Facilities Division CAG-17-235 CO NO. 4
CONTRACT CHANGE ORDER (CO) PROJECT TITLE Fire Station 15
TO: Par-Tech Construction Inc. (CONTRACTOR)
The following mutually agreed to and Owner approved Change Order Proposal(s)and/or Field Authorization(s)are hereby
incorporated by reference into the contract.
COP 12 ($349.80)
COP 14 $2,003.56
COP 15 $7,872.57
COP 18 $2,348.91
COP 19 $513.19
CONTRACT SUM:
❑ NO CHANGE
❑✓ INCREASE Twelve Thousand Three Hundred Eighty Eight Dollars and Forty 1 $12,388.43
111 DECREASE --
(WASHINGTON STATE SALES TAX INCLUDED)
CONTRACT TIME:
❑, NO CHANGE
❑INCREASE OF CALENDAR DAYS 0
❑ DECREASE
The foregoing amount covers everything required in connection with the change.Allother provisions of the contract remain in full force and
effect.
CONTRACT SUMMARY(Internal Use Only)
ORIGINAL CONTRACT SUM $ 4,273,500.00 PREVIOUS TOTAL $4,355,110.10
PREVIOUS ADDITIONS $ 0 CHANGE AMOUNT 12,388.43
PREVIOUS DEDUCTIONS $ 0 NEW TOTAL $4,367,498.53
PERCENT CHANGE FROM ORIGINAL CONTRACT AMOUNT 2.20%
NEW CONTRACT COMPLETION DATE No Change
TOTAL CONTRACT CALENDAR DAYS No Change
The City of Renton hereby accepts the foregoing Field Authorization(s)and/or Change Order Proposal(s).This formal acceptance constitutes a
Change to the contract only when authorizing signature is affixed.Invoices incorporating this Change Order constitute acceptance by the
Contractor as total reimbursement due in connection with this Change Order.
enr F(P4
AUTHORIZIN IGN/URE DATE
Community Services
• Facilities Division COP#12
CONTRACT CHANGE ORDER PROPOSAL
(COP)
TO:Par-Tech Construction (CONTRACTOR) Proposal Request Date: 6/12/18
You are directed to prepare a cost proposal for the work described below and/or detailed on the attachment referred to:
Omit the 4"PVC vents(high and low)for the flammable stroage cabinet In the Shop Room 123 shown on
1/M4.01
REASON FOR CHANGE Design Errors Design City latent Code Value
Omissions Conditions Requirement Engineering
EXPLANATION:Venting not required per City of Renton
DATE PROPOSAL REQUIRED: 6/26/18 CHANGE ORIGINATED BY: SSW Architects
(14 days from Request Date,unless other date agreed to)
PROPOSAL REQUESTED BY: Jonas Hallstrom
TO:SSW Architects(Mary Jo Lux) (NE) TO: Robert Ebert COR
WE AGREE TO PERFORM ALL CHANGE IN THE WORK DESCRIBED IN THE PROPOSAL REQUEST FOR:
CONTRACT SUM:
❑NO CHANGE ))
❑INCREASE OF -t 6$- Etc taDAa+D G2,-TY r4ii411- cf. rtO/A�a $"391.00
0 DECREASE (WASHINGTON STATE SALES TAX INCLUDED)
In accordance with the general condition,Cost Estimate Detail Sheet(s)are attached hereto.
CONTRACT TIME:
Q NO CHANGE
❑INCREASE OF 0 CALENDAR DAYS
❑DECREASE
The foregoing amount covers everything required in connection with the change.All other provisions of the contract remain In full
force and effect.
We understand that this proposal does not constitute authorization to proceed with the specified changes in the work until
Incorporation of this COP into a Change Order by the City of Renton.
BY H.
CONTRACTOR SI TURE D TE
We have carefully examined this proposal and find the cost to be reasonable. Therefore,we recommend acceptance.
1\flitAis?"
A/E DATE
/31,7,6_
C OF RENT DATE
PA R TECH Project: Renton Fire Station 15
COP:
CONSTRUCTION, INC. Project Manager: Ben Parsons
CCB#109451 WA#PARTECI972JI Cell Number: (971)275-6238
Sub Total Grand Total
Par-Trch Wok
'Par-Tech SelfPerform Total(See Breakdown on next page] $0.00
S,brwith.(tor iota•
Crescent Mechanical -$318.00
Subcontractor work -$318.00
Overhead Markup 4%to the first($50,000) $0.00
Overhead Markup 2%to the remaining costs
Profit Markup 4% $0.00
Total Subcontractor Markup $0.00
,u.
Subcontractor Total -$318.00
Sub total of Par-Tech&Subcontractor Pricing -$318.00
Irsur.inre&Bonding
Liability Insurance
Public Works Bond(160%) $0.00;
Total
fax(10%) $31.80
,Grand Total -$349.80
1320 26th St NW#16
" Auburn WA 98001
�- Phone: 253-833-5054
Fax:253-833-5144
PROPOSED CHANGE ORDER
To: Par Tech Construction
13753 S Forsythe Rd
Oregon City Or 97045
Subject: Renton FS#15 CMI Job No: 2356
CMI PCO#: 1
Attention: Ben Parsons Date: 8/13/2018
We request a change order for the following work performed on this project:
Description: COP#12-Omit 2 PVC Vents for Flammable Storage Cabinet in Shop Rm 123
Amount of This Change Request: ($318)
"'Detailed Breakdown Attached
1We are awaiting written direction before proceeding with this work.
Work During Regular Hours Only
[Work Done on Expedited Basis
JPer,we are proceeding with this work
Work in Progress
]Work Already Completed
By: Abby Haubrich
Title: Project Manager
cc:
PM
The cost of this change includes only those direct costs which can be identified at this time. There are no impact,ripple or delay costs
included. Should It be determined at a later date that we are experiencing impact costs because of multiple changes,delays or other causes
beyond our control.we will submit those costs at that time.
. Community Services
Facilities Division COP#14
CONTRACT CHANGE ORDER PROPOSAL
(COP)
TO:Par-Tech Construction (CONTRACTOR) Proposal Request Date: 7/10/18
You are directed to prepare a cost proposal for the work described below and/or detailed on the attachment referred to:
At Hallway 102A&Hallway 102D,add(2)layers of 1/2"gypsum board type C to the bottom of the Ills. Floor
/Ceiling assemblies in these Hallways to meet 1 hour fire rating per ICC-ES ESR-1153 Assembly B(see
attachment).Gypsum board shall be continuous over entire area and seal to gypsum board at adjacent fire
rated partitions.Fire Caulk all penetration through floor ceiling assembly in these areas
REASON FOR CHANGE Design Errors Design City Latent Code Value
Omissions Conditions Requirement Engineering
EXPLANATION:Code requirement
DATE PROPOSAL REQUIRED: 7/24/18 CHANGE ORIGINATED BY: SSW Architects
(14 days from Request Date,unless other date agreed to)
PROPOSAL REQUESTED BY: Jonas Halistrom
TO:SSW Architects(Mary Jo Lux) (WE) TO: Robert Ebert COR
WE AGREE TO PERFORM ALL CHANGE IN THE WORK DESCRIBED IN THE PROPOSAL REQUEST FOR:
CONTRACT SUM:
❑NO CHANGEINCREASE
ID DECREASE OF-rtA)r) -T�}f".'CJSpIt oo �#sQ -T�.g&
(WASHINGTON STATE SALES TAX INCLUDED)
In accordance with the general condition,Cost Estimate Detail Sheet(s)are attached hereto.
CONTRACT TIME:
❑✓ NO CHANGE
❑INCREASE OF
����tO CALENDAR DAYS
❑DECREASE
The foregoing amount covers everything required in connection with the change.All other provisions of the contract remain in full
force and effect.
We understand that this proposal does not constitute authorization to proceed with the specified changes in the work until
incorporation of this COP into a Change Order by the City of Renton.
BY J 61g /S-
CONTRACTOR I N' RE DATE
We have carefully examined this proposal and find the cost to be reasonable. Therefore,we recommend acceptance.
1.11. A
A/ DATE
„e Rho I/g
CITY OF REN `•N / DATE
PAR- TECH Profect:P: 14nton Fire Station 15
CONSTRUCTION, INC. Project Manager: Ben Parsons
CCB#109451 WA#PARTECI972J1 Cell Number: (971)275-6238
Sub Total Grand Total
ParT('
Par-Tech Self Perform Total(See Breakdown on next page) $261.27
DL Henricksen $1,393.24
Subcontractor work $1,393.24
Overhead Markup 4%to the first($50,000) $55.73
Overhead Markup 2%to the remaining costs
Profit Markup 4% $55.73
Total Subcontractor Markup $111.46
Subcontractor Total $1,504.70
Sub total of Par-Tech&Subcontractor Pricing $1,765.96
Insuranre>&Bonding
Liability Insurance(1.54%) $27.20
Public Works Bond(1.60%) $28.26
Total $1,821.42
Tax(10%) $182.14
Grand Total $2,003.56
PAR TECH
CONSTRUCTION, INC. Project: Renton Fire Station 15
COP# 14
Type of Worker Rate Quantity Total
Carpenter $73.25 2 $146.50
$0.00
$0.00
$0.00
Total of Labor $146.50
Type of Materials Rate Quantity Total
Fire Caulk $75.00
$0.00
$0.00
$0.00
Total of Materials $75.00
Type of Equipment Rate Quantity Total
$0.00
$0.00
$0.00
$0.00
Total of Equipment $0.00
Total of Change w/out markup $221.50
12%Markup $26.58
Small tools @ 3%of Direct Labor $4.40
6%for work performed by own forces $8.79
Sub total for Par-Tech $261.27
Project Name: Renton Fire#15
Work Desc.
COP#14 Add 2 layers of 1/2"type"C"to floor joist in Hallways 102A and 102D Firetape
A.Labor B
UNITS HOURLY l
PER LABOR Labor Unit iMaterial Unit
SPECIFCATION DESCRIPTION
QUANTITY UNIT HOUR RATE Cost Cost Cost
GWB Hang Ceilinks 360 J SF 55 76.16 1.3847273 498.50182 0.5
Tape 360 SF 90 72.48 0.8053333 289.92 0.05
Stock Scrap&Clean 2 j Hours 1 76.16 76.16 152.32
940.74
A. 940.74 B.
Labe
Hourly Rates Include Labor Burden(Suchas Labor Taxes,Union Benefits,Etc) Mate
-- =
Equl
Taxi
I Subto
_ Jobsit
Due to the added scope this change order requires an extension of time of 5 working days to the pro'ect duration/schedule
This estimate is valid for 30 days and we reserve the right to reprice this change if j9bsite conditions change Subto
T Overl
This change estimate is based on the usual cost elements such as labor,materials and markup. Unless otherwise on this document,it does not include anvalue for rot.
interfemeces;disruptions,changes in the sequence of work,delays,anycosts associated with acceleration,extended overhead,ovetime and or ineffciencLcosts. nsur
We espressly reserve the right to submit costs for any of these items should we be faced with performing a y_gf the work under any of these conditions and will TOT'
track these costs as they are incurred and submit for payment after the completion of this change order work. Bond
l I Total
D.L.Henricksen Co.,Inc.
6005 20th Street East Tacoma WA.98424
Phone(253)922 5566 Fax(253)922 2178
Paye i
- 24K0 Community Services
- Facilities Division COP#15
CONTRACT CHANGE ORDER PROPOSAL
(COP)
TO:Par-Tech Construction (CONTRACTOR) Proposal Request Date: 7/20/18
You are directed to prepare a cost proposal for the work described below and/or detailed on the attachment referred to:
Revise the lockers per attached RFI-37 response&ASK-40.
REASON FOR CHANGE Design Errors Design
CityLatent Code Value
OmissionsConditions Requirement Engineering
EXPLANATION:30"cabinet doors exceed maximum AWS recommendation
DATE PROPOSAL REQUIRED: 8/3/18 CHANGE ORIGINATED BY: SSW Architects
(14 days from Request Date,unless other date agreed to)
PROPOSAL REQUESTED BY: Jonas Hallstrom
TO:SSW Architects(Mary Jo Lux) (WE) TO: Robert Ebert COR
WE AGREE TO PERFORM ALL CHANGE IN THE WORK DESCRIBED IN THE PROPOSAL REQUEST FOR:
CONTRACT SUM:
❑NO CHANGE -? J
0 INCREASE OF A 1'tia-2,C hf q- ��b $ C5 9 2.g 2""
❑DECREASE (WASHINGTON STATE SALES TAXINCLUDED) r t
In accordance with the generalcondition, ost Estimate Detail Sheet(s)are attached hereto.
CONTRACT TIME:
Q NO CHANGE
❑INCREASE OF 0 CALENDAR DAYS
0 DECREASE
The foregoing amount covers everything required in connection with the change.All other provisions of the contract remain in full
force and effect.
We understand that this proposal does not constitute authorization to proceed with the specified changes in the work until
incorporation of this COP into a Change Order by the City of Renton.
1 ?-
CONTRACTOR SIG URE DATE
We have carefully examined this proposal and find the cost to be reasonable. Therefore,we recommend acceptance.
4111
A/E DATE
AVich
CITY OF RENT•N / DATE
pA R- TECH
Project:
f P:15 Renton Fire Station 15
CONSTRUCTION, INC. Project Manager: Ben Parsons
CCB#109451 WA#PARTECI972J1 Cell Number: (971)275-6238
Sub Total Grand Total
?ao-TE'ch V'cr
Par-Tech Self Perform Total(See Breakdown on next page) $0.00
SuLco! ' 3itnr Tptal
Genothen $6,425.00
Subcontractor work $6,425.00
Overhead Markup 4%to the first($50,000) $257.00
Overhead Markup 2%to the remaining costs
Profit Markup 4% $257.00
Total Subcontractor Markup $514.00
Subcontractor Total $6,939.00
Sub total of Par-Tech&Subcontractor Pricing $6,939.00
Insurance&Bondi rig
Liability insurance(1.54%) $106.86
Public Works Bond(1.60%) $111.02
Total $7,156.88
Tax(10%) $715.69
Grand Total $7,872.57
r,• vor
GEN !iHEN
A division of Genothen Holdings,L.L.C.
Change Order Proposal # 1 TSP
Job: 12357 Fire Station 15- City of Renton
COP Generated Per: RFI 37'ASK 41/COP 15 Locker Doors
To: Par-Tech Construction From: Kyanne Brown,Project Administrator,ext. 110
Attn: Ben Parsons Date Issued: Friday,August 03,2018
Phone: (503)557-8300
Fax: Expiration Date: Friday,August 10,2018
DESCRIPTION
In accordance with COP 15,furnish wardrobe lockers per ASK-40 in lieu of original design. This change is for a total of 20 lockers.
COSTS AMOUNT
Total Cost $6,425.00
Total: $6,425.00
The approximate lead time on this product after receipt of approval is 8 week(s).
Genothen is not proceeding with this work until written notification is received,per contract documents.
Genothen agrees to be bound by this proposal up until the Expiration Date noted above,AFTER WHICH IT BECOMES
VOID.
In accordance with contract documents, Genothen will not be held responsible for impacts to construction schedule due
to change orders left unsigned after the Expiration Date.
Signature
Name(Please Print)
Date
•
Page 1 of 1
2948 29th Ave SW — Tumwater,WA 98512 — voice(380)352-3636 — fax(360)352-0753 - www.genothen.com
Washington Contractor's License#GENOTHL944BD/Oregon CCB Registration#159658
Idaho Public Works#PWC-C-15877-A-4/Alaska General Contractor's License#30968
GENOTHEN
A division of Cenothen Holdings, L.L.C.
Project: Renton Fire Station 15
Ref-COP 15/ASK-40 COP# 15
Type of Worker Rate Quantity Total
Shop Labor $55.00 60 $3,300.00
$0.00
$0.0C
$0.0C
Total of Labor $3,300.00
Type of Materials Rate Quantity Total
Added Pulls, Banding, Hinges,Vents $2,260.00 1 $2,260.00
$0.00
$0.0C
$0.0C
Total of Materials $2,260.00
Type of Equipment Rate Quantity Total
$0.00
$0.0(
$0.0C
$0.0(
Total of Equipment $0.00
Total of Change wl out markup $5,560.00
12%Markup $667.20
Small tools @ 5%of Direct Labor $0.00
6%for work performed by own forces $198.00
Sub total for Par-Tech $6,425.20
;' Community Services
�s ;
-, • Facilities Division COP It 18
CONTRACT CHANGE ORDER PROPOSAL
(COP)
TO:Par-Tech Construction (CONTRACTOR) Proposal Request Date: 8/6/18
You are directed to prepare a cost proposal for the work described below and/or detailed on the attachment referred to:
Change the exterior board insulation type at the CMU walls(Exterior Wall Assembly Type W1)from mineral
fiber board to extruded polystyrene board per previously issued SI-15
REASON FOR CHANGE Design Errors Design City, latent Code Value
Omissions Conditions Requirement Engineering
EXPLANATION:R-10 min insulation code required
DATE PROPOSAL REQUIRED: 8/20/18 CHANGE ORIGINATED BY: SSW Architects
(14 days from Request Date,unless other date agreed to)
PROPOSAL REQUESTED BY:
TO:SSW Architects(Mary Jo Lux) (A/E) TO: Robert Ebert COR
WE AGREE TO PERFORM ALL CHANGE IN THE WORK DESCRIBED IN THE PROPOSAL REQUEST FOR:
CONTRACT SUM:
❑NO CHANGE
Q INCREASE -�^�s,�
o DECREASE OF Tir,►C+ .`�zaus ithso 7ihtez tiJNo $ 2,318.
(WASHINGTON STATE SALES TAX INCLUDED)
e12.141-r.
In accordance with the genendition,Cost Estimate Detail Sheet(s)are attached hereto.
CONTRACT TIME:
Q NO CHANGE
❑INCREASE OF 0 CALENDAR DAYS
❑DECREASE
The foregoing amount covers everything required in connection with the change.All other provisions of the contract remain in full
force and effect.
We understand that this proposal does not constitute authorization to proceed with the specified changes in the work until
incorporation of this COP into a Change Order by the Cityof enton. d,,
P --7--t+ BY 8/Sok'?
CONTRACTOR SIGN RE DATE
We have carefully examined this proposal and find the cost to be reasonable. Therefore,we recommend acceptance.
•
d AM. .14111 (0
A/E DATE
Of) by
CITY OF RE ON / DATE
PAR- TECH Project: Renton Fire Station 15
COP:
CONSTRUCTION, INC. Project Manager: Ben Parsons
CCB#109451 WA#PARTECI972J1 Cell Number: (971)275-6238
Sub Total Grand Total
Por-TErch Work
Par-Tech Self Perform Total(See Breakdown on next page) $0.00
SL lit tor l ot��!
Architectal Sheet Metal $1,917.00
Subcontractor work $1,917.00
Overhead Markup 4%to the first($50,000) $76.68
Overhead Markup 2%to the remaining costs
Profit Markup 4% $76.68
Total Subcontractor Markup $153.36
Subcontractor Total $2,070.36
Sub total of Par-Tech&Subcontractor Pricing $2,070.36
Insurance gc Bonding
Liability Insurance(1.54%) $31.88
Public Works Bond(1.60%) $33.13
Total $2,13537
Tax(10%) $213.54
Grand Total $2,348.91
Project: Renton Fire Station 15
COP# 18
Type of Worker Rate Quantity Total
Sheet Metal Add $90.88 31 $2,817.28
Sheet Metal Deduct $90.88 -14 -$1,272.32
$0.00
$0.00
Total of Labor $1,544.96
Type of Materials Rate Quantity Total
XPS Insulation $1,428.00
freight $125.00
Rookwool -$1,438.00
freight -$100.00
Total of Materials $15.00
Type of Equipment Rate Quantity Total
$0.00
$0.00
$0.00
$0.00
Total of Equipment $0.00
Total of Change w/out markup $1,559.96
12%Markup $187.20
Small tools @ 5%of Direct Labor $77.25
6%for work performed by own forces $92.70
Sub total for Par-Tech $1,917.10
vrecc AL ,- FAX TRANSMISSION
RcH ltkC.
`�Q•t j�►ti,
METAL EXTERIORS,FLASHING,U FABRICATION DATE TIME
11220 164TH ST. E.
PUYALLUP,WA 98374 8-8-2018
(253)445-9500 • FAX(253)446-0664
TO Bob Parsons FAX
COMPANY Par-Tech Construction Inc.
SUBJECT Fire Station#15 ref=Cop 018 to add 2"thick XPX Insulation
Darren Pederson
FROM
TOTAL NUMBER OF PAGES INCLUDING THIS PAGE 1 , IF YOU DO NOT RECEIVE ALL PAGES, PLEASE CONTACT US,
REMARKS
Architectural Sheet Metal is pleased to offer a quote for the above-mentioned Supplemental
instruction change
Total =$ 4,370.00
Price breakdown as follows
Material cost
-) 1,472 sq ft of 2"XPS insulation @$ .97 per sq ft $ 1,428.00
-)Freight delivery cost to jobsite 125.00
Labor cost
Shop 0
Field 35
Total=31 @$90.88 per hour 2,817.00
Total=4,370.00
Price Excludes
-)wa state sales tax
Any questions please feel free to call
Thank You Darren Pederson
L - FAX TRANSMISSION
METAL EXTERIORS,FLASHING,&FABRICATION DATE TIME
11220 164TH ST. E.
PUYALLUP,WA 98374 8-1-2018
(253)445-9500 • FAX(253)446-0664
TO Bob Parsons FAX
COMPANY Par-Tech Construction Inc.
SUBJECT Fire Station#15 ref= Credit back for deleting Rockwool insulation from project
Darren Pederson
FROM
TOTAL NUMBER OF PAGES INCLUDING THIS PAGE . IF YOU DO NOT RECEIVE ALL PAGES, PLEASE CONTACT US.
REMARKS
Architectural Sheet Metal is pleased to offer a quote for the above-mentioned Supplemental
instruction change
Total Credit =<$ 2,810.00>
Price breakdown as follows
Material cost
-) 1,410 sq ft of 2"Rockwool insulation @$1.02 per sq ft <$ 1,438.00>
-)Freight delivery cost to jobsite <100.00>
Labor cost
Shop 0
Field 14
Total= 14 @ $90.88 per hour <L272.00>
Total =<$ 2,810.00>
Price Excludes
-)wa state sales tax
Any questions please feel free to call
Thank You Darren Pederson
Community Services
Facilities Division COP#19
CONTRACT CHANGE ORDER PROPOSAL
(COP)
TO:Par-Tech Construction (CONTRACTOR) Proposal Request Date: 8/10/18
You are directed to prepare a cost proposal for the work described below and/or detailed on the attachment referred to:
Change the tile grout type at the Restroom walls from silicone rubber(as specified in 09 3000 3.07-A-4)to
cementitious(as was bid according to email from Ben Parsons on 8/1/2018).
Change the tile grout type at the Restroom floors from cementitious(as specified in 09 3000 3.07-B-3)to
epoxy grout.
REASON FOR CHANGE Design Errors Design City Latent Code Value
Omissions Conditions Requirement Engineering
EXPLANATION:Specified grout not applicable at walls;Better performance at floors
DATE PROPOSAL REQUIRED: 8/24/18 CHANGE ORIGINATED BY: SSW Architects
(14 days from Request Date,unless other date agreed to)
PROPOSAL REQUESTED BY:
TO:SSW Architects(Mary Jo Lux) (A/E) TO: Robert Ebert COR
WE AGREE TO PERFORM ALL CHANGE IN THE WORK DESCRIBED IN THE PROPOSAL REQUEST FOR:
CONTRACT SUM:
❑NO CHANGE
❑� INCREASE OF
❑DECREASE is (41.44p12-60 IL-TWOM .�^ I 10 0 $ S11. 11
(WASHINGTON STATE SALES TAX INCLUDED)
In accordance with the general condition,Cost Estimate Detail Sheet(s)are attached hereto.
CONTRACT TIME:
Q NO CHANGE
❑INCREASE OF 0 CALENDAR DAYS
❑DECREASE
The foregoing amount covers everything required in connection with the change.All other provisions of the contract remain in full
force and effect.
We understand that this proposal does not constitute authorization to proceed with the specified changes in the work until
incorporation of this COP into a Change Order by the City of Renton.
BY '`
CONTRACTOR GNAI'URE DAT
We have carefully examined this proposal and find the cost to be reasonable. Therefore,we recommend acceptance.
1\41114(1)-3
1\--(4°
A/E DAT
CITY OF RENT N DATE
Jj\ J TIT1 :fCH ProP9non Fire Station 15
CONSTRUCTION, INC. Project Manager: Ben Parsons
CCB#109451 WA#PARTECI972J1 Cell Number: (971)275-6238
Sub Total Grand Total
Par-Tech\Vork
Par-Tech Self Perform Total(See Breakdown on next page) $0.00
51,b, for Tutai
Great Floors $418.83
Subcontractor work $418.83
Overhead Markup 4%to the first($50,000) $16.75
Overhead Markup 2%to the remaining costs
Profit Markup 4% $16.75
Total Subcontractor Markup $33.51
Subcontractor Total $452.34
Sub total of Par-Tech&Subcontractor Pricing $452.34
Insurance&Bonding
Liability Insurance(1.54%) $6.97
Public Works Bond(1.60%) $7.24
Total $466.54
Tax(10%) $46.65
Grand Total $513.19
Page 1 of I
8/14/2018
GREAT FLOORS - Commercial Sales
9021 SOUTH 180TH ST,KENT, WA—PH(206)241-0229 FAX(206)241-2699
To: Partech Construction Site: Renton Fire Station #15
Attn: Ben Parsons
COP 19
Change the restroom floor tile to Laticrete Spectralock Pro epoy grout
Additional labor and materials $418.83
INCLUSIONS: Unless otherwise noted the following items are included:transitions,adhesives,sundries.
EXCLUSIONS:Any items not listed on this document are not included in this bid proposal. Additionally,unless
otherwise noted above,the following items are specifically excluded:bonds,taxes,furniture moving,demo and
removal,floor and wall prep,cleaning,waxing,sealing,protection,concrete moisture testing,concrete moisture
mitigation,underlayments,hoisting,patching,after hours/weekend work,union labor. Bid valid 30 days
TERMS:Payment,net 30 days. All floor covering to be installed per manufacturer's installation instructions.
Conditions set forth in this proposal are binding unless otherwise negotiated and mutually agreed upon
WASHINGTON CONTRACTORS LICENSE#GREATF*955D4.
Acknowledgement and Agreement:The undersigned accepts,agrees to,and acknowledges all terms and
conditions set forth in this proposal.
Signature: Thank you for the opportunity to be of service!
Printed Name: John Scott
Title: Account Representative,Great Floors
Date: Commercial Sales
Project: Renton Fire Station 15
COP# 19
Type of Worker Rate Quantity Total
epoxy installation (sq.ft rate) $1.25 115 $143.75
$0.00
$0.00
$0.00
Total of Labor $143.75
Type of Materials Rate Quantity Total
Laticrete Spectralock Pro epoxy $154.59 1 $154.59
epoxy colorant $15.01 4 $60.04
cleaning powder $1.46 1 $1.46
$0.00
Total of Materials $216.09
Type of Equipment Rate Quantity Total
$0.00
$0.00
$0.00
$0.00
Total of Equipment $0.00
Total of Change w/out markup $359.84
12%Markup $43.18
Small tools @ 5%of Direct Labor $7.19
6%for work performed by own forces $8.63
Sub total for Par-Tech $418.83