Order shall include ail Contractor(s) labor, material, overhead, profit, and all direct and/ar 'ndirect costs associated with the Change in Scope of Work. _ This Change Order is not valid unless signed by the Owner. Architect, and Contractor. ................... $4,620,755,00 The Original Contract Sum was ..... ..................... ............. .................................. d Change Order(s) .625,700 23 Net Change by previously authorize g r(s) was...............................................................................5,24G,�i65.23 The Contract Sum prior to this Change Orderw,rs............................................................................ The Contract Sum will be revised by this Change Order in the amount of.................................................................. 6,000.67 The new Contract Su incorporating this Change Order will be ............................................................•...........: 252,465.90 Sum into + 3 days The Contract Time will be changed by ........... .. . ..................... *January14, 1993 The Substartial Completion Date Including this Change Order is See si ©rd Wrs.#12. 1l3 2L 19 for items NOTE: The above summary does not include any changes in the Contract Sum or Contract TimL which have been approved by ORB Form 301 - Construction Change Directive or Owner's Field Directives. THE ORB ORGANIZATION, INC. KIRTLEY-COLE ASSOCIATES CITY OF RENTON, P & R DEPT. 607 SW Grady Way, Suite 210 1002 - 10th Street 200 Mill Avenue South Renton, Washington 98055 Snohomish, Washington 98290 Renton, Washington 98055 zol m, A!A rdon Cole Vincent Lee Date Date Date 'ANO rE: Acceptance of the additional days on this Change Order is conditional pending receipt of K.C.'s critical path method schedule review. z 0 -r n M q:fi mz M m0 -� O OC C m m� DZ C O m� rnm_ U� 0 F O Z z 0 6 m PROPOSAL REQUEST Project Name: _ RENTON SENIOR HCUSING PROPOSAL REQUEST NO.: Forty -Nine (49) Project Address: 3151 NE 18th Street {REF: MOD. PROPOSAL No.: Renton, Washington W058 OWNER: Ctty cf Renton DATE,July 23, 1992 (Rev. July 24,1992} TO: (Contractors K1RTt.EY-CCLE ASSOCIATES COR CONTRACT NO- CAG 095-91 1o02. 10th Street OV Project No.- 9007 Snohomish, Washington 98290 Contract For: General Cons c lon Ccntract Date: Oc:ober 31. 1991 Please submit an hernized quotation for changes in the Contract Sum andlor Time Incidental to proposed modificatlons to the Contract Documents dr:sc,,ibed herein. THIS IS NOT A CHANGE ORDER CR A OIRECTION TO PROCEED WITH THE WORK DESCRIBED HEREIN. Description: (Written description of the Work) Per RFI 1180 - Additional Circuit Breaker: "Provide and install (1) extra circuit breaker in each of the unit panclboards - to accomodate the GF1 outlet in bathroom. Attachments: (List aUnched documents that support description) RFI #188 OWNER: BY: `i•c- . r+...� .., vv i...r c.�•.,� re,. rr�.�++-e_� arx:srrx+..�. rc� w*.,. M7fr ru. MnEY-4COLE ASSOCIATES, INC. 1002. 10th 39 owW Dox 1179. Seobomirk WA 98:91 now 000 SU -3175 DATE: TO: r ATTN: FROM: FAX/: RE: PAGES: G 2- FAXHITTAL (" 5610919 FAX r0C-g— f)k ( 3 (Ynctudulg Cava Sheet) p� � c2W 568-317vc AU 5. A Or Vad Witt Be Seat By Mail LAW - YES Reply Egmtcd - YES NO 0 n m RUB'S ELECTRIC INC. T :_206-334-7056 Ju 30-92 9:44 No.002 P.02 1 C IRACTM TRM4K*d" CHANGE MURDER NuMSM 2191 _. TO Nirtley Cale 1002 10th Street Snohomieh, WA 98290 nn nW=y Maas 10 malas the th6n99I6) SPOCIlled te1ow; Install one extra circuit breaker in the unit panels to accomodate the separate circuit as installed for GFI circuit.. 104 - 20 amp breakers 4 $7.30 ea. 52 - hours of labor 0 ;35.00 per hour Subtotal Plus 15% Total Amount Due 746.80 $ 2568.80 385.32 $ 2954.12 NOTti: This Ch"" Order UsoWM ,put or end to oon}xxmanx s with the existing con1mcl. WE AOARE hereby to make the change(s) specified above at this price _ 'a,xta PREVIOUS CONTRACT AMOUNT S REVISED CONTRACT TOTAL. IS A000n= — The avow prices and speelfloallone of pair of ecceplanc* _.. this Change Order ars wllsfaetory and are hereby Be— cooled. All wort( to be performed under same terms and aondittons as speckled In original contract unless Other. Signature wlse atlpulaled. tawr,uo o.n 7-29-92 As wNftft- ?XW Renton Senior Housing PR # 49 Jos MONA jail r.rox.c Kix, "o COPMACT P%)L _._ 9&A OF LtMxuM ^=Kjj aC— Install one extra circuit breaker in the unit panels to accomodate the separate circuit as installed for GFI circuit.. 104 - 20 amp breakers 4 $7.30 ea. 52 - hours of labor 0 ;35.00 per hour Subtotal Plus 15% Total Amount Due 746.80 $ 2568.80 385.32 $ 2954.12 NOTti: This Ch"" Order UsoWM ,put or end to oon}xxmanx s with the existing con1mcl. WE AOARE hereby to make the change(s) specified above at this price _ 'a,xta PREVIOUS CONTRACT AMOUNT S REVISED CONTRACT TOTAL. IS A000n= — The avow prices and speelfloallone of pair of ecceplanc* _.. this Change Order ars wllsfaetory and are hereby Be— cooled. All wort( to be performed under same terms and aondittons as speckled In original contract unless Other. Signature wlse atlpulaled. tawr,uo