Loading...
HomeMy WebLinkAboutCO 10 CAG-17-088, CO 10-18 CITY OF RENTON Community Services Department CONTRACT CHANGE ORDER AGREEMENT CONTRACT: City of Renton 4/27/2018 CAG-17-088 CONTRACTOR: Road Construction Northwest,Inc. CHANGE ORDER: No.10R SUMMARY OF PROPOSED CHANGE: Reason/Justification: 1. City requested additional Free Library Box Weatherization 2. City requested door closures and stops at restroom. DESCRIPTION: Item Qty. Description Unit Price Amount No. w/WSST 1 1 Free Library Box Weatherization $ 749.24 $ 824.16 2 1 Door closures and stops at restrooms. $ 2,344.49 $ 2,578.94 $ - Total this Change Order: $ 3,403.10 ORIGINAL CONTRACT CURRENT CONTRACT NET CHANGE REVISED CONTRACT AMOUNT(W/WSST) AMOUNT THIS ORDER(WI WSST) TOTAL AFTER CHANGE $ 2,351,010.48 $ 2,412,229.13 $ 3,403.10 $ 2,415,632.23 Additional Calendar Days: (1)Calendar Day.New Substantial Completion Date is May 11,2018. The payment specified and agreed to in this change order includes every claim by the contractor for any extra payment with respect to the work described in this change order. The work covered by this change order must be performed under the same terms and conditions as that included in the original agreement. All of the other/terms of the original agreement remain in effect. SIGNATURES'IT,., r,, /a.c.,,,, Contractor ) Jeffrey M.Kanyer/President Date: ' , / Project Manager`��4C' Date /3 JZof 8 Approved By: // Date: /9//g. ommunity Services Administrator} !!! ROAD CONSTRUCTION NORTHWEST, INC. Force Account Request for Payment F.A.# 99-004 Bid Item# N/A DATE: 04/24/18 NAME: Sunset Neighborhood Park REMARKS: Free Library Box Weatherizing Classification Name Hours Rate of Pay Taxes/Fringe Gross Rate Total Foreman Chad 6 $ 47.00 $ 21.33 $ 68.33 $ 409.98 $ Subtotal $ 409.98 Contractor M/U @ 29% 118.89 Total $ 528.87 v5.r,"i..,..a ., .. .,,,..u,. ....e ..............z<wnS3£c.. 3.adZcvasr,..::.afi.,.. /'✓�4a�3,3'h..,... `�. _'_,. ... ,. F"- • Equipment# Class Tvpe Hours Gross Rate Total 38-101 Foreman Pickup 6 $ 22.02 $ 132.12 Subtotal $ 132.12 Contractor M/U @ 21% 27.75 Total $ 159.87 A. Description Vendor UOM Quantity Cost Total Weatherizing Materials Lowes LS 1 $ 50.000 $ 50.00 Subtotal $ 50.00 Contractor M/U @ 21% 10.50 Total $ 60.50 Classification UOM Quantity Cost Total Subtotal $ - Contractor M/U @ 12% - Total $ - Total labor,equipment,material,subcontractors $ 749.24 4/24/2018 Received/Accepted by(Owner) Submitted by(RCNW) Date Phone(425)254-9999 PO Box 2228, Renton WA 98057 Fax(425)254-1334 ROAD CONSTRUCTION NORTHWEST, INC. Force Account Request for Payment F.A.# 99-005 Bid Item# N/A DATE: 04/24/18 NAME: Sunset Neighborhood Park REMARKS:Add-LCN 4040XP door closer with drop plate @ restrooms$774.09 Add-Floor applied door stops(dome)@ restroom$31.75 Add-PS 902 power supply for bathroom doors(supply only)$160.02 Stansell Glass Labor to install door closers,drop plates and floor stops$782.00 1 Additional Workin. Da Re.uested Classification Name Hours Rate of Pay Taxes/Frinae Gross Rate Total Foreman Chad 2 $ 47.00 $ 21.33 $ 68.33 $ 136.66 $ $ Subtotal $ 136.66 Contractor M/U @ 29% 39.63 Total $ 176.29 Eauioment# Class Tvoe Hours Gross Rate Total 38-101 Foreman Pickup 2 $ 22.02 $ 44.04 Subtotal $ 44.04 Contractor M/U @ 21% 9.25 Total $ 53.29 Descr(otion Vendor 11.01 Quantity got Tota( Restroom Adds Stansell Glass LS 1 $ 1,747.860 $ 1,747.86 Subtotal $ 1,747.86 Contractor M/U @ 21% 367.05 Total $ 2,114.91 - ClassificationVendor UQM Quantity Cost Total Subtotal $ - Contractor M/U @ 12% - Total $ - Total labor,equipment,material,subcontractors $ 2,344.49 fi u 4/24/2018 Reeelved/Accepted by(Owner) Submitted by(RCNW) Date Phone(425)254-9999 PO Box 2228, Renton WA 98057 Fax(425)254-1334