CITY OF RENTON
Community Services Department
CONTRACT CHANGE ORDER AGREEMENT
6/22/2018
CONTRACT: City of Renton
CAG-17-088
CONTRACTOR: Road Construction Northwest, Inc.
CHANGE ORDER: No.14
SUMMARY OF PROPOSED CHANGE:
Reason/Justification:
Additional Work to Contract:1)Soil Amendments,2)Point of Connection,3)Landscape Additonal
Planting Area,4)Additonal Rain Garden Planting,and 5)Restroom Signage.
DESCRIPTION:
Item Qty. Description Unit Price Amount
No. w/WSST
99-006 Soil Amendments,Point of Connection,Planting $ 8,896.94 $ 9,786.63
99-007 Additional Rain Garden Planting $ 2,524.65 $ 2,777.12
99-009 Restroom Signage $ 331.22 $ 364.34
Total this Change Order: $ 12,928.09
ORIGINAL CONTRACT CURRENT CONTRACT NET CHANGE REVISED CONTRACT •
AMOUNT(W/WSST) AMOUNT THIS ORDER(W/WSST) TOTAL AFTER CHANGE
$ 2,351,010.48 $ 2,415,632.23 $ 12,928.09 $ 2,428,560.32
Additional Calendar Days:
(0)No Extension of Time.Completion Date is July 13,2018.
The payment specified and agreed to in this change order includes every claim by the contractor for any
extra payment with respect to the work described in this change order, The work covered by this change
order must be performed under the same terms and conditions as that included in the original
agreement. All of the other terjns of the original agreement remain in effect.
SIGNATURES: ------
-04
Contractor: 'vel ♦ ...„----Jeffrey M.Kanyer,President Date: 6/27/18
/
Project Manager: ' Date 4028/20/8
11119
Date: 7/&
Approved By: //8
r'ommunity Services Administrator)