AMENDMENT NO. 3 TO AGREEMENT FOR ARCHITECTURAL
SERVICES, FIRE STATION #15
THIS AMENDMENT, dated I / D , is by and between the City of Renton (the
"City"), a Washington municip I corporation, and Schreiber Starling Whitehead, Architects
("Consultant"), a Washington Professional Services Company. The City and the Consultant are
referred to collectively in this Amendment as the "Parties." Once fully executed by the Parties,
this Amendment is effective as of the last date signed by both parties.
Whereas, the City engaged the services of the Consultant under Agreement CAG-17-046, dated
March 15, 2017, to provide necessary services for the design of Fire Station #15 (referred to
herein as the "Agreement");
Whereas, the Parties wish to amend the Agreement to change the scope of work, change the
time for performance, and change the compensation in order to design the station signaling and
administer construction administration (CA)through the completion of the project.
NOW THEREFORE, It is mutually agreed upon that CAG-17-046 is amended as follows:
1. Scope of Work: Section 1, Scope of Work, is amended to add work as specified in Exhibit
A-3 and A-4, which are attached and incorporated herein]
2. Time of Performance: Section 3, Time of Performance, is amended pursuant to the
schedule(s)set forth in Exhibit A-4.All Work shall be performed by no later than February
1, 2019.
3. Compensation: Section 4, Compensation, is amended so that the maximum amount of
compensation payable to Consultant is increased by $5,450 + $26,250 for a total of
$31,700 increasing the total contract amount from $804,297.70 to$835,997.70, plus any
applicable state and local sales taxes. The additional compensation shall be paid based
upon Work actual performed according to the rate(s) or amounts specified in Exhibit C of
the CAG-17-046 Agreement.
4. All terms of the Agreement not explicitly modified herein shall remain in full force and
effect and such terms shall apply to Work performed according to this Amendment as if
fully set forth herein.
IN WITNESS WHEREOF, the Parties have voluntarily entered into this Agreement as of the date
last signed by the Parties below.
CITY OF RENTON CONSULTANT
By: By: rg , - ��
Kelly Beymer Keit Sc ;�A
Community Services Administrator Schreiber Starling Whitehead
Architects
//( Itg 08/16/18
Date Date
Approved as to Legal Form
Shane Moloney
Renton City Attorney
Contract Template R CLB 8-15-18(127)
(;)
PAGE 2 OF 2
EXHIBIT A-3
lob`����
.•••••1 ARCHITECTS
SCHREIBER
STARLING
WHITEHEAD
13 August 2018 901 I TO AVE a"3100
SEATTLE.WA 98164
Mr.Robert Ebert 206 682 8300
Capital Projects Coordinator SSWAPCHITECTS 500
Community Services Department
Renton City Hall-6th Floor
1055 South Grady Way
Subject: Fire Station#15
Agreement CAG-17-046 Request for Amendment: Station Alerting Design
Dear Robert:
When we originally established the services for our design team,it was not certain how we were to
include the needed Station Alerting systems in the project.The RRFA has an operational agreement
with a vendor to provide and maintain these systems in their existing stations and it was
undetermined if we should include their design efforts under our contract,or if the City of the RRFA
would contract direct for the altering systems design and construction.
As the design progressed,it was clear that the alerting system needed to be designed and included
in the bid documents so that its provision and installation would be covered under the
construction contract. To provide for this,we engaged Jaymarc AV,the District's preferred provider
to develop design drawings and specification that were incorporated into the bid documents.
Unfortunately,we did not address the lack of their inclusion under our prime agreement for this
element of design. Accordingly,I request an amendment to our agreement totaling$5,450($4,954
+10%)to correct this issue and to compensate our consultant for their design work on the Station
Alerting system.
Thank you very much for your attention to this request.
Respectfully,
Keith Jame c er AIA
Principal
Attachment:Jaymarc Invoice#3515
INVOICE: 3515 Invoice Date:
MRc giv Project Number: 17-51359 08ro6/2018
F
I _ .-
or:
R f i , j
Terms:Net 20 Days
Date Due: 08/26/2018
2732 1st Ave South Client#:C19289
Seattle, WA 98134
206-682-6111 Renton FS#15- ENG/SPEC ONLY
Bill to: Project Site:
Schreiber Starling Whitehead Architects
Keith Schreiber 901 Fifth Avenue
901 5th Ave, No,3100 No. 3100
Seattle,WA 98164 USA Seattle WA 98164
Tel:206-682-8300
Sales Person: Tyson &Josh Invoice Date: 08/06/2018
Authorized Agent: Mary Jo Lux Product Code: S
Qty Mfr-Part No. Description Unit Price Extended
1 FS Alerting System Specs-per quote 4500.00
Sales Tax WA $ 454.50
Tax ID:91-1637343 Balance Due: $ 4,954.50
Print Date:8/6/2018 JAYMARC-AV Project: 17-51359 INVOICE:3515 Page 1 of 1
EXHIBIT A-4
ARCHITECTS
SCHREIBER
STARLING
WHITEHEAD
13 August 2018 901 FIFTH AVE" 3100
SEATTLE.WA 98164
Mr.Robert Ebert 206 6828300
Capital Projects Coordinator SSWARCHTE(TS COM
Community Services Department
Renton City Hall-6`h Floor
1055 South Grady Way
Subject: Fire Station#15
Agreement CAG-17-046 Request for Amendment: CA/Contract Extension
Dear Robert:
As we discussed last week,it is apparent that the contractor will likely not achieve substantial
completion of the Fire Station by 1 December as currently planned. They have been managing the
project on their 3-week look-ahead schedule which has resulting in their overall schedule lagging
behind projection,particularly on the exterior envelope scope. Their schedule indicates that the
roofing was to have been completed 7/31/18 and the siding was to have been completed 8/1/18.
As of our 8/10 meeting,neither of these elements has started installation. Additionally,I note that
the schedule has the close-out and completion of the project extending to 2/1/19 whereas our
current agreement ends on 12/31/18.
Given the current status of construction and inevitable issue that come up as a project nears
completion,we anticipate that and additional 1.5 months of our Project Architect and Project
Manager may be needed to complete the project.Based on our efforts to date,our PM logs approx.
30-hrs/month and our PA logs on average 160 hrs.per month during the construction phase. This
totals$17,500/month. I request that we increase our CA Phase services by$26,250 which would
only be used if needed. Additionally,I request that a No-Cost Amendment be made to our
agreement to extend the duration until 1 March 2019.
Thank you very much for your attention to this request.
Respectfully,
Keith Jame c er AIA
Principal .