AMENDMENT NO. 2 TO AGREEMENT FOR CITY HALL
MODERNIZATION PROJECT (CAG-17-153)
THIS AMENDMENT, dated ilv a t Z , 2019, is by and between the City of Renton (the
"City"), a Washington munici al corporation, and Stemper Architecture Collaborative, Inc.
("Consultant"), a Washington State Professional Services Corporation. The City and the
Consultant are referred to collectively in this Amendment as the "Parties." Once fully executed
by the Parties,this Amendment is effective as of the last date signed by both parties.
Whereas,the City engaged the services of the Consultant under Agreement CAG-17-153, dated
July 13, 2017, to provide necessary services for the Architectural and Engineering Services,
Production of Permit and Bid Documents, Assistance with Bidding, Construction Administration
and Project Close-Out(referred to herein as the"Agreement");
Whereas, the Parties wish to amend the Agreement to provide professional services necessary
to replace the Emergency Generator in Renton City Hall required to provide emergency power to
the elevators and other critical systems.
NOW THEREFORE, It is mutually agreed upon that CAG-17-153 is amended as follows:
1. Scope of Work:Section 1,Scope of Work, is amended to add work as specified in Exhibit
A-2,which is attached and incorporated herein.
2. Compensation: Section 4, Compensation, is amended so that the maximum amount of
compensation payable to Consultant is increased by $82,897.00 from $365,118.00 to
$448,015.00 plus any applicable state and local sales taxes.The additional compensation
shall be paid based upon Work actual performed according to the rate(s) or amounts
specified in Exhibit A-2 which is attached and incorporated herein.
3. All terms of the Agreement not explicitly modified herein shall remain in full force and
effect and such terms shall apply to Work performed according to this Amendment as if
fully set forth herein.
IN WITNESS WHEREOF,the Parties have voluntarily entered into this Agreement as of the date
last signed by the Parties below.
CITY OF RENTON St i F er Archite Collaborative
De is Law, Mayor Enter Signer's Name
Enter Signer's Title
/27/
Date Date
Attes
1as n A. ethurnrrrrr' 0
�ii4
Cit Clerk °`< •
SFAL
Approved as to Legal Form
Ir
Shane Moloney,
City Attorney
Contract Template Updated 03/12/2019 clb 07/16/19/69
PAGE 2 OF 2
Exhibit A-2
Friday,July 26,2019
Russ Woodruff
Capital Project Coordinator
Community Services Facilities Division
Renton City Hall,6th Floor
1055 South Grady Way
Renton,WA 98057-3232
Russ,
Thank you for the opportunity to submit this request for professional services for the emergency
generators replacement project at Renton City Hall.These services will cover all design fees, production
of bid documents, bidding,and construction administration for the replacement of two generators
with one generator at the Renton City Hall building in Renton,WA.
Project Scope:
1. Removal of existing chain link fence to allow for access to generator space.
2. Removal of existing(2)generators and supporting equipment.
3. Installation of(1) replacement generator that would replace the load capacity of the original
(2)generators.
4. Installation of supporting equipment.
5. Reuse of existing penetrations in building for adequate venting.
6. Replacement of chainlink fence with stronger fencing that includes man door.
7. Retain location of man door access to enclosure to allow for relief from requirement for
remote fueling station.
Design Team Scope:
1. Services for architectural, mechanical,and electrical design services.
2. Load testing for one panel served by generators.
3. Design and production of draft design documents and an opportunity for Authority Having
Jurisdiction)AHJ to review and recommend revisions.
4. Design and production of final bid documents and an opportunity for Owner review and
revisions.
5. Bidding assistance.
6. Construction administration and close out.
7. Punch list and Final Completion paperwork.
At this time the design team has already invested some efforts to move this project forward,those
amounts are also captured in this proposed.
4000 DELRIDGE WAY SW • SUITE 200 • SEATTLE,WA 98106 • 206/624-2777 • www.stemperac,com
a
Lacking input from AHJ,the design team's code interpretations will guide initial design.Therefore,
any significant changes to project scope required by AHJ will be considered additional services to
the base contract. Further, it is anticipated that existing structure will be able to support one
generator where there was previously two. If additional structural work beyond review of
documents and confirmation of this anticipation are required then those efforts will be considered
additional services to the base contract.
Design Fees:
Our proposed basic services fees total$82,897.
We are very excited to work with you on this project. Please feel free to contact us with any
questions or concerns about this fee proposal.
Thomas Hon
Design Team Project Manager
Stemper Architecture Collaborative
' t..
Project Title: City Hall Emergency Generator Replacement
Fee Proposal For: City of Renton
Date: 7/26/2019
Full design,bidding,construction administration,and close out services
for the replacement of the emergency generators at Renton City Hall.
Scope:
Esimated MACC: TBD
Design and Construction Admin
Architectural Services $38,983
SubConsultant
Mechanical $12,540
Electrical $24,200
Structural $600
SubConsultant Total $37,340
Mark-Up(10%) $3,734
Subtotal $80,057
Reimbursables
Reprographics $200
Load testing $2,640
Reimbursables Sub-total $2,840
Total $82,897
Project Title: City Hall Emergency Generator Replacement
Fee Proposal For: City of Renton
Date: 7/26/2019
Consultant: Stemper Architecture Collaborative
Scope: Full design,bidding,construction administration,and close out services
for the replacement of the emergency generators at Renton City Hall.
Hours Rate Extension
Work Already Completed
Nov 2017-Drawing editing,site visit,coordination 11 $135.00 $1,485
March 2018-Pricing generator and coordination 2.75 $135.00 $371
June 2018-Site visit and coordination 10.25 $135.00 $1,384
Remainder 2018-Drawings,coordination,Cummins rev 19 $135.00 $2,565
March-May 2019-Meeting,coordination and review 5 $135.00 $675
May 2019-Meeting 1.5 $135.00 $203
Subtotal $6,683
75%Design Phase
Kick-off Meeting and site visit 6 $135.00 $810
Materials research 6 $135.00 $810
Design to 75% 10 $135.00 $1,350
Design to 75%-Principal 4 $175.00 $700
Drawings to 75%-(3)24"x36" 18 $135.00 $2,430
Develop cost estimate 4 $135.00 $540
Develop project schedule 2 $135.00 $270
Daily Team Coordination 10 $135.00 $1,350
Full Team QC/QC 2 $135.00 $270
Full Team QC/QC-Principal 3 $175.00 $525
Drawings to AHJ 1 $135.00 $135
75%Specs-Technical 10 $135.00 $1,350
Subtotal $10,540
Construction Documents
CD Drawings(3)24"x36" 18 $135.00 $2,430
Spec Divisions 00&01 2 $135.00 $270
CD Specs-Technical 8 $135.00 $1,080
Submittal for Owner review 1 $135.00 $135
CD review meeting 4 $135.00 $540
Meeting minutes 2 $135.00 $270
Cost Estimate update 2 $135.00 $270
Document Pick-ups 2 $135.00 $270
AHJ coversheet 3 $135.00 $405
Permit Intake Appointments 1 $135.00 $135
Submittal for Owner Contracts Review 1 $135.00 $135
Revisions per comments 2 $135.00 $270
Daily Team Coordination 8 $135.00 $1,080
Subtotal $7,290
Instruction to Bidders
Instruction to Bidders 1 $135.00 $135
Subtotal $135
Print Bid Sets
Plot final set 1 $135.00 $135
Subtotal $135
Pre Bid Conferene
Telecon Meeting and MM 2 $135.00 $270
Subtotal $270
Bidding Questions
Respond to telephone questions 2 $135.00 $270
Respond to telephone questions-Principal Architect 1 $175.00 $175
Provide(1)addenda 2 $135.00 $270
Provide(1)addenda-Principal Architect 1 $135.00 $135
Subtotal $850
Bid Opening
Review bid opening 1 $135.00 $135
Subtotal $135
Pre-Con meeting and Submittal List
Develop submittal list and letter 0 $135.00 $0
Pre-Con meeting w/minutes 2 $135.00 $270
Pre-Con meeting-Principal 0 $135.00 $0
Review project sched.and sched.of values 3 $135,00 $405
Subtotal $675
Construction Meetings
Meetings(4)w/minutes 20 $135.00 $2,700
Meetings(1)-Principal 0 $175.00 $0
Site Visits(2)w/notes 0 $135.00 $0
Site Visits(1)-Principal 0 $175.00 $0
Subtotal $2,700
Construction Coordination
Day-to-day coordination(2hr/week x 8 weeks) 16 $135.00 $2,160
Day-to-day coordination-Principal 0 $175.00 $0
Subtotal $2,160
Review Submittals
Review architectural submittals 6 $135.00 $810
Review architectural submittals-Principal 1 $175.00 $175
Coordinate engineering submittals 2 $135.00 $270
Subtotal $1,255
RFIs
Respond/process RFIs(3) 6 $135.00 $810
Respond/process RFIs-Principal 1 $175.00 $175
Subtotal $985
COPs and Change Orders
Review/process(2)COPs 4 $135.00 $540
Review/process COPs-Principal 1 $175.00 $175
Review/process(1)COs 0 $135.00 $0
Review/process COs-Principal 0 $175.00 $0
Subtotal $715
Contractor Payment Requests
Review Schedule of Values 2 $135.00 $270
Review I process(2)Pay Apps 4 $135.00 $540
Review/process Pay Apps-Principal 0 $175.00 $0
Subtotal $810
Substantial Completion
SC inspection and list 4 $135.00 $540
SC inspection and list-Principal 0 $175.00 $0
Substantial completion form&letter 1 $135.00 $135
Subtotal $675
Final Completion
Punchlist inspection 4 $135.00 $540
Punch list 2 $135.00 $270
Final punchlist inspection-construction 0 $135.00 $0
Final punchlist inspection-warranty period 0 $135.00 $0
Final review-Principal 0 $175.00 $0
Subtotal $810
Final Documentation
O&M review 4 $135.00 $540
As-built coordination 3 $135.00 1 $405
As-built drafting 8 $135.00 $1,080
As-built repro and docs to Owner 1 $135.00 $135
Subtotal $2,160
Architectural Total 285.5 $38,983
a,
Project Title: City Hall Emergency Generator Replacement
Fee Proposal For: City of Renton
Date: 7/26/2019
Consultant: Sazan Group(Mechanical)
Scope: Full design,bidding,construction administration,and close out services
for the replacement of the emergency generators at Renton City Hall.
Task Hours Rate Extension
75%Design
See attached proposal from Sazan $6,280
100%Design
See attached proposal from Sazan $3,370
Construction Administration
See attached proposal from Sazan $2,890
Mechanical Total $12,540
Satan Group,Inc. Renton City Hall Generator Upgrade
600 Stewart Street,Suite 1400 Renton,WA
Seattle,Washington 98101 1055 S.Grady Way
Date: 07/26/19
ENGINEERING FEE CALCULATION-MECHANICAL By: CEM
DESIGN AND CONSTRUCTION ADMINISTRATION
Constriction Documents(751) Mechanical
PRIN. SR. ENGR/SR ACAD ADMIN. TOTAL TASK
TASK ENG. DESN. TECH ASST. HOURS AMOUNT
Field Investigation(1 Site Visit) 4 4 $640
Review record documents 2 2 4 $510
Fuel Piping Design/Drawing Layout 6 10 2 18 $2,060
Controls/Sequence of Operations 3 3 $480
Specifications 6 6 $960
Coordination with AHJ 2 2 $320
Coordination with Generator Manufacturer 1 1 $160
Cost Estimate 2 2 $320
Internal Coordination 2 2 4 $510
Internal QA,QC,PM and Admin. 2 2 $320
Total Electrical Hours: 30 14 2 46 $6,280
Rates: $225 $160 $125 $95 $75
Ca-..ryAmount: $4,800 $1,330 $150 TOTAL: $8,280
Construction Documents/Permit Set(100%) Mechanical
PRIN. SR. SR. ACAD. ADMIN. TOTAL TASK
TASK ENG. DESN. TECH ASST. HOURS AMOUNT
Finalize drawings 2 2 4 $510
Finalize Specifications 2 3 5 $545
Coordination with Others 3 2 5 $670
Design Team Meetings(Assume 1 @ Renton) 4 4 $640
Cost Estimate 1 1 $160
Internal QA,QC,PM and Admin. 1 2 4 7 $845
Total Electrical Hours: 1 14 4 7 26 $3,370
Rates: $225 $160 $125 $95 $75
Ca=: Amount: $225 $2,240 $380 $525 TOTAL: $3,370
Construction Administration Mechanical
PRIN. SR. SR. ACAD. ADMIN. TOTAL TASK
TASK ENG. DESN. TECH ASST. HOURS AMOUNT
Submittal Review 2 1 3 $395
Field Questions and Changes 2 1 3 $395
Phone Meetings/Coordination 3 3 $480
Punchlist and Site Visit 5 5 $800
As-Built Drawings 1 2 1 4 $425
Project Administration and Management 2 1 3 $395
Total Electrical Hours: 15 2 4 21 $2,890
Rates: $225 $160 $125 $95 $75
Ca ;tit Amount: $2,400 $190 $300 TOTAL: $2,890
Mechanical Total Fee $12,540
Project Title: City Hall Emergency Generator Replacement
Fee Proposal For: City of Renton
Date: 7/26/2019
Consultant: Sazan Group(Electrical)
Scope: Full design,bidding,construction administration,and close out services
for the replacement of the emergency generators at Renton City Hall.
Task Hours Rate Extension
75%Design
See attached proposal from Sazan $16,130
100%Design
See attached proposal from Sazan $3,470
Construction Administration
See attached proposal from Sazan $4,600
Electrical Total $24,200
Satan Group,Inc. Renton City Hall Generator Upgrade
600 Stewart Street,Suite 1400 Renton,WA
Seattle,Washington 98101 1055 S.Grady Way
Date:07/26/19
ENGINEERING FEE CALCULATION-ELECTRICAL By.CEM
DESIGN AND CONSTRUCTION ADMINISTRATION
Construction Documents(75%) Electrical
PRIN. SR. ENGR/SR ACAD ADMIN. TOTAL TASK
TASK ENG. DESN. TECH ASST. HOURS AMOUNT
Pre-generator design coordination 15 15 $2,400
Pre-Design Meeting and Site Assessment/Measure-up 4 4 $640
Generator size confirmation and calculations 2 2 $320
Layout/Dimensional coordination 2 2 4 $510
Coordination with generator manufacturer 4 4 $640
Record Documents Review 2 2 $320
Revise existing one-line to single generator 3 4 7 $860
Demolition Drawings 6 8 14 $1,720
Panel S Metering-Review/Interpretation/Coordination 3 1 4 $555
Engineering/Plan and Layout Drawings 8 8 16 $2,040
Panel Schedules.Load Calm,Fault Current Calculations 6 8 14 $1,720
Cost Estimate(ROM) 3 3 $480
Specification 10 10 $1,600
Miscellaneous Code Assessments 3 3 $480
Coordination with AHJ 2 2 $320
Cost Estimate 2 2 $320
Internal QA,QC,PM and Admin. 1 4 2 2 9 $1,205
Total Electrical Hours: 1 79 32 3 115 $18,130
Rates: $225 $160 $125 $95 $75
Ca:%Li Amount $225 $12,640 $3,040 $225 TOTAL: $16,130
Construction Documents/Pennit Set(100%) Electrical
PRIN. SR. SR. ACAD. ADMIN. TOTAL TASK
TASK ENG. DESN. TECH ASST. HOURS AMOUNT
Finalize drawings 2 4 6 $700
Finalize Specifications 2 2 4 $510
Coordination with Others 4 2 6 $830
Cost Estimate 2 2 $320
Design Team Meetings(Assume 1 n@ Renton) 4 4 $640
Internal QA,QC,PM and Admin. 2 2 4 $470
Total Electrical Hours: 16 8 2 $3,470
Rates: $225 $160 $125 $95 $75
Ca: Amount $2,560 $760 $150 TOTAL: $3,470
Construction Administration Electrical
PRIN. SR. SR. ACAD. ADMIN. TOTAL TASK
TASK ENG. DESN. TECH ASST. HOURS AMOUNT
Submittal Review 1 3 1 5 $610
Field Questions and Changes 1 3 1 5 $610
Phone Meetings/Coordination 3 3 $480
Punc hlist and Site Visit 5 5 $800
As-Built Drawings 1 2 1 4 $125
Project Administration and Management 10 1 11 $1,675
Total Electrical Hours: 21 6 2 4 33 $4,600
Rates: $225 $160 $125 $95 $75
Ca,-'. Amount $3,360 $750 $190 $300 TOTAL: $4,600
Electrical Total Fee S24,200
v *.. .,
Project Title: City Hall Emergency Generator Replacement
Fee Proposal For: City of Renton
Date: 7/26/2019
Consultant: Peterson Strehle Martinson(Structural)
Scope: Review of existng deck for capacity to carry generator loads.
Task Hours Rate Extension
75%Design
See attached proposal from Sazan $600
Structural Total 0 $600
November 15,2018
Thomas Horton
S.M. Stemper Architects
RE: Structural Engineering Fee Proposal
Renton City Hall Elevator Modernization Check Slab for New Generator
Dear Thomas:
As you requested,we are sending you a fee proposal for the above referenced project.
SCOPE: Structural Engineering Review of the capacity of an existing slab for a new generator,
which replaces an earlier installation.
FEES: We propose to complete this work on a fixed fee basis for$600.
TERMS AND CONDITIONS:
II ft
Please-review-this-proposal-and,if a eat ta-yoursign--be10 ---Thank you far
asking project:-Please-call--ify .
Sincerely, Accepted-by;.
Peterson Strehle Martinson,Inc. S.MrStemper-Architects
v ) Cr
") I VAk," a t/j.a
11/15/18
Ronald E.Martinson,P.E.,S.E. Date Date
President