CITY OF RENTON STREET LIGHT-LUMINAIRE CHECKLIST
Inspection 5: Following initial and final inspection, electrical contractor is required to submit application
to PSE to energize the street lighting. PSE application (201E) may be found at the following
website: https://pse.com/accountsandservices/Construction/CCS%20Forms/1378_201E.pdf
Inspection 6: Typical inspection items reviewed during Maintenance Inspection: conductor size,
insulation, type; electrical service panel (including address); grounding and connections;
wire/splices/fuses; fixture and associated parts; poles and plumb/nut covers; decorative pad
around vault; street lighting pole locations; pole numbers; and check for damage. Meg reading
may be required.
Last Modified: 3/15/2024
CONTACT: PHONE: EMAIL:
INSPECTOR NAMES: const/elect/maintenance
/ /
ELECTRICAL CONTRACTORS NAME:
PROJECT NAME(s): DATE OF INSPECTION COMPLETION:
LOCATION:
NOTE TO CONTRACTOR: Check to ensure the following is installed as outlined in WSDOT Standard Specifications Section 8 &
9 or as amended by the Renton Standard details and is installed per the approved plans.
Construction Inspection Checklist
Lighting Contractor call 425-430-7203 for inspections 1-4
Date of
Inspection:
Initials of
Inspector
If Accepted
CONSTRUCTION PERMIT#
COMMENTS
1. Pole Foundations
2. Base Bolts
3. Cabinet foundation and Type
4. Underground/Rough-In Inspection:
Junction Box/Conduit Size, Type, Burial
Electrical Construction Inspection Checklist
Lighting Contractor call 425-430-7202 for inspections 5
Date of
Inspection:
Initials of
Inspector
If Accepted
ELECTRICAL PERMIT#
COMMENTS
5. Service Inspection: Confirm electrical
system conforms with Electrical Code prior
to being energized. (See contractor
requirements for energizing system.)
Transportation Maintenance Inspection Checklist
Lighting Contractor call 425-430-7423 for inspection 6
Date of
Inspection:
Initials of
Inspector
If Accepted
CONSTRUCTION PERMIT#
COMMENTS
6. Street Lighting Inspection for Project by
City Maintenance confirming standard
details and plans have been met prior to
energizing (see list below for typical
inspection items).
7. Final Inspection:
Final Street Lighting Inspection for Project
by City Maintenance once street lighting
has been energized.