AMENDMENT NO. 1 TO AGREEMENT FOR SUNSET
NEIGHBORHOOD PARK, PHASE I, ADDITIONAL CONSTRUCTION
INSPECTION & MATERIALS TESTING & CONTRACT EXTENSION
THIS AMENDMENT, dated April 16 2018, is by and between the City of Renton (the "City"), a
Washington municipal corporation, and Otto Rosenau & Associates, Inc. ("Consultant"), to
provide for additional construction inspection and materials testing services, and to extend the
contract date of completion. The City and the Consultant are referred to collectively in this
Amendment as the "Parties."Once fully executed by the Parties,this Amendment is effective as
of the last date signed by both parties.
Whereas,the City engaged the services of the Consultant under Agreement CAG-17-121, dated
July 7, 2017,to provide necessary services for the Sunset Neighborhood Park, Phase I (referred
to herein as the"Agreement");
Whereas, the Parties wish to amend the Agreement to change the time for performance in
order to complete the landscape architecture services at Sunset Neighborhood Park, Phase I.
NOW THEREFORE, It is mutually agreed upon that CAG-17-121 is amended as follows:
1. Scope of Work: Section 1, Scope of Work, is amended to modify the Work as specified
in Exhibit A-1,which is attached and incorporated herein.
2. Time of Performance: Section 3, Time of Performance, is amended pursuant to the
schedule(s) set forth in Exhibit A-1. All Work shall be performed by no later than May
15,2018.
3. Compensation: Section 4, Compensation, is amended so that the maximum amount of
compensation payable to Consultant is increased from $20,615.00 to $22,278.00, plus
any applicable state and local sales taxes. The additional compensation shall be paid
based upon Work actual performed according to the rate(s) or amounts specified in
Exhibit'A'of the Agreement.
4. All terms of the Agreement not explicitly modified herein shall remain in full force and
effect and such terms shall apply to Work performed according to this Amendment as if
fully set forth herein.
CAG-17-121 Amend No 1 Page 1 of
IN WITNESS WHEREOF,the Parties have voluntarily entered into this Agreement as of the date
last signed by the Parties below.
CITY OF RENTON CONSULTANT
By: . -411j..if
1 f7,0 By: •i# j Pjl V
Ke ly Beymer �
Judi •senau-Payseno
Community Services Administrator Owner/Principal Officer
14//. IA I i t (201.?) :
Date Date
Approved as to Legal Form
Shane Moloney
Renton City Attorney
clb 4-10-18
CAG-17-121 Amend No 1 Page 2 of 2
EXHIBIT A-1
From: Jeff Rabe I'
To: Todd Black
Cc: Judi Payseno
Subject: Pervious concrete testing
Date: Wednesday,April 04,2018 2:25:32 PM
i
Todd,
Thank you for speaking with me this morning about the pervious concrete testing at the Sunset Neighborhood
Park. I
1
The table below summarizes what we believe will be involved to this added scope of work.
Please let us know if this is acceptable and we will make ourselves available to the contractor's testing
requests.
Pervious concrete-Density of fresh concrete
by jigging method Engineer Technician 1 4 Hr $81.00 $324.00
Thickness measurement of three contractor 3 ea $70.00 $210.00
provided pervious concrete core specimens
Void Content of three contractor provided 3 ea $70.00 $210.00
previous concrete core specimens
Average density of three contractor provided ,
3 Ea $70.00 $210.00
pervious concrete core specimens.
Infiltration rate at 4 locations of pervious 1 8 hrs $81.00 $648.00
concrete placement—Engineer Technician
Pick up conctractor provided pervious
concrete core specimens 1 1 1 $61.00 $61.00
Associated Mileage(Portal to Portal) 3 60 Mile No Charge $0.00 ='
Total Estimated Budget: $1,663.00 '.
Thanks,
d
Jeffrey D. Rabe i;
Project Manager
Otto Rosenau&Associates,Inc. l';
Office Phone: (206)725-4600
Cell: (206)799-5672 t
Fax: (206)723-2221 1.
Email:jeffQottorosenau.com (